{"title":"提高复杂建设项目阶段成本和进度绩效的最佳实践选择","authors":"Elnaz Safapour, Sharareh Kermanshachi, Issa J. Ramaji","doi":"10.1080/10429247.2022.2036068","DOIUrl":null,"url":null,"abstract":"Abstract A common assumption made by construction professionals is that complex projects are more likely than simple ones to entail cost overruns and delays. Although several researchers have studied the critical causes of complexity and have identified their indicators (CIs), few of them have investigated how they actually impact a project’s schedule and cost performance during the design, procurement, and construction phases. This research aimed to study the impact of each CI and determine the most effective best practices (BPs) for preventing it. Data from 44 case studies were collected and analyzed, and the results revealed that implementing the BPs of team building, front-end planning (FEP), constructability, alignment, partnering, and change management significantly reduces cost overruns and delays in all three phases of complex construction projects and, in fact, can improve the cost and schedule performance, due to fewer complex challenges. The outcomes of this research will help project managers identify the challenges that stem from complex aspects of projects and lead to phase-base cost overruns and time delays. They will also assist decision-makers in deciding which are the most effective BPs for mitigating challenges stemming from the characteristics that make projects complex and will them improve phase-based cost and schedule performance in complex construction projects.","PeriodicalId":54353,"journal":{"name":"Engineering Management Journal","volume":"35 1","pages":"84 - 99"},"PeriodicalIF":1.9000,"publicationDate":"2022-03-16","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":"{\"title\":\"Selection of Best Practices that Enhance Phase-Based Cost and Schedule Performances in Complex Construction Projects\",\"authors\":\"Elnaz Safapour, Sharareh Kermanshachi, Issa J. Ramaji\",\"doi\":\"10.1080/10429247.2022.2036068\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Abstract A common assumption made by construction professionals is that complex projects are more likely than simple ones to entail cost overruns and delays. Although several researchers have studied the critical causes of complexity and have identified their indicators (CIs), few of them have investigated how they actually impact a project’s schedule and cost performance during the design, procurement, and construction phases. This research aimed to study the impact of each CI and determine the most effective best practices (BPs) for preventing it. Data from 44 case studies were collected and analyzed, and the results revealed that implementing the BPs of team building, front-end planning (FEP), constructability, alignment, partnering, and change management significantly reduces cost overruns and delays in all three phases of complex construction projects and, in fact, can improve the cost and schedule performance, due to fewer complex challenges. The outcomes of this research will help project managers identify the challenges that stem from complex aspects of projects and lead to phase-base cost overruns and time delays. They will also assist decision-makers in deciding which are the most effective BPs for mitigating challenges stemming from the characteristics that make projects complex and will them improve phase-based cost and schedule performance in complex construction projects.\",\"PeriodicalId\":54353,\"journal\":{\"name\":\"Engineering Management Journal\",\"volume\":\"35 1\",\"pages\":\"84 - 99\"},\"PeriodicalIF\":1.9000,\"publicationDate\":\"2022-03-16\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"5\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Engineering Management Journal\",\"FirstCategoryId\":\"91\",\"ListUrlMain\":\"https://doi.org/10.1080/10429247.2022.2036068\",\"RegionNum\":4,\"RegionCategory\":\"管理学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"ENGINEERING, INDUSTRIAL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering Management Journal","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.1080/10429247.2022.2036068","RegionNum":4,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
Selection of Best Practices that Enhance Phase-Based Cost and Schedule Performances in Complex Construction Projects
Abstract A common assumption made by construction professionals is that complex projects are more likely than simple ones to entail cost overruns and delays. Although several researchers have studied the critical causes of complexity and have identified their indicators (CIs), few of them have investigated how they actually impact a project’s schedule and cost performance during the design, procurement, and construction phases. This research aimed to study the impact of each CI and determine the most effective best practices (BPs) for preventing it. Data from 44 case studies were collected and analyzed, and the results revealed that implementing the BPs of team building, front-end planning (FEP), constructability, alignment, partnering, and change management significantly reduces cost overruns and delays in all three phases of complex construction projects and, in fact, can improve the cost and schedule performance, due to fewer complex challenges. The outcomes of this research will help project managers identify the challenges that stem from complex aspects of projects and lead to phase-base cost overruns and time delays. They will also assist decision-makers in deciding which are the most effective BPs for mitigating challenges stemming from the characteristics that make projects complex and will them improve phase-based cost and schedule performance in complex construction projects.
期刊介绍:
EMJ is designed to provide practical, pertinent knowledge on the management of technology, technical professionals, and technical organizations. EMJ strives to provide value to the practice of engineering management and engineering managers. EMJ is an archival journal that facilitates both practitioners and university faculty in publishing useful articles. The primary focus is on articles that improve the practice of engineering management. To support the practice of engineering management, EMJ publishes papers within key engineering management content areas. EMJ Editors will continue to refine these areas to ensure they are aligned with the challenges faced by technical organizations and technical managers.