INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)最新文献

筛选
英文 中文
COST AND TIME ANALYSIS USING EARNED VALUE METHOD ON THE CONSTRUCTION OF THE NATIONAL KEDIRI AIRPORT ACCESS ROAD PHASE 1 KEDIRI - NGANJUK 采用挣值法对基迪里国家机场通道第一阶段基迪里--楠竹路段的施工进行成本和时间分析
Ichsan Yanuansyah Pramadha, H. T. Tjendani, Budi Witjaksana
{"title":"COST AND TIME ANALYSIS USING EARNED VALUE METHOD ON THE CONSTRUCTION OF THE NATIONAL KEDIRI AIRPORT ACCESS ROAD PHASE 1 KEDIRI - NGANJUK","authors":"Ichsan Yanuansyah Pramadha, H. T. Tjendani, Budi Witjaksana","doi":"10.55047/ijateis.v3i1.1023","DOIUrl":"https://doi.org/10.55047/ijateis.v3i1.1023","url":null,"abstract":"Project completion delays have adverse consequences on a contractor's credibility and result in additional penalty costs, reducing potential profits. To mitigate these issues and optimize project outcomes, refining activity schedules and budgets is crucial. The Earned Value Method proves effective in monitoring and controlling project activities. In the case of the Kediri airport access road construction project, weeks 1 to 6 revealed a negative Cost Variance (CV), indicating higher-than-planned costs, while weeks 7 to 8 showed a positive CV, suggesting costs were lower than anticipated. Schedule Variance (SV) for the 1st week was unfavorable, indicating a delay, and SV>1 from weeks 2 to 8 signaled a project delay. The Estimate to Complete (ETC) is IDR 17,470,510,292.77, and the Estimate at Complete (EAC) is IDR 32,509,153,464.05. The Time Estimate (TE) forecasts project completion in 89 calendar days, five days beyond the contracted 84 days. Employing the Earned Value Method enhances project performance evaluation and decision-making to avoid delays and cost overruns.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"412 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140502913","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
ANALYSIS OF IMPLEMENTATION DELAYS USING THE EARNED VALUE METHOD (ON THE PURWOSARI - SEKARMOJO ROAD WORKS, PASURUAN DISTRICT) 利用挣值法分析实施延误(关于帕苏鲁安县 Purwosari - Sekarmojo 公路工程)
Pandji Thoha S. Balido, H. T. Tjendani, Budi Witjaksana
{"title":"ANALYSIS OF IMPLEMENTATION DELAYS USING THE EARNED VALUE METHOD (ON THE PURWOSARI - SEKARMOJO ROAD WORKS, PASURUAN DISTRICT)","authors":"Pandji Thoha S. Balido, H. T. Tjendani, Budi Witjaksana","doi":"10.55047/ijateis.v3i1.1022","DOIUrl":"https://doi.org/10.55047/ijateis.v3i1.1022","url":null,"abstract":"Along with the very rapid development of infrastructure and construction in Indonesia in the era of globalization, the Indonesian government has carried out various large-scale projects to achieve the increasingly complex expectations of society. This will trigger the growth of the construction industry in Indonesia and become one of the main goals in the framework of national development. An infrastructure development project is an activity carried out with limited time and resources to achieve a specified final result. One of the construction projects currently being developed is Road Works. The Earned Value method can be used to determine cost performance and implementation time during the project and the indicators used for analysis include: BCWP (Budget Cost of Work Performance), BCWS (Budget Cost of Work Schedule), ACWP (Actual Cost of Work Performance), SV (Schedule Variance), CV (Cost Variance), SPI (Schedule Performance Index), CPI (Cost Performance Index), EAC (Estimated At Complete) and ET (Estimated To Complete) and TE (Time Estimate). Conclusions from this research is to determine the estimated costs and time for project completion. In the data analysis in the 9th week, the project schedule performance (CPI) was 1.14, greater than 1, while (SPI) was 0.587, less than 1. The results of the calculation of projected costs for the remaining work (ETC) were IDR. 1,586,686,537.62 and total project costs (EAC) of Rp. 2,509,041,243.08.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"74 4","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140503286","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
OPTIMIZATION OF INTERSECTION PERFORMANCE AND VEHICLE TRAFFIC FLOW AT INTERSECTION FOUR DHOHO PLAZA KEDIRI CITY USING MKJI METHOD 1997 用 MKJI 方法优化吉打里市 DHOHO 广场 4 号交叉口的交叉性能和车辆流量 1997 年
E. F. Hidiyati, Laksono Djoko Nugroho, Haris Muhammadun
{"title":"OPTIMIZATION OF INTERSECTION PERFORMANCE AND VEHICLE TRAFFIC FLOW AT INTERSECTION FOUR DHOHO PLAZA KEDIRI CITY USING MKJI METHOD 1997","authors":"E. F. Hidiyati, Laksono Djoko Nugroho, Haris Muhammadun","doi":"10.55047/ijateis.v3i1.990","DOIUrl":"https://doi.org/10.55047/ijateis.v3i1.990","url":null,"abstract":"Kediri is the third largest city in East Java after Surabaya and Malang with a population growth of 289,418 people in 2023. The International Airport will open at the end of 2023 in Kediri. However, rapid population growth has also led to an increase in mobility and the number of motorized vehicles on the streets of Kediri City, including at the research site in Dhoho Plaza. The analysis of the signaled intersection was carried out using the MKJI 1997 method, and Visual PTV Vissim for three days on Monday, Friday, and Sunday. Based on the results of the analysis, a cycle time of 90.7 was obtained which affected saturation in each arm of the intersection. There is a potential reduction in signal light waiting time from 135 seconds to 118 seconds by repairing side obstacles. The solution to overcome side obstacles is to improve facilities such as traffic lights and adjust the timing of signal lights. The change in the value of side barriers also has a significant impact on waiting times, queues, and fuel costs at the intersection of Pasar Pahing, with congestion cost efficiency reaching Rp. 22,679,183 in the next 5 years.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"407 2","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140502750","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
COST AND TIME ANALYSIS USING EARNED VALUE METHOD BUILDING CONSTRUCTION OF DISTANCE LEARNING PROGRAM UNITS OF SURABAYA OPEN UNIVERSITY PHASE II 利用挣值法对泗水开放大学远程教育项目第二阶段的建设进行成本和时间分析
Mochamad Ranoe Asmoro, Budi Witjaksana, H. T. Tjendani
{"title":"COST AND TIME ANALYSIS USING EARNED VALUE METHOD BUILDING CONSTRUCTION OF DISTANCE LEARNING PROGRAM UNITS OF SURABAYA OPEN UNIVERSITY PHASE II","authors":"Mochamad Ranoe Asmoro, Budi Witjaksana, H. T. Tjendani","doi":"10.55047/ijateis.v3i1.1020","DOIUrl":"https://doi.org/10.55047/ijateis.v3i1.1020","url":null,"abstract":"Project delays often serve as a catalyst for conflicts and disagreements between project owners and contractors, leading to significant financial implications. Such delays result in costly consequences for both parties involved. Contractors face the imposition of penalty fines as stipulated in the contractual agreement, alongside incurring overhead costs during the prolonged project duration. Conversely, owners experience a direct impact on their revenue streams due to delays in the operationalization of the facility. In the context of the construction of the Surabaya Open University Distance Learning Program Unit building phase II, the examination of cost and time performance becomes imperative. Employing the earned value method offers a comprehensive approach to project performance evaluation, involving a meticulous comparison of actual expenses and timelines with the initially anticipated costs. This analytical approach aids in understanding the project's progress and identifying areas where adjustments may be necessary to mitigate potential delays. The Earned Value Method (EVM) analysis of the Surabaya Open University Distance Learning Program Unit building phase II reveals a projected total cost of IDR 73,908,443,223.09 by the time the project reaches completion. This estimation provides stakeholders with valuable insights into the financial commitment required for the successful conclusion of the project. Additionally, the anticipated timeline for completion is estimated at 53 weeks, serving as a crucial parameter for project planning and management.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"406 1","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140502922","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
TIME AND COST ACCELERATION ANALYSIS USING CRASHING METHOD (CASE STUDY: TANJUNG UNCANG JETTY CONSTRUCTION PROJECT BATAM CITY) 采用碰撞法进行时间和成本加速分析(案例研究:巴淡省丹戎羌码头建设项目)
Harisa Ramadhani Putra, K. Koespiadi, W. Oetomo
{"title":"TIME AND COST ACCELERATION ANALYSIS USING CRASHING METHOD (CASE STUDY: TANJUNG UNCANG JETTY CONSTRUCTION PROJECT BATAM CITY)","authors":"Harisa Ramadhani Putra, K. Koespiadi, W. Oetomo","doi":"10.55047/ijateis.v3i1.1018","DOIUrl":"https://doi.org/10.55047/ijateis.v3i1.1018","url":null,"abstract":"Contractors involved in construction projects face the crucial challenge of effectively managing time to ensure the timely completion of the project as stipulated in the contract, if not earlier. Efficient time management not only facilitates adherence to contractual obligations but also transforms incurred costs into profitable outcomes, thereby preventing financial penalties associated with project delays. Consequently, the strategic implementation of acceleration efforts emerges as a pivotal solution to address and mitigate the complexities inherent in construction project timelines. The acceleration process is intricately tied to the identification and prioritization of critical activities within the project schedule. By employing a comprehensive approach that integrates both cost and time analyses, the Crashing method with additional modifications emerges as a valuable tool in this endeavor. The Crashing method involves a strategic acceleration of critical activities, coupled with a meticulous calculation of the additional costs incurred due to the acceleration process. A compelling case study that exemplifies the efficacy of the Crashing method and its supplementary measure of alternative overtime work is evident in the Tanjung Uncang Pier construction project in Batam City. Through the meticulous application of the Crashing method and the incorporation of alternative overtime work, the project's completion timeline was successfully curtailed from the originally delayed schedule of 257 calendar days to a more expedited 244 calendar days.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"64 8","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140503110","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
TECHNICAL AND COST ANALYSIS OF FLOOD CONTROL PLANNING USING THE ECODRAINS-BASED SPONGE VILLAGE MODEL IN THE KAMONING SAMPANG WATERSHED 利用基于生态排水系统的海绵村庄模式对卡莫宁桑邦流域的防洪规划进行技术和成本分析
Zaiful Muqaddas, Budi Witjaksanahanie, H. T. Tjendani
{"title":"TECHNICAL AND COST ANALYSIS OF FLOOD CONTROL PLANNING USING THE ECODRAINS-BASED SPONGE VILLAGE MODEL IN THE KAMONING SAMPANG WATERSHED","authors":"Zaiful Muqaddas, Budi Witjaksanahanie, H. T. Tjendani","doi":"10.55047/ijateis.v3i1.1021","DOIUrl":"https://doi.org/10.55047/ijateis.v3i1.1021","url":null,"abstract":"The Kali Kamoning Watershed in Sampang Regency, spanning 35,421.15 Ha, experiences annual major floods affecting Sampang City. Despite various attempts and budget allocations at different administrative levels, flooding remains a persistent issue. A proposed solution is the implementation of an Ecodrains-based sponge village model for flood control, specifically targeting upstream areas like Karang Penang, Robatal, Kedungdung, Omben, and Sampang sub-districts. The model, cost-effective and easy to construct, utilizes the HEC-HMS software for technical analysis, simulating river capacity and calculating flood reduction. The sponge village model demonstrates a substantial reduction of flooding by 73.14%, equivalent to 326.3 m3/sec. The Q25th flood discharge measures 446.1 m3/sec. Estimated construction costs using the SNI method amount to IDR 917,588,260,000, aiming to control the Q25th flood. This innovative approach offers a promising strategy for mitigating flooding in Sampang City through sustainable watershed management and cost-efficient infrastructure development. Key terms: Watershed, Flood Reduction, Ecodrains, Sponge Village Model, HEC-HMS, Q25th, Construction Costs.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"9 4","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140502889","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
ANALYSIS OF PIPE NETWORK OPTIMIZATION FOR RAW WATER IN JABUNG SUB-DISTRICT, MALANG DISTRICT 马朗县贾榜分区原水管网优化分析
Putut Subandriyo, Laksono Djoko Nugroho, Haris Muhammadun
{"title":"ANALYSIS OF PIPE NETWORK OPTIMIZATION FOR RAW WATER IN JABUNG SUB-DISTRICT, MALANG DISTRICT","authors":"Putut Subandriyo, Laksono Djoko Nugroho, Haris Muhammadun","doi":"10.55047/ijateis.v2i3.1053","DOIUrl":"https://doi.org/10.55047/ijateis.v2i3.1053","url":null,"abstract":"Jabung District is a sub-district located in the Malang Regency area of 135.89 km2 or around 4.56 percent of the total area of Malang Regency. This sub-district consists of 15 villages, including Argosari, Gadingkembar, Gunungjati, Jabung, Kemantren, Kemiri, Kenongo, Ngadirejo, Pandansari Lor, Sidomulyo, Sidorejo, Slamparejo, Sukolilo, Sukopuro, and Taji. With a population of 74,311 people in 2020, with a population density of 592 people/km2. In Jabung District, especially in 4 villages, including Pandansari Lor Village, Gading Kembar Village, Argosari Village, and Kemiri Village, there is currently a water shortage. Siuk Source Potential has water potential large enough to meet the standard needs in these 4 villages by gravity. From the results of instantaneous discharge measurements during the dry season in 2021, it can be seen that the discharge in Sumber Siuk is 65 l/sec, and the planned collection to fulfill these 4 villages is 20 l/sec. Construction of the broncaptering and raw water distribution network was built in 3 stages. Before the physical implementation of the installation of distribution pipes in stage 3, a trial run was carried out from stage 1 and stage 2.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"56 5-6","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140505410","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
PERFORMANCE ANALYSIS OF SUPERVISORY CONSULTANTS ON PROJECTS IN THE HOUSING AND SETTLEMENT AREAS OF EAST JAVA PROVINCE 东爪哇省住房和安置区项目监理顾问的绩效分析
Deni Rahadian, K. Koespiadi, W. Oetomo
{"title":"PERFORMANCE ANALYSIS OF SUPERVISORY CONSULTANTS ON PROJECTS IN THE HOUSING AND SETTLEMENT AREAS OF EAST JAVA PROVINCE","authors":"Deni Rahadian, K. Koespiadi, W. Oetomo","doi":"10.55047/ijateis.v2i3.1015","DOIUrl":"https://doi.org/10.55047/ijateis.v2i3.1015","url":null,"abstract":"The Supervisory Consultant is the party assigned by the project owner to realize the planned planning results according to the development of good settlement infrastructure facilities and utilities. The government, especially in the PRKP Division of East Java Province, collaborates with service providers, one of which is a supervisory consultant, in this case encouraging supervisory consultants to increase understanding of customer satisfaction. This research has several objectives, namely identifying variables of project management performance of PRKP activities in East Java Province; measuring the level of customer satisfaction from the project management performance of PRKP activities in East Java Province. The research stages taken in this study, namely Research background, Formulation of problems and research objectives, Literature study, Preliminary survey, Data collection, Data testing, Data analysis. The analysis method used is the customer satisfaction index method. The data is processed using the MS.Excel and SPSS programs. The results of the analysis with the customer satisfaction index show a CSI value of 63.55% which means satisfied. which is low and needs to be improved.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"109 4","pages":""},"PeriodicalIF":0.0,"publicationDate":"2024-01-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"140504970","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
PROJECT SCHEDULING ANALYSIS USING THE CRITICAL PATH METHOD – CASE STUDY: SUBSIDIZED HOUSE CONSTRUCTION PROJECT IN HILL MULYA HOUSING, SAMARINDA CITY 关键路径法的项目进度分析——以萨玛林达市山木雅住宅保障性住房建设项目为例
Gilang Ramadhan Rakasyiwi, Budi Witjaksana, H. T. Tjendani
{"title":"PROJECT SCHEDULING ANALYSIS USING THE CRITICAL PATH METHOD – CASE STUDY: SUBSIDIZED HOUSE CONSTRUCTION PROJECT IN HILL MULYA HOUSING, SAMARINDA CITY","authors":"Gilang Ramadhan Rakasyiwi, Budi Witjaksana, H. T. Tjendani","doi":"10.55047/ijateis.v1i4.480","DOIUrl":"https://doi.org/10.55047/ijateis.v1i4.480","url":null,"abstract":"Samarinda City has a total of 123 housing estates with 20 subsidized housing (MBR) and 4 mixed housing. Project scheduling in construction greatly determines the project's success because it is a benchmark that the project is successful within the allotted time. CPM (Critical Path Method). CPM is a method that introduces an element of project time by using a predefined activity time estimate. This method is used for crushing the Bukit Mulya housing project, which only applies to the implementation of crash time. From the analysis results, the initial scheduling time, which was originally 87 days, was trimmed by 9 days using CPM, the optimal time was 78 days.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"393 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-12-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"130839326","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
IMPROVEMENT OF SOME SOIL CHEMICAL PROPERTIES ON MARGINAL LANDS TO INCREASE CORN PRODUCTION THROUGH CONSERVATION TILLAGE TECHNIQUES AND ORGANIC FERTILIZERS 利用保护性耕作技术和有机肥改善边缘土地部分土壤化学性质以提高玉米产量
David Kusairi, Sunarti, Aswandi
{"title":"IMPROVEMENT OF SOME SOIL CHEMICAL PROPERTIES ON MARGINAL LANDS TO INCREASE CORN PRODUCTION THROUGH CONSERVATION TILLAGE TECHNIQUES AND ORGANIC FERTILIZERS","authors":"David Kusairi, Sunarti, Aswandi","doi":"10.55047/ijateis.v1i4.483","DOIUrl":"https://doi.org/10.55047/ijateis.v1i4.483","url":null,"abstract":"This study aims to analyze the effect of applying conservation tillage techniques and a combination of organic and inorganic fertilizers on soil chemical properties on marginal land and maize production. This research was conducted in Jambi Outer City District, Muaro Jambi Regency, Jambi Province, from January to April 2021 using a randomized block design with 15 treatments and 3 replications. Parameters observed were corn plant height at the age of 15 DAP, 30 DAP and 45 DAP, weight of corn cobs, weight of dry shelled corn seeds, Soil pH, Soil C-Organic Content, Soil Nitrogen Content, Soil Phosphorus Content, Soil Potassium Content, Cation Exchange Capacity, Base Saturation. The results showed that the application of conservation tillage techniques and a combination of organic and inorganic fertilizers had a significant effect on corn plant height 45 DAP, corn cob weight, soil pH, C-Organic Soil, Soil Phosphorus Content, Soil Potassium Content, Cation Exchange Capacity.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"33 1","pages":"0"},"PeriodicalIF":0.0,"publicationDate":"2022-12-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":null,"resultStr":null,"platform":"Semanticscholar","paperid":"116989430","PeriodicalName":null,"FirstCategoryId":null,"ListUrlMain":null,"RegionNum":0,"RegionCategory":"","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":"","EPubDate":null,"PubModel":null,"JCR":null,"JCRName":null,"Score":null,"Total":0}
引用次数: 0
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
相关产品
×
本文献相关产品
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信