{"title":"调查欧盟电力高速公路的长期效益:绿色爱琴海互联线路案例","authors":"Christos K. Simoglou ,&nbsp;Pandelis N. Biskas","doi":"10.1016/j.segan.2024.101558","DOIUrl":null,"url":null,"abstract":"<div><div>This paper investigates the potential long-term benefits that could be arisen by the construction and operation of the envisioned “Green Aegean Interconnector”. This will be a pioneering 9-GW direct interconnection line connecting Greece with Germany to facilitate the transfer of massive amounts of RES generation from South-East to Central-North Europe. The ultimate goal of this analysis is to estimate the total electricity supply cost to be undertaken by the end-consumers in Greece with and without the said interconnector along with the cost/benefit of the Greek national economy associated with the foreseen cross-border electricity exchange. Detailed simulations of the Greek electricity market using a specialized electricity market simulation software on the basis of the main provisions of the revised Greek National Energy and Climate Plan are performed under realistic market evolution scenarios for a future 30-year study horizon (2026–2055). Simulation results and the associated cost-benefit analysis indicate that such a project would enable the operation of additional RES projects in Greece. This would, in turn, decrease the overall Greek end-consumers’ electricity cost and create a significant surplus for the Greek economy through the increased exporting activity, whereas at EU-level it would assist towards further achieving the European energy market integration.</div></div>","PeriodicalId":56142,"journal":{"name":"Sustainable Energy Grids & Networks","volume":"40 ","pages":"Article 101558"},"PeriodicalIF":4.8000,"publicationDate":"2024-10-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Investigating the long-term benefits of EU electricity highways: The case of the Green Aegean Interconnector\",\"authors\":\"Christos K. Simoglou ,&nbsp;Pandelis N. Biskas\",\"doi\":\"10.1016/j.segan.2024.101558\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><div>This paper investigates the potential long-term benefits that could be arisen by the construction and operation of the envisioned “Green Aegean Interconnector”. This will be a pioneering 9-GW direct interconnection line connecting Greece with Germany to facilitate the transfer of massive amounts of RES generation from South-East to Central-North Europe. The ultimate goal of this analysis is to estimate the total electricity supply cost to be undertaken by the end-consumers in Greece with and without the said interconnector along with the cost/benefit of the Greek national economy associated with the foreseen cross-border electricity exchange. Detailed simulations of the Greek electricity market using a specialized electricity market simulation software on the basis of the main provisions of the revised Greek National Energy and Climate Plan are performed under realistic market evolution scenarios for a future 30-year study horizon (2026–2055). Simulation results and the associated cost-benefit analysis indicate that such a project would enable the operation of additional RES projects in Greece. This would, in turn, decrease the overall Greek end-consumers’ electricity cost and create a significant surplus for the Greek economy through the increased exporting activity, whereas at EU-level it would assist towards further achieving the European energy market integration.</div></div>\",\"PeriodicalId\":56142,\"journal\":{\"name\":\"Sustainable Energy Grids & Networks\",\"volume\":\"40 \",\"pages\":\"Article 101558\"},\"PeriodicalIF\":4.8000,\"publicationDate\":\"2024-10-24\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Sustainable Energy Grids & Networks\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/S2352467724002881\",\"RegionNum\":2,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"ENERGY & FUELS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Sustainable Energy Grids & Networks","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S2352467724002881","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"ENERGY & FUELS","Score":null,"Total":0}
引用次数: 0

摘要

本文研究了设想中的 "绿色爱琴海互联线路 "的建设和运营可能带来的长期潜在效益。这将是一条连接希腊和德国的 9 千兆瓦直接互联线路,将促进大量可再生能源发电从东南欧向中北欧转移。本次分析的最终目标是估算希腊终端用户在有无上述联网线路的情况下所需承担的总供电成本,以及希腊国民经济在预期跨境电力交换方面的成本/收益。根据修订后的希腊国家能源与气候计划的主要规定,在未来 30 年的研究范围内(2026-2055 年),在现实的市场演变情景下,使用专门的电力市场模拟软件对希腊电力市场进行了详细模拟。模拟结果和相关的成本效益分析表明,该项目将使希腊更多的可再生能源项目得以运行。反过来,这将降低希腊终端消费者的总体电力成本,并通过增加出口活动为希腊经济创造大量盈余,而在欧盟层面,这将有助于进一步实现欧洲能源市场一体化。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Investigating the long-term benefits of EU electricity highways: The case of the Green Aegean Interconnector
This paper investigates the potential long-term benefits that could be arisen by the construction and operation of the envisioned “Green Aegean Interconnector”. This will be a pioneering 9-GW direct interconnection line connecting Greece with Germany to facilitate the transfer of massive amounts of RES generation from South-East to Central-North Europe. The ultimate goal of this analysis is to estimate the total electricity supply cost to be undertaken by the end-consumers in Greece with and without the said interconnector along with the cost/benefit of the Greek national economy associated with the foreseen cross-border electricity exchange. Detailed simulations of the Greek electricity market using a specialized electricity market simulation software on the basis of the main provisions of the revised Greek National Energy and Climate Plan are performed under realistic market evolution scenarios for a future 30-year study horizon (2026–2055). Simulation results and the associated cost-benefit analysis indicate that such a project would enable the operation of additional RES projects in Greece. This would, in turn, decrease the overall Greek end-consumers’ electricity cost and create a significant surplus for the Greek economy through the increased exporting activity, whereas at EU-level it would assist towards further achieving the European energy market integration.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Sustainable Energy Grids & Networks
Sustainable Energy Grids & Networks Energy-Energy Engineering and Power Technology
CiteScore
7.90
自引率
13.00%
发文量
206
审稿时长
49 days
期刊介绍: Sustainable Energy, Grids and Networks (SEGAN)is an international peer-reviewed publication for theoretical and applied research dealing with energy, information grids and power networks, including smart grids from super to micro grid scales. SEGAN welcomes papers describing fundamental advances in mathematical, statistical or computational methods with application to power and energy systems, as well as papers on applications, computation and modeling in the areas of electrical and energy systems with coupled information and communication technologies.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信