{"title":"利用时间成本权衡法(TCTO)对帕苏鲁安某政府机构(OPD)办公楼建设项目进行成本和时间分析的研究","authors":"Didik Purnomo, W. Oetomo, Risma Marleno","doi":"10.55047/ijateis.v2i4.1007","DOIUrl":null,"url":null,"abstract":"In construction project control, the main factors of concern are quality, time and cost control. So it is necessary to use one method in the implementation of its control. This study aims to analyze the time and cost of the Raci OPD Office Building Construction project. The benefit of this research is to anticipate potential delays that occur in the project. The problem limitation is focused on work that has not been completed in the remaining time of the contract period. To analyze time and cost, this research uses Critical Path Method (CPM) and Time-Cost Trade- Off (TCTO) which begins with determining the work network and critical path. TCTO analysis is carried out by shortening the duration of work by adding 3 hours of overtime and calculating the Crash Slope of each job on the critical path. Rescheduling is done by accelerating the work that has the lowest cost The results showed that the most effective rescheduling was carried out on the Lt.3 Installation and Plastering work with the acquisition of an acceleration duration of 8 days. And the total cost required for this acceleration is Rp. 29,441,424, - or Rp. 1,226,726,- per day for 24 days.","PeriodicalId":475177,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","volume":"197 2","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"STUDY OF COST AND TIME ANALYSIS USING THE TIME COST TRADE-OFF (TCTO) METHOD IN THE CONSTRUCTION PROJECT OF THE OFFICE BUILDING OF A GOVERNMENT AGENCY (OPD) IN PASURUAN\",\"authors\":\"Didik Purnomo, W. Oetomo, Risma Marleno\",\"doi\":\"10.55047/ijateis.v2i4.1007\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In construction project control, the main factors of concern are quality, time and cost control. So it is necessary to use one method in the implementation of its control. This study aims to analyze the time and cost of the Raci OPD Office Building Construction project. The benefit of this research is to anticipate potential delays that occur in the project. The problem limitation is focused on work that has not been completed in the remaining time of the contract period. To analyze time and cost, this research uses Critical Path Method (CPM) and Time-Cost Trade- Off (TCTO) which begins with determining the work network and critical path. TCTO analysis is carried out by shortening the duration of work by adding 3 hours of overtime and calculating the Crash Slope of each job on the critical path. Rescheduling is done by accelerating the work that has the lowest cost The results showed that the most effective rescheduling was carried out on the Lt.3 Installation and Plastering work with the acquisition of an acceleration duration of 8 days. And the total cost required for this acceleration is Rp. 29,441,424, - or Rp. 1,226,726,- per day for 24 days.\",\"PeriodicalId\":475177,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"197 2\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"0\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v2i4.1007\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.55047/ijateis.v2i4.1007","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
STUDY OF COST AND TIME ANALYSIS USING THE TIME COST TRADE-OFF (TCTO) METHOD IN THE CONSTRUCTION PROJECT OF THE OFFICE BUILDING OF A GOVERNMENT AGENCY (OPD) IN PASURUAN
In construction project control, the main factors of concern are quality, time and cost control. So it is necessary to use one method in the implementation of its control. This study aims to analyze the time and cost of the Raci OPD Office Building Construction project. The benefit of this research is to anticipate potential delays that occur in the project. The problem limitation is focused on work that has not been completed in the remaining time of the contract period. To analyze time and cost, this research uses Critical Path Method (CPM) and Time-Cost Trade- Off (TCTO) which begins with determining the work network and critical path. TCTO analysis is carried out by shortening the duration of work by adding 3 hours of overtime and calculating the Crash Slope of each job on the critical path. Rescheduling is done by accelerating the work that has the lowest cost The results showed that the most effective rescheduling was carried out on the Lt.3 Installation and Plastering work with the acquisition of an acceleration duration of 8 days. And the total cost required for this acceleration is Rp. 29,441,424, - or Rp. 1,226,726,- per day for 24 days.