{"title":"在Maury 500-kV GIS设施扩建期间保持区域可靠性","authors":"Randal Petty","doi":"10.1109/ichve.2010.5640792","DOIUrl":null,"url":null,"abstract":"Staged expansion of 500-kV GIS switchgear was completed at the Maury 500-kV Substation without impact to system performance based upon proper planning and execution of the work being performed.","PeriodicalId":287425,"journal":{"name":"2010 International Conference on High Voltage Engineering and Application","volume":"22 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2010-11-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Maintaining regional reliability during expansion of the Maury 500-kV GIS facility\",\"authors\":\"Randal Petty\",\"doi\":\"10.1109/ichve.2010.5640792\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Staged expansion of 500-kV GIS switchgear was completed at the Maury 500-kV Substation without impact to system performance based upon proper planning and execution of the work being performed.\",\"PeriodicalId\":287425,\"journal\":{\"name\":\"2010 International Conference on High Voltage Engineering and Application\",\"volume\":\"22 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2010-11-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2010 International Conference on High Voltage Engineering and Application\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ichve.2010.5640792\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2010 International Conference on High Voltage Engineering and Application","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ichve.2010.5640792","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Maintaining regional reliability during expansion of the Maury 500-kV GIS facility
Staged expansion of 500-kV GIS switchgear was completed at the Maury 500-kV Substation without impact to system performance based upon proper planning and execution of the work being performed.