利用挣值法分析实施延误(关于帕苏鲁安县 Purwosari - Sekarmojo 公路工程)

Pandji Thoha S. Balido, H. T. Tjendani, Budi Witjaksana
{"title":"利用挣值法分析实施延误(关于帕苏鲁安县 Purwosari - Sekarmojo 公路工程)","authors":"Pandji Thoha S. Balido, H. T. Tjendani, Budi Witjaksana","doi":"10.55047/ijateis.v3i1.1022","DOIUrl":null,"url":null,"abstract":"Along with the very rapid development of infrastructure and construction in Indonesia in the era of globalization, the Indonesian government has carried out various large-scale projects to achieve the increasingly complex expectations of society. This will trigger the growth of the construction industry in Indonesia and become one of the main goals in the framework of national development. An infrastructure development project is an activity carried out with limited time and resources to achieve a specified final result. One of the construction projects currently being developed is Road Works. The Earned Value method can be used to determine cost performance and implementation time during the project and the indicators used for analysis include: BCWP (Budget Cost of Work Performance), BCWS (Budget Cost of Work Schedule), ACWP (Actual Cost of Work Performance), SV (Schedule Variance), CV (Cost Variance), SPI (Schedule Performance Index), CPI (Cost Performance Index), EAC (Estimated At Complete) and ET (Estimated To Complete) and TE (Time Estimate). Conclusions from this research is to determine the estimated costs and time for project completion. In the data analysis in the 9th week, the project schedule performance (CPI) was 1.14, greater than 1, while (SPI) was 0.587, less than 1. The results of the calculation of projected costs for the remaining work (ETC) were IDR. 1,586,686,537.62 and total project costs (EAC) of Rp. 2,509,041,243.08.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"74 4","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ANALYSIS OF IMPLEMENTATION DELAYS USING THE EARNED VALUE METHOD (ON THE PURWOSARI - SEKARMOJO ROAD WORKS, PASURUAN DISTRICT)\",\"authors\":\"Pandji Thoha S. Balido, H. T. Tjendani, Budi Witjaksana\",\"doi\":\"10.55047/ijateis.v3i1.1022\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Along with the very rapid development of infrastructure and construction in Indonesia in the era of globalization, the Indonesian government has carried out various large-scale projects to achieve the increasingly complex expectations of society. This will trigger the growth of the construction industry in Indonesia and become one of the main goals in the framework of national development. An infrastructure development project is an activity carried out with limited time and resources to achieve a specified final result. One of the construction projects currently being developed is Road Works. The Earned Value method can be used to determine cost performance and implementation time during the project and the indicators used for analysis include: BCWP (Budget Cost of Work Performance), BCWS (Budget Cost of Work Schedule), ACWP (Actual Cost of Work Performance), SV (Schedule Variance), CV (Cost Variance), SPI (Schedule Performance Index), CPI (Cost Performance Index), EAC (Estimated At Complete) and ET (Estimated To Complete) and TE (Time Estimate). Conclusions from this research is to determine the estimated costs and time for project completion. In the data analysis in the 9th week, the project schedule performance (CPI) was 1.14, greater than 1, while (SPI) was 0.587, less than 1. The results of the calculation of projected costs for the remaining work (ETC) were IDR. 1,586,686,537.62 and total project costs (EAC) of Rp. 2,509,041,243.08.\",\"PeriodicalId\":188915,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"74 4\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v3i1.1022\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.55047/ijateis.v3i1.1022","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

随着全球化时代印尼基础设施和建筑业的飞速发展,印尼政府实施了各种大型项目,以实现社会日益复杂的期望。这将引发印尼建筑业的增长,并成为国家发展框架中的主要目标之一。基础设施开发项目是指在有限的时间和资源范围内为实现特定的最终结果而开展的活动。目前正在开发的建筑项目之一是道路工程。挣值法可用于确定项目期间的成本绩效和实施时间,用于分析的指标包括分析指标包括:BCWP(工作绩效预算成本)、BCWS(工作进度预算成本)、ACWP(工作绩效实际成本)、SV(进度差异)、CV(成本差异)、SPI(进度绩效指数)、CPI(成本绩效指数)、EAC(完工估算)和 ET(完工估算)以及 TE(时间估算)。本研究的结论是确定项目完成的估计成本和时间。在第 9 周的数据分析中,项目进度绩效(CPI)为 1.14,大于 1,而(SPI)为 0.587,小于 1。1,586,686,537.62 印尼盾,项目总成本(EAC)为 2,509,041,243.08 印尼盾。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
ANALYSIS OF IMPLEMENTATION DELAYS USING THE EARNED VALUE METHOD (ON THE PURWOSARI - SEKARMOJO ROAD WORKS, PASURUAN DISTRICT)
Along with the very rapid development of infrastructure and construction in Indonesia in the era of globalization, the Indonesian government has carried out various large-scale projects to achieve the increasingly complex expectations of society. This will trigger the growth of the construction industry in Indonesia and become one of the main goals in the framework of national development. An infrastructure development project is an activity carried out with limited time and resources to achieve a specified final result. One of the construction projects currently being developed is Road Works. The Earned Value method can be used to determine cost performance and implementation time during the project and the indicators used for analysis include: BCWP (Budget Cost of Work Performance), BCWS (Budget Cost of Work Schedule), ACWP (Actual Cost of Work Performance), SV (Schedule Variance), CV (Cost Variance), SPI (Schedule Performance Index), CPI (Cost Performance Index), EAC (Estimated At Complete) and ET (Estimated To Complete) and TE (Time Estimate). Conclusions from this research is to determine the estimated costs and time for project completion. In the data analysis in the 9th week, the project schedule performance (CPI) was 1.14, greater than 1, while (SPI) was 0.587, less than 1. The results of the calculation of projected costs for the remaining work (ETC) were IDR. 1,586,686,537.62 and total project costs (EAC) of Rp. 2,509,041,243.08.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信