{"title":"对班尤万吉县 Karetan - Sambimulyo 公路维修项目的成本和时间绩效进行评估","authors":"Oscar Harris, Risma Marleno, W. Oetomo","doi":"10.55047/ijateis.v2i4.1045","DOIUrl":null,"url":null,"abstract":"Along with technological developments in the field of project work implementation, it must also be accompanied by developments in the field of Management as a control function in the implementation of the project. In this case, the application of the Earned Value Concept Method is expected to be able to provide an alternative solution to the problem of evaluating the cost and time that has been spent on project implementation. The purpose of this study is to evaluate a project work that is being carried out, namely in the form of Maintenance of Karetan-Sambimulyo Road, Banyuwangi Regency against Time and Cost Control of the Project, so that it can be used as a reference material by the project implementer and the employer in terms of decision making whether the project is feasible to complete or not. The research was conducted at the end of week 21 (twenty-one), with different evaluation results, thus it can be concluded with the following description: a. Based on Cost Variance (CV) & Schedule Variance (SV) analysis results obtained: Work is carried out later than the schedule plan, costs are lower than the budget plan; b. Based on Cost Performance Index (CPI) & Schedule Performance Index (SPI): Profit but experiencing delays; c. Based on Estimation to Complete (ETC) & Estimation at Completion (EAC): Obtaining a profit of Rp. 263,004,000, 00-,; d. Based on Estimate Temporary Cost (ETC) & Estimate All Cost (EAS): Experienced a Time Delay of 2.09 Weeks.","PeriodicalId":475177,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","volume":"25 24","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"EVALUATION OF COST AND TIME PERFORMANCE OF KARETAN - SAMBIMULYO ROAD MAINTENANCE PROJECT IN BANYUWANGI DISTRICT\",\"authors\":\"Oscar Harris, Risma Marleno, W. Oetomo\",\"doi\":\"10.55047/ijateis.v2i4.1045\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Along with technological developments in the field of project work implementation, it must also be accompanied by developments in the field of Management as a control function in the implementation of the project. In this case, the application of the Earned Value Concept Method is expected to be able to provide an alternative solution to the problem of evaluating the cost and time that has been spent on project implementation. The purpose of this study is to evaluate a project work that is being carried out, namely in the form of Maintenance of Karetan-Sambimulyo Road, Banyuwangi Regency against Time and Cost Control of the Project, so that it can be used as a reference material by the project implementer and the employer in terms of decision making whether the project is feasible to complete or not. The research was conducted at the end of week 21 (twenty-one), with different evaluation results, thus it can be concluded with the following description: a. Based on Cost Variance (CV) & Schedule Variance (SV) analysis results obtained: Work is carried out later than the schedule plan, costs are lower than the budget plan; b. Based on Cost Performance Index (CPI) & Schedule Performance Index (SPI): Profit but experiencing delays; c. Based on Estimation to Complete (ETC) & Estimation at Completion (EAC): Obtaining a profit of Rp. 263,004,000, 00-,; d. Based on Estimate Temporary Cost (ETC) & Estimate All Cost (EAS): Experienced a Time Delay of 2.09 Weeks.\",\"PeriodicalId\":475177,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"25 24\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"0\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v2i4.1045\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.55047/ijateis.v2i4.1045","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
随着项目工作实施领域的技术发展,作为项目实施过程中控制职能的管理领域也必须随之发展。在这种情况下,应用挣值概念法有望为评估项目实施所花费的成本和时间问题提供另一种解决方案。本研究的目的是根据项目的时间和成本控制,对一个正在实施的项目工程进行评估,该项目工程的形式是班佑万吉县卡雷坦-桑比姆尤约公路维修工程,以便项目实施者和雇主在决策项目是否可行时将其作为参考材料。研究在第 21 周(21 周)结束时进行,评估结果各不相同,因此可以得出以下结论: a. 基于成本差异(CV)和进度差异(SV)的分析结果:工作开展晚于进度计划,成本低于预算计划; b. 基于成本绩效指数(CPI)和进度绩效指数(SPI):获得利润,但出现延误; c. 基于完工估算(ETC)和完工估算(EAC):获得利润 263 004 000 印尼盾; d. 基于临时费用估算(ETC)和全部费用估算(EAS):时间延误 2.09 周。
EVALUATION OF COST AND TIME PERFORMANCE OF KARETAN - SAMBIMULYO ROAD MAINTENANCE PROJECT IN BANYUWANGI DISTRICT
Along with technological developments in the field of project work implementation, it must also be accompanied by developments in the field of Management as a control function in the implementation of the project. In this case, the application of the Earned Value Concept Method is expected to be able to provide an alternative solution to the problem of evaluating the cost and time that has been spent on project implementation. The purpose of this study is to evaluate a project work that is being carried out, namely in the form of Maintenance of Karetan-Sambimulyo Road, Banyuwangi Regency against Time and Cost Control of the Project, so that it can be used as a reference material by the project implementer and the employer in terms of decision making whether the project is feasible to complete or not. The research was conducted at the end of week 21 (twenty-one), with different evaluation results, thus it can be concluded with the following description: a. Based on Cost Variance (CV) & Schedule Variance (SV) analysis results obtained: Work is carried out later than the schedule plan, costs are lower than the budget plan; b. Based on Cost Performance Index (CPI) & Schedule Performance Index (SPI): Profit but experiencing delays; c. Based on Estimation to Complete (ETC) & Estimation at Completion (EAC): Obtaining a profit of Rp. 263,004,000, 00-,; d. Based on Estimate Temporary Cost (ETC) & Estimate All Cost (EAS): Experienced a Time Delay of 2.09 Weeks.