莉娜盖耶德塔退役工程

Fu Wu, Carlos Alvarez, Gary Osterman, Ching-Hsiang Chen, R. Litton, Georgios Apostolakis
{"title":"莉娜盖耶德塔退役工程","authors":"Fu Wu, Carlos Alvarez, Gary Osterman, Ching-Hsiang Chen, R. Litton, Georgios Apostolakis","doi":"10.4043/31237-ms","DOIUrl":null,"url":null,"abstract":"\n The Mississippi Canyon 280-A platform, also known as Lena Guyed Tower located in 1,000 ft water depth in the Gulf of Mexico (GoM), was successfully decommissioned and reefed in-place in 2020. To meet the regulatory requirements on offshore platform decommissioning, i.e. BSEE decommissioning requirements and the LDWF artificial reef program, an environmental study and an engineering study were performed to ensure that the platform decommissioning satisfies these critical requirements on environmental protection and operational safety.\n The environmental study revealed the abundance of marine lives residing on the tower and rare coral species only observed in deepwater region. This justified the environmental benefit of turning the tower into an on-site artificial reef and functioning as a vibrant marine life habitat at the end of its production service life.\n The engineering study on Lena decommissioning, as addressed in this paper, involved three (3) stages of engineering work: tower decommissioning concepts and feasibility study; selected concept definition; and detailed tower reef-in-place laydown (toppling) plan and design. High-level tower reef-in-place criteria were set up in the early engineering stage as guidelines to the detailed laydown design, including specific project requirements on minimal environmental impact and safe offshore field operations.\n This engineering study relied heavily on multiple expert brainstorm sessions on various decommissioning concepts and options, and advanced structural modeling and computer simulations for assessment and design. A large number of tower structural models were developed to verify the plan and check various factors and risk scenarios that may affect the tower performance in different stages of the decommissioning operation. Advanced analytical techniques were developed and applied, which feature the driving mechanisms of the problem such as soil-structure-interaction, guyline tension, structural member contact and sliding, large displacement simulation, structural collapse, and hydrodynamics. Stringent quality assurance and testing procedures were followed to ensure the credibility of developed analytical techniques and engineering technologies.\n The most challenging part that differentiates the decommissioning engineering from typical structural design is how to properly estimate the platform in-situ \"as-is\" condition and carry out the assessment as such to make a regulatory compliant, feasible, reliable, and efficient plan. Therefore, engineering judgment had to go beyond the scope covered by existing industry codes and standards, and rely on the most recent advances in industry research and technology.\n This engineering study resulted in a clearly defined tower decommissioning plan and procedure, backed up with contingency plans for various risk scenarios and potential deviations in field operation due to limitations and/or uncertainties. The decommissioning plan minimized the offshore field construction scope and risk, and kept the required tower laydown pull loads within the capacity range of typical GoM offshore tugboats. As a result, the Lena tower was successfully laid down on seafloor in an anticipated reefing position, with no major deviations from the plan.\n Lena Guyed Tower is the first deepwater compliant structure decommissioned. This decommissioning effort may provide the most valuable information and lessons learned to the industry for similar decommissioning and abandonment operations in the future.","PeriodicalId":11184,"journal":{"name":"Day 3 Wed, August 18, 2021","volume":"4 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-08-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Lena Guyed Tower Decommissioning Engineering\",\"authors\":\"Fu Wu, Carlos Alvarez, Gary Osterman, Ching-Hsiang Chen, R. Litton, Georgios Apostolakis\",\"doi\":\"10.4043/31237-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n The Mississippi Canyon 280-A platform, also known as Lena Guyed Tower located in 1,000 ft water depth in the Gulf of Mexico (GoM), was successfully decommissioned and reefed in-place in 2020. To meet the regulatory requirements on offshore platform decommissioning, i.e. BSEE decommissioning requirements and the LDWF artificial reef program, an environmental study and an engineering study were performed to ensure that the platform decommissioning satisfies these critical requirements on environmental protection and operational safety.\\n The environmental study revealed the abundance of marine lives residing on the tower and rare coral species only observed in deepwater region. This justified the environmental benefit of turning the tower into an on-site artificial reef and functioning as a vibrant marine life habitat at the end of its production service life.\\n The engineering study on Lena decommissioning, as addressed in this paper, involved three (3) stages of engineering work: tower decommissioning concepts and feasibility study; selected concept definition; and detailed tower reef-in-place laydown (toppling) plan and design. High-level tower reef-in-place criteria were set up in the early engineering stage as guidelines to the detailed laydown design, including specific project requirements on minimal environmental impact and safe offshore field operations.\\n This engineering study relied heavily on multiple expert brainstorm sessions on various decommissioning concepts and options, and advanced structural modeling and computer simulations for assessment and design. A large number of tower structural models were developed to verify the plan and check various factors and risk scenarios that may affect the tower performance in different stages of the decommissioning operation. Advanced analytical techniques were developed and applied, which feature the driving mechanisms of the problem such as soil-structure-interaction, guyline tension, structural member contact and sliding, large displacement simulation, structural collapse, and hydrodynamics. Stringent quality assurance and testing procedures were followed to ensure the credibility of developed analytical techniques and engineering technologies.\\n The most challenging part that differentiates the decommissioning engineering from typical structural design is how to properly estimate the platform in-situ \\\"as-is\\\" condition and carry out the assessment as such to make a regulatory compliant, feasible, reliable, and efficient plan. Therefore, engineering judgment had to go beyond the scope covered by existing industry codes and standards, and rely on the most recent advances in industry research and technology.\\n This engineering study resulted in a clearly defined tower decommissioning plan and procedure, backed up with contingency plans for various risk scenarios and potential deviations in field operation due to limitations and/or uncertainties. The decommissioning plan minimized the offshore field construction scope and risk, and kept the required tower laydown pull loads within the capacity range of typical GoM offshore tugboats. As a result, the Lena tower was successfully laid down on seafloor in an anticipated reefing position, with no major deviations from the plan.\\n Lena Guyed Tower is the first deepwater compliant structure decommissioned. This decommissioning effort may provide the most valuable information and lessons learned to the industry for similar decommissioning and abandonment operations in the future.\",\"PeriodicalId\":11184,\"journal\":{\"name\":\"Day 3 Wed, August 18, 2021\",\"volume\":\"4 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-08-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Wed, August 18, 2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/31237-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, August 18, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/31237-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

密西西比峡谷280-A平台,也被称为Lena Guyed塔,位于墨西哥湾(GoM)水深1000英尺处,于2020年成功退役并在原地礁化。为了满足海上平台退役的监管要求,即BSEE退役要求和LDWF人工鱼礁计划,进行了环境研究和工程研究,以确保平台退役满足这些环境保护和运行安全的关键要求。环境研究表明,栖息在塔上的海洋生物丰富,只有深水地区才有罕见的珊瑚物种。这证明了将塔变成现场人工珊瑚礁并在其生产使用寿命结束时作为充满活力的海洋生物栖息地的环境效益。本文所述的莱拿塔退役工程研究包括三个阶段的工程工作:塔退役概念和可行性研究;选定概念定义;并详细介绍了塔礁就地布放(推倒)方案和设计。在工程早期阶段,制定了高水平的塔礁就位标准,作为详细布局设计的指导方针,包括对最小环境影响和安全海上油田作业的具体项目要求。这项工程研究在很大程度上依赖于多次专家头脑风暴会议,讨论各种退役概念和方案,以及先进的结构建模和计算机模拟,以进行评估和设计。开发了大量的塔架结构模型来验证该方案,并对退役作业不同阶段可能影响塔架性能的各种因素和风险情景进行了校核。发展和应用了先进的分析技术,研究了土-结构相互作用、线张力、构件接触和滑动、大位移模拟、结构倒塌和水动力等问题的驱动机制。我们遵循严格的质量保证和测试程序,以确保开发的分析技术和工程技术的可信度。将退役工程与典型结构设计区别开来的最具挑战性的部分是如何正确评估平台的原位“现状”,并进行评估,以制定符合法规、可行、可靠和高效的计划。因此,工程判断必须超越现有行业规范和标准所涵盖的范围,依靠行业研究和技术的最新进展。该工程研究制定了明确的塔退役计划和程序,并制定了应急计划,以应对各种风险情况和现场作业中由于限制和/或不确定性而产生的潜在偏差。退役计划最大限度地减少了海上油田的施工范围和风险,并将所需的塔下拉载荷保持在典型的GoM海上拖船的能力范围内。结果,莱拿塔成功地在海底放置在预期的珊瑚礁位置,与计划没有重大偏差。Lena Guyed塔是第一个退役的深水合规结构。这项退役工作可能为行业未来类似的退役和废弃作业提供最有价值的信息和经验教训。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Lena Guyed Tower Decommissioning Engineering
The Mississippi Canyon 280-A platform, also known as Lena Guyed Tower located in 1,000 ft water depth in the Gulf of Mexico (GoM), was successfully decommissioned and reefed in-place in 2020. To meet the regulatory requirements on offshore platform decommissioning, i.e. BSEE decommissioning requirements and the LDWF artificial reef program, an environmental study and an engineering study were performed to ensure that the platform decommissioning satisfies these critical requirements on environmental protection and operational safety. The environmental study revealed the abundance of marine lives residing on the tower and rare coral species only observed in deepwater region. This justified the environmental benefit of turning the tower into an on-site artificial reef and functioning as a vibrant marine life habitat at the end of its production service life. The engineering study on Lena decommissioning, as addressed in this paper, involved three (3) stages of engineering work: tower decommissioning concepts and feasibility study; selected concept definition; and detailed tower reef-in-place laydown (toppling) plan and design. High-level tower reef-in-place criteria were set up in the early engineering stage as guidelines to the detailed laydown design, including specific project requirements on minimal environmental impact and safe offshore field operations. This engineering study relied heavily on multiple expert brainstorm sessions on various decommissioning concepts and options, and advanced structural modeling and computer simulations for assessment and design. A large number of tower structural models were developed to verify the plan and check various factors and risk scenarios that may affect the tower performance in different stages of the decommissioning operation. Advanced analytical techniques were developed and applied, which feature the driving mechanisms of the problem such as soil-structure-interaction, guyline tension, structural member contact and sliding, large displacement simulation, structural collapse, and hydrodynamics. Stringent quality assurance and testing procedures were followed to ensure the credibility of developed analytical techniques and engineering technologies. The most challenging part that differentiates the decommissioning engineering from typical structural design is how to properly estimate the platform in-situ "as-is" condition and carry out the assessment as such to make a regulatory compliant, feasible, reliable, and efficient plan. Therefore, engineering judgment had to go beyond the scope covered by existing industry codes and standards, and rely on the most recent advances in industry research and technology. This engineering study resulted in a clearly defined tower decommissioning plan and procedure, backed up with contingency plans for various risk scenarios and potential deviations in field operation due to limitations and/or uncertainties. The decommissioning plan minimized the offshore field construction scope and risk, and kept the required tower laydown pull loads within the capacity range of typical GoM offshore tugboats. As a result, the Lena tower was successfully laid down on seafloor in an anticipated reefing position, with no major deviations from the plan. Lena Guyed Tower is the first deepwater compliant structure decommissioned. This decommissioning effort may provide the most valuable information and lessons learned to the industry for similar decommissioning and abandonment operations in the future.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信