COST AND TIME ANALYSIS USING EARNED VALUE METHOD BUILDING CONSTRUCTION OF DISTANCE LEARNING PROGRAM UNITS OF SURABAYA OPEN UNIVERSITY PHASE II

Mochamad Ranoe Asmoro, Budi Witjaksana, H. T. Tjendani
{"title":"COST AND TIME ANALYSIS USING EARNED VALUE METHOD BUILDING CONSTRUCTION OF DISTANCE LEARNING PROGRAM UNITS OF SURABAYA OPEN UNIVERSITY PHASE II","authors":"Mochamad Ranoe Asmoro, Budi Witjaksana, H. T. Tjendani","doi":"10.55047/ijateis.v3i1.1020","DOIUrl":null,"url":null,"abstract":"Project delays often serve as a catalyst for conflicts and disagreements between project owners and contractors, leading to significant financial implications. Such delays result in costly consequences for both parties involved. Contractors face the imposition of penalty fines as stipulated in the contractual agreement, alongside incurring overhead costs during the prolonged project duration. Conversely, owners experience a direct impact on their revenue streams due to delays in the operationalization of the facility. In the context of the construction of the Surabaya Open University Distance Learning Program Unit building phase II, the examination of cost and time performance becomes imperative. Employing the earned value method offers a comprehensive approach to project performance evaluation, involving a meticulous comparison of actual expenses and timelines with the initially anticipated costs. This analytical approach aids in understanding the project's progress and identifying areas where adjustments may be necessary to mitigate potential delays. The Earned Value Method (EVM) analysis of the Surabaya Open University Distance Learning Program Unit building phase II reveals a projected total cost of IDR 73,908,443,223.09 by the time the project reaches completion. This estimation provides stakeholders with valuable insights into the financial commitment required for the successful conclusion of the project. Additionally, the anticipated timeline for completion is estimated at 53 weeks, serving as a crucial parameter for project planning and management.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"406 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.55047/ijateis.v3i1.1020","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Project delays often serve as a catalyst for conflicts and disagreements between project owners and contractors, leading to significant financial implications. Such delays result in costly consequences for both parties involved. Contractors face the imposition of penalty fines as stipulated in the contractual agreement, alongside incurring overhead costs during the prolonged project duration. Conversely, owners experience a direct impact on their revenue streams due to delays in the operationalization of the facility. In the context of the construction of the Surabaya Open University Distance Learning Program Unit building phase II, the examination of cost and time performance becomes imperative. Employing the earned value method offers a comprehensive approach to project performance evaluation, involving a meticulous comparison of actual expenses and timelines with the initially anticipated costs. This analytical approach aids in understanding the project's progress and identifying areas where adjustments may be necessary to mitigate potential delays. The Earned Value Method (EVM) analysis of the Surabaya Open University Distance Learning Program Unit building phase II reveals a projected total cost of IDR 73,908,443,223.09 by the time the project reaches completion. This estimation provides stakeholders with valuable insights into the financial commitment required for the successful conclusion of the project. Additionally, the anticipated timeline for completion is estimated at 53 weeks, serving as a crucial parameter for project planning and management.
利用挣值法对泗水开放大学远程教育项目第二阶段的建设进行成本和时间分析
项目延误往往是项目业主和承包商之间冲突和分歧的催化剂,导致重大的财务影响。这种延误会给当事双方带来代价高昂的后果。承包商会面临合同协议中规定的罚款处罚,还会在项目工期延长期间产生间接费用。相反,业主则会因设施运营的延误而直接影响其收入来源。在泗水开放大学远程教育项目大楼二期工程的施工过程中,对成本和时间绩效的检查势在必行。采用挣值法提供了一种全面的项目绩效评估方法,包括将实际支出和时间与最初预计的成本进行细致比较。这种分析方法有助于了解项目的进展情况,并找出可能需要调整的地方,以减少潜在的延误。对泗水开放大学远程教育项目单元楼二期工程的挣值法(EVM)分析显示,到项目竣工时,预计总成本为 73,908,443,223.09 印尼盾。这一估算为利益相关者提供了宝贵的信息,使其了解成功完成项目所需的资金投入。此外,预计完工时间估计为 53 周,这是项目规划和管理的一个重要参数。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信