采用劳动乘数驱动法编制项目资源预算

IF 6.2 2区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY
Suet-Wai Tracy Cheung, Ming-Fung Francis Siu, Ping-Chuen Albert Chan
{"title":"采用劳动乘数驱动法编制项目资源预算","authors":"Suet-Wai Tracy Cheung,&nbsp;Ming-Fung Francis Siu,&nbsp;Ping-Chuen Albert Chan","doi":"10.1016/j.dibe.2024.100496","DOIUrl":null,"url":null,"abstract":"<div><p>Manpower demand for construction projects is roughly budgeted based on planners’ personal experience. This research study explores an analytical way to characterise project labour demand profiles throughout project duration. Labour multiplier (LM) approach was advanced to characterise the labour demand profiles. Optimistic, most-likely, and pessimistic LM and labour demand profiles at 10 project stages are defined by using manpower and payment data derived from 91 completed public construction projects under 21 project types in Hong Kong. The root-mean-square-error and root-mean-squared-logarithmic-error are used to quantify the difference between the budgeted and the benchmarked manpower. A text-book example is successfully adopted to demonstrate the steps of the proposed approach, validated by two practical projects. This research is the first to study the use of LM to characterise optimistic, most-likely, pessimistic resource demand profiles for validating manpower resource budgets. Also, the approach provides a basis to evaluate the reasonableness of planned resource.</p></div>","PeriodicalId":34137,"journal":{"name":"Developments in the Built Environment","volume":"19 ","pages":"Article 100496"},"PeriodicalIF":6.2000,"publicationDate":"2024-07-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://www.sciencedirect.com/science/article/pii/S2666165924001777/pdfft?md5=bfec8882a10da27d66d7f2242e46b3dd&pid=1-s2.0-S2666165924001777-main.pdf","citationCount":"0","resultStr":"{\"title\":\"Labour multiplier driven approach for budgeting project resources\",\"authors\":\"Suet-Wai Tracy Cheung,&nbsp;Ming-Fung Francis Siu,&nbsp;Ping-Chuen Albert Chan\",\"doi\":\"10.1016/j.dibe.2024.100496\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><p>Manpower demand for construction projects is roughly budgeted based on planners’ personal experience. This research study explores an analytical way to characterise project labour demand profiles throughout project duration. Labour multiplier (LM) approach was advanced to characterise the labour demand profiles. Optimistic, most-likely, and pessimistic LM and labour demand profiles at 10 project stages are defined by using manpower and payment data derived from 91 completed public construction projects under 21 project types in Hong Kong. The root-mean-square-error and root-mean-squared-logarithmic-error are used to quantify the difference between the budgeted and the benchmarked manpower. A text-book example is successfully adopted to demonstrate the steps of the proposed approach, validated by two practical projects. This research is the first to study the use of LM to characterise optimistic, most-likely, pessimistic resource demand profiles for validating manpower resource budgets. Also, the approach provides a basis to evaluate the reasonableness of planned resource.</p></div>\",\"PeriodicalId\":34137,\"journal\":{\"name\":\"Developments in the Built Environment\",\"volume\":\"19 \",\"pages\":\"Article 100496\"},\"PeriodicalIF\":6.2000,\"publicationDate\":\"2024-07-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://www.sciencedirect.com/science/article/pii/S2666165924001777/pdfft?md5=bfec8882a10da27d66d7f2242e46b3dd&pid=1-s2.0-S2666165924001777-main.pdf\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Developments in the Built Environment\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/S2666165924001777\",\"RegionNum\":2,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"CONSTRUCTION & BUILDING TECHNOLOGY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Developments in the Built Environment","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S2666165924001777","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 0

摘要

建筑项目的人力需求是根据规划人员的个人经验进行粗略预算的。本研究探索了一种分析方法,用于描述整个项目期间的项目劳动力需求概况。采用劳动力乘数(LM)方法来描述劳动力需求概况。通过使用从香港 21 个项目类型下 91 个已完成公共建筑项目中获得的人力和付款数据,定义了 10 个项目阶段的乐观、最有可能和悲观劳动力乘数和劳动力需求概况。均方根误差和均方根对数误差用于量化预算人力和基准人力之间的差异。通过两个实际项目的验证,成功地采用了一个教科书中的例子来演示所建议方法的步骤。这项研究首次研究了如何使用 LM 来描述乐观、最有可能和悲观的资源需求状况,以验证人力资源预算。此外,该方法还为评估计划资源的合理性提供了依据。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Labour multiplier driven approach for budgeting project resources

Manpower demand for construction projects is roughly budgeted based on planners’ personal experience. This research study explores an analytical way to characterise project labour demand profiles throughout project duration. Labour multiplier (LM) approach was advanced to characterise the labour demand profiles. Optimistic, most-likely, and pessimistic LM and labour demand profiles at 10 project stages are defined by using manpower and payment data derived from 91 completed public construction projects under 21 project types in Hong Kong. The root-mean-square-error and root-mean-squared-logarithmic-error are used to quantify the difference between the budgeted and the benchmarked manpower. A text-book example is successfully adopted to demonstrate the steps of the proposed approach, validated by two practical projects. This research is the first to study the use of LM to characterise optimistic, most-likely, pessimistic resource demand profiles for validating manpower resource budgets. Also, the approach provides a basis to evaluate the reasonableness of planned resource.

求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
7.40
自引率
1.20%
发文量
31
审稿时长
22 days
期刊介绍: Developments in the Built Environment (DIBE) is a recently established peer-reviewed gold open access journal, ensuring that all accepted articles are permanently and freely accessible. Focused on civil engineering and the built environment, DIBE publishes original papers and short communications. Encompassing topics such as construction materials and building sustainability, the journal adopts a holistic approach with the aim of benefiting the community.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信