{"title":"10兆瓦/次/薄膜光伏组件一体化工厂的启动和运行","authors":"D. Bonnet, S. Oelting, M. Harr, S. Will","doi":"10.1109/PVSC.2002.1190627","DOIUrl":null,"url":null,"abstract":"ANTEC Solar GmbH has entered production of thin film solar modules on a scale of 100,000 m/sup 2/ per year, using closed-spaced sublimation as the deposition technique for the semiconductor films and high-rate in-line sputtering for transparent and opaque contacts. The standard module size is 60 /spl times/ 120 cm/sup 2/. The equipment has been built, installed and integrated in 2000, start-up phase has been finished in September 2001. Full capacity of 11,000 modules per month will be achieved during the second half of 2002. The line operates 24 hours per day for seven days per week, allowing for one service shift to replenish consumed materials. The line presently has a cycle time of 120 s, which is planned to be decreased to the nominal value of 90 s. Efficiencies of the CdS/CdTe standard modules are about 7%, expected to rise continuously with time.","PeriodicalId":177538,"journal":{"name":"Conference Record of the Twenty-Ninth IEEE Photovoltaic Specialists Conference, 2002.","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2002-05-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"Start-up and operation of an integrated 10 MW/sub p/ thin film PV module factory\",\"authors\":\"D. Bonnet, S. Oelting, M. Harr, S. Will\",\"doi\":\"10.1109/PVSC.2002.1190627\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"ANTEC Solar GmbH has entered production of thin film solar modules on a scale of 100,000 m/sup 2/ per year, using closed-spaced sublimation as the deposition technique for the semiconductor films and high-rate in-line sputtering for transparent and opaque contacts. The standard module size is 60 /spl times/ 120 cm/sup 2/. The equipment has been built, installed and integrated in 2000, start-up phase has been finished in September 2001. Full capacity of 11,000 modules per month will be achieved during the second half of 2002. The line operates 24 hours per day for seven days per week, allowing for one service shift to replenish consumed materials. The line presently has a cycle time of 120 s, which is planned to be decreased to the nominal value of 90 s. Efficiencies of the CdS/CdTe standard modules are about 7%, expected to rise continuously with time.\",\"PeriodicalId\":177538,\"journal\":{\"name\":\"Conference Record of the Twenty-Ninth IEEE Photovoltaic Specialists Conference, 2002.\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2002-05-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Conference Record of the Twenty-Ninth IEEE Photovoltaic Specialists Conference, 2002.\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/PVSC.2002.1190627\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Conference Record of the Twenty-Ninth IEEE Photovoltaic Specialists Conference, 2002.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PVSC.2002.1190627","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3
摘要
ANTEC Solar GmbH已进入薄膜太阳能组件的生产,其规模为每年100,000 m/sup / /,采用封闭间隔的热沉技术作为半导体薄膜的沉积技术,并采用高速率的在线溅射技术用于透明和不透明的接触。标准模块尺寸为60 /spl倍/ 120厘米/sup 2/。设备于2000年建成、安装、集成,2001年9月完成启动阶段。2002年下半年将达到每月11,000个组件的满负荷生产能力。这条生产线每周7天每天24小时运行,允许一次服务班次来补充消耗的材料。该生产线目前的循环时间为120秒,计划将其减少到90秒的标称值。cd /CdTe标准模块的效率约为7%,预计将随着时间的推移不断提高。
Start-up and operation of an integrated 10 MW/sub p/ thin film PV module factory
ANTEC Solar GmbH has entered production of thin film solar modules on a scale of 100,000 m/sup 2/ per year, using closed-spaced sublimation as the deposition technique for the semiconductor films and high-rate in-line sputtering for transparent and opaque contacts. The standard module size is 60 /spl times/ 120 cm/sup 2/. The equipment has been built, installed and integrated in 2000, start-up phase has been finished in September 2001. Full capacity of 11,000 modules per month will be achieved during the second half of 2002. The line operates 24 hours per day for seven days per week, allowing for one service shift to replenish consumed materials. The line presently has a cycle time of 120 s, which is planned to be decreased to the nominal value of 90 s. Efficiencies of the CdS/CdTe standard modules are about 7%, expected to rise continuously with time.