在帕苏鲁安县 BPBD 建筑群施工项目中使用挣值法进行成本和时间分析

Bagus Cahyono, Risma Marleno, W. Oetomo
{"title":"在帕苏鲁安县 BPBD 建筑群施工项目中使用挣值法进行成本和时间分析","authors":"Bagus Cahyono, Risma Marleno, W. Oetomo","doi":"10.55047/ijateis.v2i4.1043","DOIUrl":null,"url":null,"abstract":"In the construction project of the Pasuruan Regency BPBD building complex which is currently still running, there have been problems related to the schedule for the implementation of its activities. The problem in question is the delay in the schedule for the implementation of its activities. where the results of the progress realization are not in accordance with the schedule plan, through this paper an evaluation is carried out related to performance in the field through an approach using the Earned Value Method. The data analysis process is carried out by calculating analysis indicators including BCWS, BCWP and ACWP. The results of the performance evaluation of the Pasuruan Regency BPBD building complex construction project using the Earned Value method show that the project has a negative deviation in the activity implementation schedule. The cost performance indicator on this project shows a Cost Performance Index (CPI) value of 1.137, which means that the costs incurred are greater than planned. While the time performance indicator shows a Schedule Performance Index (SPI) value of 0.949, which means the project is delayed from the planned schedule.","PeriodicalId":475177,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","volume":"10 2","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"COST AND TIME ANALYSIS USING THE EARNED VALUE METHOD IN THE CONSTRUCTION PROJECT OF THE BPBD BUILDING COMPLEX IN PASURUAN DISTRICT\",\"authors\":\"Bagus Cahyono, Risma Marleno, W. Oetomo\",\"doi\":\"10.55047/ijateis.v2i4.1043\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In the construction project of the Pasuruan Regency BPBD building complex which is currently still running, there have been problems related to the schedule for the implementation of its activities. The problem in question is the delay in the schedule for the implementation of its activities. where the results of the progress realization are not in accordance with the schedule plan, through this paper an evaluation is carried out related to performance in the field through an approach using the Earned Value Method. The data analysis process is carried out by calculating analysis indicators including BCWS, BCWP and ACWP. The results of the performance evaluation of the Pasuruan Regency BPBD building complex construction project using the Earned Value method show that the project has a negative deviation in the activity implementation schedule. The cost performance indicator on this project shows a Cost Performance Index (CPI) value of 1.137, which means that the costs incurred are greater than planned. While the time performance indicator shows a Schedule Performance Index (SPI) value of 0.949, which means the project is delayed from the planned schedule.\",\"PeriodicalId\":475177,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"10 2\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"0\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v2i4.1043\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.55047/ijateis.v2i4.1043","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

在目前仍在实施的 Pasuruan 区 BPBD 建筑群建设项目中,存在着与活动实施进度相关的问题。在进度实现结果与进度计划不符的情况下,本文通过使用挣值法(Earned Value Method)对现场绩效进行了评估。数据分析过程是通过计算包括 BCWS、BCWP 和 ACWP 在内的分析指标来进行的。使用挣值法对 Pasuruan Regency BPBD 建筑群建设项目进行绩效评价的结果表明,该项目在活动实施进度方面存在负偏差。该项目的成本绩效指标显示,成本绩效指数(CPI)值为 1.137,这意味着发生的成本高于计划。而时间绩效指标显示的进度绩效指数(SPI)值为 0.949,这意味着项目比计划进度延迟。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
COST AND TIME ANALYSIS USING THE EARNED VALUE METHOD IN THE CONSTRUCTION PROJECT OF THE BPBD BUILDING COMPLEX IN PASURUAN DISTRICT
In the construction project of the Pasuruan Regency BPBD building complex which is currently still running, there have been problems related to the schedule for the implementation of its activities. The problem in question is the delay in the schedule for the implementation of its activities. where the results of the progress realization are not in accordance with the schedule plan, through this paper an evaluation is carried out related to performance in the field through an approach using the Earned Value Method. The data analysis process is carried out by calculating analysis indicators including BCWS, BCWP and ACWP. The results of the performance evaluation of the Pasuruan Regency BPBD building complex construction project using the Earned Value method show that the project has a negative deviation in the activity implementation schedule. The cost performance indicator on this project shows a Cost Performance Index (CPI) value of 1.137, which means that the costs incurred are greater than planned. While the time performance indicator shows a Schedule Performance Index (SPI) value of 0.949, which means the project is delayed from the planned schedule.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信