COST AND TIME ANALYSIS USING EARNED VALUE METHOD ON THE CONSTRUCTION OF THE NATIONAL KEDIRI AIRPORT ACCESS ROAD PHASE 1 KEDIRI - NGANJUK

Ichsan Yanuansyah Pramadha, H. T. Tjendani, Budi Witjaksana
{"title":"COST AND TIME ANALYSIS USING EARNED VALUE METHOD ON THE CONSTRUCTION OF THE NATIONAL KEDIRI AIRPORT ACCESS ROAD PHASE 1 KEDIRI - NGANJUK","authors":"Ichsan Yanuansyah Pramadha, H. T. Tjendani, Budi Witjaksana","doi":"10.55047/ijateis.v3i1.1023","DOIUrl":null,"url":null,"abstract":"Project completion delays have adverse consequences on a contractor's credibility and result in additional penalty costs, reducing potential profits. To mitigate these issues and optimize project outcomes, refining activity schedules and budgets is crucial. The Earned Value Method proves effective in monitoring and controlling project activities. In the case of the Kediri airport access road construction project, weeks 1 to 6 revealed a negative Cost Variance (CV), indicating higher-than-planned costs, while weeks 7 to 8 showed a positive CV, suggesting costs were lower than anticipated. Schedule Variance (SV) for the 1st week was unfavorable, indicating a delay, and SV>1 from weeks 2 to 8 signaled a project delay. The Estimate to Complete (ETC) is IDR 17,470,510,292.77, and the Estimate at Complete (EAC) is IDR 32,509,153,464.05. The Time Estimate (TE) forecasts project completion in 89 calendar days, five days beyond the contracted 84 days. Employing the Earned Value Method enhances project performance evaluation and decision-making to avoid delays and cost overruns.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"412 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.55047/ijateis.v3i1.1023","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Project completion delays have adverse consequences on a contractor's credibility and result in additional penalty costs, reducing potential profits. To mitigate these issues and optimize project outcomes, refining activity schedules and budgets is crucial. The Earned Value Method proves effective in monitoring and controlling project activities. In the case of the Kediri airport access road construction project, weeks 1 to 6 revealed a negative Cost Variance (CV), indicating higher-than-planned costs, while weeks 7 to 8 showed a positive CV, suggesting costs were lower than anticipated. Schedule Variance (SV) for the 1st week was unfavorable, indicating a delay, and SV>1 from weeks 2 to 8 signaled a project delay. The Estimate to Complete (ETC) is IDR 17,470,510,292.77, and the Estimate at Complete (EAC) is IDR 32,509,153,464.05. The Time Estimate (TE) forecasts project completion in 89 calendar days, five days beyond the contracted 84 days. Employing the Earned Value Method enhances project performance evaluation and decision-making to avoid delays and cost overruns.
采用挣值法对基迪里国家机场通道第一阶段基迪里--楠竹路段的施工进行成本和时间分析
项目完工延迟会对承包商的信誉造成不利影响,并导致额外的罚款成本,降低潜在利润。为了减少这些问题并优化项目成果,完善活动计划和预算至关重要。实践证明,挣值法可以有效监控项目活动。在基迪里机场通路建设项目中,第 1 至 6 周的成本差异(CV)为负值,表明成本高于计划,而第 7 至 8 周的成本差异(CV)为正值,表明成本低于预期。第 1 周的进度差异(SV)为负值,表明项目延迟,第 2 至第 8 周的进度差异(SV)大于 1,表明项目延迟。完工估算(ETC)为 17,470,510,292.77 印尼盾,完工估算(EAC)为 32,509,153,464.05 印尼盾。时间估算(TE)预测项目将在 89 个日历日内完成,比合同规定的 84 天超出 5 天。采用挣值法可以加强项目绩效评估和决策,避免延误和成本超支。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信