{"title":"兰德桥(维戈)扩建侧板的施工","authors":"Fatima Otero Vieitez","doi":"10.33586/HYA.2020.2336","DOIUrl":null,"url":null,"abstract":"The enlargement of the Rande Bridge was a milestone in the lateral widening on a high-span cable-stayed bridge built with the infrastructure open to traffic. The project attaches a new deck to each of the two outer sides of the main piers. This deck is formed by a metal box section and an external lattice connected to the pre-existing deck by means of metallic lattices and spherical labelled joints. The segments were made in a workshop, moved by road to the storage area where they were finished and on a pontoon by sea to the vertical of their definitive position. The lifting was carried out in collaboration between a front traveler and a rear one designed for this purpose. PALABRAS CLAVE: Ampliación, atirantado, izado, pórtico, carro, dovela, tablero metálico.","PeriodicalId":41423,"journal":{"name":"Hormigon y Acero","volume":" ","pages":""},"PeriodicalIF":0.1000,"publicationDate":"2020-12-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Ejecución de los tableros laterales en la ampliación del puente de Rande (Vigo)\",\"authors\":\"Fatima Otero Vieitez\",\"doi\":\"10.33586/HYA.2020.2336\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The enlargement of the Rande Bridge was a milestone in the lateral widening on a high-span cable-stayed bridge built with the infrastructure open to traffic. The project attaches a new deck to each of the two outer sides of the main piers. This deck is formed by a metal box section and an external lattice connected to the pre-existing deck by means of metallic lattices and spherical labelled joints. The segments were made in a workshop, moved by road to the storage area where they were finished and on a pontoon by sea to the vertical of their definitive position. The lifting was carried out in collaboration between a front traveler and a rear one designed for this purpose. PALABRAS CLAVE: Ampliación, atirantado, izado, pórtico, carro, dovela, tablero metálico.\",\"PeriodicalId\":41423,\"journal\":{\"name\":\"Hormigon y Acero\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":0.1000,\"publicationDate\":\"2020-12-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Hormigon y Acero\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.33586/HYA.2020.2336\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Hormigon y Acero","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.33586/HYA.2020.2336","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
Ejecución de los tableros laterales en la ampliación del puente de Rande (Vigo)
The enlargement of the Rande Bridge was a milestone in the lateral widening on a high-span cable-stayed bridge built with the infrastructure open to traffic. The project attaches a new deck to each of the two outer sides of the main piers. This deck is formed by a metal box section and an external lattice connected to the pre-existing deck by means of metallic lattices and spherical labelled joints. The segments were made in a workshop, moved by road to the storage area where they were finished and on a pontoon by sea to the vertical of their definitive position. The lifting was carried out in collaboration between a front traveler and a rear one designed for this purpose. PALABRAS CLAVE: Ampliación, atirantado, izado, pórtico, carro, dovela, tablero metálico.