卡廷安县公路分局道路项目施工延迟分析

Mey Midina Suta, Irfan Prasetia
{"title":"卡廷安县公路分局道路项目施工延迟分析","authors":"Mey Midina Suta, Irfan Prasetia","doi":"10.47577/technium.v19i.10597","DOIUrl":null,"url":null,"abstract":"ABSTRACT. This paper studied 21 road projects in Katingan Regency. In this research, nine factors were used, which were divided into 61 indicators that cause work delays. The analysis used in the research is descriptive analysis with index and variance analysis, which were previously tested for the validity and reliability of the questionnaire instrument. \nThe research results show that 3 factors are very dominant in causing work delays, namely the equipment factor with indicators of delays in providing heavy equipment or delays in delivery or provision of equipment; material factors with indicators of delays in material delivery to the project location; and other factors with natural disaster indicators. Steps to minimize delays in work implementation are: holding periodic meetings; communicating and agreeing upon the critical path in order to obtain the most efficient and effective strategy; planning and scheduling the procurement of tools, materials, and labor in terms of purchasing, transportation, and delivery times; determining appropriate routes for transportation and delivery; determining the appropriate route and means of transportation for access to the project location to suit time and cost planning; as well as the readiness of supervisory consultants in the field to supervise contractor work methods. \nKeywords: Delays in Work Implementation, Delay Factors, Roads","PeriodicalId":388226,"journal":{"name":"Technium: Romanian Journal of Applied Sciences and Technology","volume":"470 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Analysis of Delay in Implementation of Work on Road Projects in Highways Division of Katingan Regency\",\"authors\":\"Mey Midina Suta, Irfan Prasetia\",\"doi\":\"10.47577/technium.v19i.10597\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"ABSTRACT. This paper studied 21 road projects in Katingan Regency. In this research, nine factors were used, which were divided into 61 indicators that cause work delays. The analysis used in the research is descriptive analysis with index and variance analysis, which were previously tested for the validity and reliability of the questionnaire instrument. \\nThe research results show that 3 factors are very dominant in causing work delays, namely the equipment factor with indicators of delays in providing heavy equipment or delays in delivery or provision of equipment; material factors with indicators of delays in material delivery to the project location; and other factors with natural disaster indicators. Steps to minimize delays in work implementation are: holding periodic meetings; communicating and agreeing upon the critical path in order to obtain the most efficient and effective strategy; planning and scheduling the procurement of tools, materials, and labor in terms of purchasing, transportation, and delivery times; determining appropriate routes for transportation and delivery; determining the appropriate route and means of transportation for access to the project location to suit time and cost planning; as well as the readiness of supervisory consultants in the field to supervise contractor work methods. \\nKeywords: Delays in Work Implementation, Delay Factors, Roads\",\"PeriodicalId\":388226,\"journal\":{\"name\":\"Technium: Romanian Journal of Applied Sciences and Technology\",\"volume\":\"470 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Technium: Romanian Journal of Applied Sciences and Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.47577/technium.v19i.10597\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Technium: Romanian Journal of Applied Sciences and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.47577/technium.v19i.10597","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

摘要本文研究了 Katingan 地区的 21 个道路项目。研究中使用了九个因素,并将其划分为 61 个导致工程延误的指标。研究中使用的分析方法是描述性指数分析和方差分析,此前已对问卷工具的有效性和可靠性进行了测试。研究结果表明,有 3 个因素在造成工程延误方面非常主要,即设备因素,其指标是重型设备提供延误或设备交付或提供延误;材料因素,其指标是材料交付到项目地点延误;其他因素,其指标是自然灾害。尽量减少工程实施延误的步骤有:定期召开会议;沟通并商定关键路径,以获得最有效率和效果的策略;在采购、运输和交付时间方面规划和安排工具、材料和劳动力的采购;确定适当的运输和交付路线;确定进入项目地点的适当路线和运输工具,以适应时间和成本规划;以及监理顾问在现场监督承包商工作方法的准备情况。关键词工程实施延误、延误因素、道路
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Analysis of Delay in Implementation of Work on Road Projects in Highways Division of Katingan Regency
ABSTRACT. This paper studied 21 road projects in Katingan Regency. In this research, nine factors were used, which were divided into 61 indicators that cause work delays. The analysis used in the research is descriptive analysis with index and variance analysis, which were previously tested for the validity and reliability of the questionnaire instrument. The research results show that 3 factors are very dominant in causing work delays, namely the equipment factor with indicators of delays in providing heavy equipment or delays in delivery or provision of equipment; material factors with indicators of delays in material delivery to the project location; and other factors with natural disaster indicators. Steps to minimize delays in work implementation are: holding periodic meetings; communicating and agreeing upon the critical path in order to obtain the most efficient and effective strategy; planning and scheduling the procurement of tools, materials, and labor in terms of purchasing, transportation, and delivery times; determining appropriate routes for transportation and delivery; determining the appropriate route and means of transportation for access to the project location to suit time and cost planning; as well as the readiness of supervisory consultants in the field to supervise contractor work methods. Keywords: Delays in Work Implementation, Delay Factors, Roads
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信