{"title":"110、220千伏4号室外开关柜电站主方案可靠性研究","authors":"D. Sodnomdorj, N. Enkhmunkh","doi":"10.1109/IFOST.2012.6357690","DOIUrl":null,"url":null,"abstract":"In this paper to determine the reliable operation of main characteristics of power plant No4's outdoor switchgear main scheme method is produced. Also the reliable operation of power plant No4's 110, 220 kV-s main scheme of element's are researched and the all variants of commutation in operation is make and reliability research is done. And characteristics of reliable operations are determined.","PeriodicalId":319762,"journal":{"name":"2012 7th International Forum on Strategic Technology (IFOST)","volume":"8 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2012-11-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Research on reliability of main scheme of 110, 220 kV outdoor switchgear power plant №4's\",\"authors\":\"D. Sodnomdorj, N. Enkhmunkh\",\"doi\":\"10.1109/IFOST.2012.6357690\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this paper to determine the reliable operation of main characteristics of power plant No4's outdoor switchgear main scheme method is produced. Also the reliable operation of power plant No4's 110, 220 kV-s main scheme of element's are researched and the all variants of commutation in operation is make and reliability research is done. And characteristics of reliable operations are determined.\",\"PeriodicalId\":319762,\"journal\":{\"name\":\"2012 7th International Forum on Strategic Technology (IFOST)\",\"volume\":\"8 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2012-11-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2012 7th International Forum on Strategic Technology (IFOST)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/IFOST.2012.6357690\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2012 7th International Forum on Strategic Technology (IFOST)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/IFOST.2012.6357690","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Research on reliability of main scheme of 110, 220 kV outdoor switchgear power plant №4's
In this paper to determine the reliable operation of main characteristics of power plant No4's outdoor switchgear main scheme method is produced. Also the reliable operation of power plant No4's 110, 220 kV-s main scheme of element's are researched and the all variants of commutation in operation is make and reliability research is done. And characteristics of reliable operations are determined.