利用挣值法分析西多阿州瓦敦加斯里市场渠道正常化工程的成本和时间绩效

Wuri Proboretno, Budi Witjaksana, H. T. Tjendani
{"title":"利用挣值法分析西多阿州瓦敦加斯里市场渠道正常化工程的成本和时间绩效","authors":"Wuri Proboretno, Budi Witjaksana, H. T. Tjendani","doi":"10.55047/ijateis.v3i2.983","DOIUrl":null,"url":null,"abstract":"The construction project management for Wadungasri Sidoarjo Market Drainage Normalization aims to achieve cost, quality, and time objectives within a 100-day timeframe. This study addresses a 7.44% delay experienced by contractors, seeking to establish early warning mechanisms for poor project performance. The Earned Value Method is employed, integrating time and cost value concepts. Key indicators such as Cost Variance (CV), Schedule Variance (SV), work productivity index (CPI), time productivity index (SPI), project completion cost forecast (EAC), and project completion schedule forecast (ECD) are utilized. The results reveal a required cost of Rp 563,044,547.85 (ETC) and a 65-day timeframe (ETS) at the end of the 7th week, with a 0.64% increase in project completion cost (EAC) over the contract cost. The project completion time (EAS) is estimated at 114 days, reflecting a 0.14% extension. The analysis emphasizes the importance for construction service providers to implement efficient methods and consistent supervision to avoid delays in the Wadungasri Sidoarjo Market Drainage Normalization project.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"47 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ANALYSIS OF COST AND TIME PERFORMANCE IN THE WADUNGASRI MARKET CHANNEL NORMALIZATION WORK IN SIDOARJO USING THE EARNED VALUE METHOD\",\"authors\":\"Wuri Proboretno, Budi Witjaksana, H. T. Tjendani\",\"doi\":\"10.55047/ijateis.v3i2.983\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The construction project management for Wadungasri Sidoarjo Market Drainage Normalization aims to achieve cost, quality, and time objectives within a 100-day timeframe. This study addresses a 7.44% delay experienced by contractors, seeking to establish early warning mechanisms for poor project performance. The Earned Value Method is employed, integrating time and cost value concepts. Key indicators such as Cost Variance (CV), Schedule Variance (SV), work productivity index (CPI), time productivity index (SPI), project completion cost forecast (EAC), and project completion schedule forecast (ECD) are utilized. The results reveal a required cost of Rp 563,044,547.85 (ETC) and a 65-day timeframe (ETS) at the end of the 7th week, with a 0.64% increase in project completion cost (EAC) over the contract cost. The project completion time (EAS) is estimated at 114 days, reflecting a 0.14% extension. The analysis emphasizes the importance for construction service providers to implement efficient methods and consistent supervision to avoid delays in the Wadungasri Sidoarjo Market Drainage Normalization project.\",\"PeriodicalId\":188915,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"47 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v3i2.983\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.55047/ijateis.v3i2.983","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

Wadungasri Sidoarjo 市场排水正常化的施工项目管理旨在 100 天内实现成本、质量和时间目标。本研究针对承包商经历的 7.44% 的延误,寻求建立不良项目绩效的预警机制。研究采用了挣值法,将时间价值和成本价值概念融为一体。采用了成本差异 (CV)、进度差异 (SV)、工作效率指数 (CPI)、时间效率指数 (SPI)、项目完工成本预测 (EAC) 和项目完工进度预测 (ECD) 等关键指标。结果显示,所需成本为 563,044,547.85 印尼盾(ETC),第 7 周结束时的工期为 65 天(ETS),项目完工成本(EAC)比合同成本增加了 0.64%。项目完工时间(EAS)估计为 114 天,延长了 0.14%。该分析强调了施工服务提供商采用高效方法和连贯监督的重要性,以避免 Wadungasri Sidoarjo 市场排水正常化项目出现延误。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
ANALYSIS OF COST AND TIME PERFORMANCE IN THE WADUNGASRI MARKET CHANNEL NORMALIZATION WORK IN SIDOARJO USING THE EARNED VALUE METHOD
The construction project management for Wadungasri Sidoarjo Market Drainage Normalization aims to achieve cost, quality, and time objectives within a 100-day timeframe. This study addresses a 7.44% delay experienced by contractors, seeking to establish early warning mechanisms for poor project performance. The Earned Value Method is employed, integrating time and cost value concepts. Key indicators such as Cost Variance (CV), Schedule Variance (SV), work productivity index (CPI), time productivity index (SPI), project completion cost forecast (EAC), and project completion schedule forecast (ECD) are utilized. The results reveal a required cost of Rp 563,044,547.85 (ETC) and a 65-day timeframe (ETS) at the end of the 7th week, with a 0.64% increase in project completion cost (EAC) over the contract cost. The project completion time (EAS) is estimated at 114 days, reflecting a 0.14% extension. The analysis emphasizes the importance for construction service providers to implement efficient methods and consistent supervision to avoid delays in the Wadungasri Sidoarjo Market Drainage Normalization project.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信