{"title":"桩基施工的工期优化模型","authors":"Kenneth Miebaka Oba","doi":"10.55524/ijirem.2024.11.1.7","DOIUrl":null,"url":null,"abstract":"Time and adequate management of the scheduling of activities are very critical in every construction project. This study formulated a multiple linear regression optimization model to address issues bordering on delays in pile construction operations. A 300mm diameter reinforced concrete pile, 5.4m long, with a plastic casing was used. A total of 32 piles were constructed in a silty soil completely submerged in water at Bonny, Nigeria. The friction piles were constructed serially with a boring method, while the soil was extracted with the piling auger. The volumes of the extracted soil and concrete poured to fill the holes were accounted for, theoretically and actually. The same was done for the reinforcement cages installed in each pile shaft. The model was formulated and tested using Statistical Package for the Social Sciences (SPSS) software. The model was found to be fit, adequate, and highly accurate with an R2 value of 0.874.","PeriodicalId":507949,"journal":{"name":"International Journal of Innovative Research in Engineering and Management","volume":"19 11","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-02-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"A Time Duration Optimization Model for the Construction of Piles\",\"authors\":\"Kenneth Miebaka Oba\",\"doi\":\"10.55524/ijirem.2024.11.1.7\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Time and adequate management of the scheduling of activities are very critical in every construction project. This study formulated a multiple linear regression optimization model to address issues bordering on delays in pile construction operations. A 300mm diameter reinforced concrete pile, 5.4m long, with a plastic casing was used. A total of 32 piles were constructed in a silty soil completely submerged in water at Bonny, Nigeria. The friction piles were constructed serially with a boring method, while the soil was extracted with the piling auger. The volumes of the extracted soil and concrete poured to fill the holes were accounted for, theoretically and actually. The same was done for the reinforcement cages installed in each pile shaft. The model was formulated and tested using Statistical Package for the Social Sciences (SPSS) software. The model was found to be fit, adequate, and highly accurate with an R2 value of 0.874.\",\"PeriodicalId\":507949,\"journal\":{\"name\":\"International Journal of Innovative Research in Engineering and Management\",\"volume\":\"19 11\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-02-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Innovative Research in Engineering and Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.55524/ijirem.2024.11.1.7\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Innovative Research in Engineering and Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.55524/ijirem.2024.11.1.7","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

时间和活动安排的充分管理在每个建筑项目中都非常关键。本研究制定了一个多线性回归优化模型,以解决桩基施工作业中的延迟问题。研究使用了直径为 300 毫米、长 5.4 米、带有塑料护筒的钢筋混凝土桩。在尼日利亚邦尼完全浸没在水中的淤泥中总共打了 32 根桩。摩擦桩采用钻孔法连续施工,而泥土则用打桩钻抽取。从理论和实际角度计算了抽取的土壤和浇筑的混凝土的体积。每个桩井中安装的钢筋笼也是如此。该模型是使用社会科学统计软件包 (SPSS) 建立和测试的。结果发现,该模型拟合、充分且高度准确,R2 值为 0.874。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A Time Duration Optimization Model for the Construction of Piles
Time and adequate management of the scheduling of activities are very critical in every construction project. This study formulated a multiple linear regression optimization model to address issues bordering on delays in pile construction operations. A 300mm diameter reinforced concrete pile, 5.4m long, with a plastic casing was used. A total of 32 piles were constructed in a silty soil completely submerged in water at Bonny, Nigeria. The friction piles were constructed serially with a boring method, while the soil was extracted with the piling auger. The volumes of the extracted soil and concrete poured to fill the holes were accounted for, theoretically and actually. The same was done for the reinforcement cages installed in each pile shaft. The model was formulated and tested using Statistical Package for the Social Sciences (SPSS) software. The model was found to be fit, adequate, and highly accurate with an R2 value of 0.874.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信