采用碰撞法对普罗林戈 - 班佑万吉收费公路项目进行成本和时间分析 Peket 2: STA 9+000 - 20+200

Budidarma Ardi Nugraha, H. T. Tjendani, Budi Witjaksana
{"title":"采用碰撞法对普罗林戈 - 班佑万吉收费公路项目进行成本和时间分析 Peket 2: STA 9+000 - 20+200","authors":"Budidarma Ardi Nugraha, H. T. Tjendani, Budi Witjaksana","doi":"10.55047/ijateis.v2i4.984","DOIUrl":null,"url":null,"abstract":"The government is building toll roads in various regions in Indonesia to realize economic acceleration and minimize economic inequality in society. However, based on facts on the ground, there are still many delays in toll road construction projects which are detrimental so it is necessary to take steps to accelerate the work. The aim of this research is to analyze the time and costs of accelerating the Probolinggo – Banyuwangi Toll Road construction project STA 9+000 – 20+200 using the Crashing Method. This type of research is quantitative research with the research subject being PT. Hutama Karya Indonesia (HKI) as the project implementing contractor. The research uses secondary data, namely the Draft Expenditure Budget (RAB), Schedule, weekly reports, and project costs for the completion of Toll Road construction work. The data collection method was carried out using observation and documentation methods. The research data analysis technique uses the Crashing. The results of research state: 1) On work on the Probolinggo – Banyuwangi Toll Road project Job STA 9+000 – 20 +200 job time can be accelerated to 311 days, which originally lasted 394 days. 2) Application of the Crashing Method to the Probolinggo Toll Road project– Banyuwangi STA Jobs 9+000 – 20+200 with critical path on public works, workplace cleaning, earthworks, drainage, sub grade, aggregate base layer, pavement, work others, traffic light lighting and electrical works, plazas Tolls, and work on toll facilities and toll gate offices can saving 115 days of work time with additions cost Rp. 72,941,450,191.64.","PeriodicalId":475177,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","volume":"27 19","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"COST AND TIME ANALYSIS USING THE CRASHING METHOD ON THE PROBOLINGGO – BANYUWANGI TOLL ROAD PROJECT PEKET 2: STA 9+000 – 20+200\",\"authors\":\"Budidarma Ardi Nugraha, H. T. Tjendani, Budi Witjaksana\",\"doi\":\"10.55047/ijateis.v2i4.984\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The government is building toll roads in various regions in Indonesia to realize economic acceleration and minimize economic inequality in society. However, based on facts on the ground, there are still many delays in toll road construction projects which are detrimental so it is necessary to take steps to accelerate the work. The aim of this research is to analyze the time and costs of accelerating the Probolinggo – Banyuwangi Toll Road construction project STA 9+000 – 20+200 using the Crashing Method. This type of research is quantitative research with the research subject being PT. Hutama Karya Indonesia (HKI) as the project implementing contractor. The research uses secondary data, namely the Draft Expenditure Budget (RAB), Schedule, weekly reports, and project costs for the completion of Toll Road construction work. The data collection method was carried out using observation and documentation methods. The research data analysis technique uses the Crashing. The results of research state: 1) On work on the Probolinggo – Banyuwangi Toll Road project Job STA 9+000 – 20 +200 job time can be accelerated to 311 days, which originally lasted 394 days. 2) Application of the Crashing Method to the Probolinggo Toll Road project– Banyuwangi STA Jobs 9+000 – 20+200 with critical path on public works, workplace cleaning, earthworks, drainage, sub grade, aggregate base layer, pavement, work others, traffic light lighting and electrical works, plazas Tolls, and work on toll facilities and toll gate offices can saving 115 days of work time with additions cost Rp. 72,941,450,191.64.\",\"PeriodicalId\":475177,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"27 19\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"0\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v2i4.984\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.55047/ijateis.v2i4.984","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

政府正在印尼各地区修建收费公路,以实现经济加速发展,最大限度地减少社会中的经济不平等现象。然而,根据当地的实际情况,收费公路建设项目仍然存在许多延误,这对工程造成了不利影响,因此有必要采取措施加快工程进度。本研究的目的是使用崩溃法分析加快普罗波林戈-班裕万吉收费公路建设项目 STA 9+000 - 20+200 的时间和成本。本研究为定量研究,研究对象为 PT.Hutama Karya Indonesia (HKI) 作为项目实施承包商。研究使用二手数据,即完成收费公路建设工程的支出预算草案(RAB)、时间表、周报和项目成本。数据收集方法采用观察法和记录法。研究数据分析技术采用碰撞法。研究结果表明1) 普罗波林戈 - 班佑万吉收费公路项目的工作 STA 9+000 - 20 +200 工作时间可加快到 311 天,而原来的工作时间为 394 天。2) 在普罗波林戈-班裕万吉收费公路项目 STA 工作 9+000 - 20+200 中应用崩溃法,关键路径包括公共工程、工作场所清洁、土方工程、排水工程、基层、集料基层、路面、其他工程、交通灯照明和电气工程、广场收费、收费设施和收费站办公室工程,可节省 115 天的工作时间,增加成本 72 941 450 191.64 印尼盾。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
COST AND TIME ANALYSIS USING THE CRASHING METHOD ON THE PROBOLINGGO – BANYUWANGI TOLL ROAD PROJECT PEKET 2: STA 9+000 – 20+200
The government is building toll roads in various regions in Indonesia to realize economic acceleration and minimize economic inequality in society. However, based on facts on the ground, there are still many delays in toll road construction projects which are detrimental so it is necessary to take steps to accelerate the work. The aim of this research is to analyze the time and costs of accelerating the Probolinggo – Banyuwangi Toll Road construction project STA 9+000 – 20+200 using the Crashing Method. This type of research is quantitative research with the research subject being PT. Hutama Karya Indonesia (HKI) as the project implementing contractor. The research uses secondary data, namely the Draft Expenditure Budget (RAB), Schedule, weekly reports, and project costs for the completion of Toll Road construction work. The data collection method was carried out using observation and documentation methods. The research data analysis technique uses the Crashing. The results of research state: 1) On work on the Probolinggo – Banyuwangi Toll Road project Job STA 9+000 – 20 +200 job time can be accelerated to 311 days, which originally lasted 394 days. 2) Application of the Crashing Method to the Probolinggo Toll Road project– Banyuwangi STA Jobs 9+000 – 20+200 with critical path on public works, workplace cleaning, earthworks, drainage, sub grade, aggregate base layer, pavement, work others, traffic light lighting and electrical works, plazas Tolls, and work on toll facilities and toll gate offices can saving 115 days of work time with additions cost Rp. 72,941,450,191.64.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信