{"title":"采用碰撞法对 Sdn Kutisari 2 号开发项目进行加速度分析","authors":"Muhammad Bayu Firdaus, H. T. Tjendani, Budi Witjaksana","doi":"10.55047/ijateis.v2i4.950","DOIUrl":null,"url":null,"abstract":"In the construction of the Kutisari 2 SDN Project, there were several obstacles that hampered the implementation of the project, such as heavy rainy weather. The aim of the research is to determine the cost and acceleration time for the construction of the SDN Kutisari 2 Project. The research design was carried out to identify the time and costs of implementing the building construction completion project. The research was conducted at CV.Nisya Multi Bintang as the implementing contractor with a budget of Rp. 1,614,171,924 for 165 calendar days. The research subjects were contractors completing work on the Kutisari 2 Elementary School Development Project. This research used secondary data from the Draft Expenditure Budget, Schedule, weekly reports and project cost costs. Data analysis used Microsoft Project 2016 software. The results of the research stated (1) The duration of the Crashing was 8 calendar days with work that was on the Critical Work Route for the Construction of School Facilities, Infrastructure and Utilities at SDN Kutisari 2, namely water proofing coating with fiber on the 2nd floor, cleaning location to the end, B-0 work to cover 2nd floor columns, 2nd floor column cutting work, and floor screading work. (2) From the initial cost of the Kutisari 2 SDN School Facilities, Infrastructure and Utilities Construction Work Project, namely Rp. 1,164,171,924 with additional costs due to Crashing of Rp. 24,569,780 so the total costs due to the Crashing are Rp. 1,638,741,704.","PeriodicalId":475177,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","volume":"163 3","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ACCELERATION ANALYSIS USING THE CRASHING METHOD IN THE SDN KUTISARI 2 DEVELOPMENT PROJECT\",\"authors\":\"Muhammad Bayu Firdaus, H. T. Tjendani, Budi Witjaksana\",\"doi\":\"10.55047/ijateis.v2i4.950\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In the construction of the Kutisari 2 SDN Project, there were several obstacles that hampered the implementation of the project, such as heavy rainy weather. The aim of the research is to determine the cost and acceleration time for the construction of the SDN Kutisari 2 Project. The research design was carried out to identify the time and costs of implementing the building construction completion project. The research was conducted at CV.Nisya Multi Bintang as the implementing contractor with a budget of Rp. 1,614,171,924 for 165 calendar days. The research subjects were contractors completing work on the Kutisari 2 Elementary School Development Project. This research used secondary data from the Draft Expenditure Budget, Schedule, weekly reports and project cost costs. Data analysis used Microsoft Project 2016 software. The results of the research stated (1) The duration of the Crashing was 8 calendar days with work that was on the Critical Work Route for the Construction of School Facilities, Infrastructure and Utilities at SDN Kutisari 2, namely water proofing coating with fiber on the 2nd floor, cleaning location to the end, B-0 work to cover 2nd floor columns, 2nd floor column cutting work, and floor screading work. (2) From the initial cost of the Kutisari 2 SDN School Facilities, Infrastructure and Utilities Construction Work Project, namely Rp. 1,164,171,924 with additional costs due to Crashing of Rp. 24,569,780 so the total costs due to the Crashing are Rp. 1,638,741,704.\",\"PeriodicalId\":475177,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"163 3\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"0\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v2i4.950\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.55047/ijateis.v2i4.950","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
在库蒂萨里 2 号 SDN 项目的建设过程中,有几个障碍阻碍了项目的实施,如大雨天气。本研究旨在确定库蒂萨里 2 号 SDN 项目的建设成本和加速时间。研究设计的目的是确定建筑竣工项目的实施时间和成本。研究以 CV.Nisya Multi Bintang 为实施承包商,预算为 1,614,171,924 印尼盾,历时 165 天。研究对象是完成 Kutisari 2 小学发展项目的承包商。本研究使用了来自支出预算草案、时间表、周报和项目成本费用的二手数据。数据分析使用了 Microsoft Project 2016 软件。研究结果表明:(1)撞击持续时间为 8 个日历日,工作内容为 SDN Kutisari 2 小学学校设施、基础设施和公用事业建设的关键工作路线,即二楼纤维防水涂层、清洁位置至末端、覆盖二楼柱子的 B-0 工作、二楼柱子切割工作和楼板清扫工作。(2) Kutisari 2 SDN 学校设施、基础设施和公用事业建设工程的初始成本为 1,164,171,924 印尼盾,由于撞击造成的额外成本为 24,569,780 印尼盾,因此撞击造成的总成本为 1,638,741,704 印尼盾。
ACCELERATION ANALYSIS USING THE CRASHING METHOD IN THE SDN KUTISARI 2 DEVELOPMENT PROJECT
In the construction of the Kutisari 2 SDN Project, there were several obstacles that hampered the implementation of the project, such as heavy rainy weather. The aim of the research is to determine the cost and acceleration time for the construction of the SDN Kutisari 2 Project. The research design was carried out to identify the time and costs of implementing the building construction completion project. The research was conducted at CV.Nisya Multi Bintang as the implementing contractor with a budget of Rp. 1,614,171,924 for 165 calendar days. The research subjects were contractors completing work on the Kutisari 2 Elementary School Development Project. This research used secondary data from the Draft Expenditure Budget, Schedule, weekly reports and project cost costs. Data analysis used Microsoft Project 2016 software. The results of the research stated (1) The duration of the Crashing was 8 calendar days with work that was on the Critical Work Route for the Construction of School Facilities, Infrastructure and Utilities at SDN Kutisari 2, namely water proofing coating with fiber on the 2nd floor, cleaning location to the end, B-0 work to cover 2nd floor columns, 2nd floor column cutting work, and floor screading work. (2) From the initial cost of the Kutisari 2 SDN School Facilities, Infrastructure and Utilities Construction Work Project, namely Rp. 1,164,171,924 with additional costs due to Crashing of Rp. 24,569,780 so the total costs due to the Crashing are Rp. 1,638,741,704.