{"title":"克罗地亚海运货物单一窗口系统开发中的风险管理","authors":"S. Aksentijević, E. Tijan, Kristijan Nikolozo, A. Hadzic","doi":"10.23919/MIPRO57284.2023.10159978","DOIUrl":null,"url":null,"abstract":"The aim of this paper is to research and describe the effectiveness of the risk management approach used during implementation of the Croatian national maritime Single Window system related to cargo, or Port Community System, initially in the port of Rijeka. The primary stakeholders and their internal systems, as well as formal development requirements, are defined. Project risk is identified within the project management framework’s criteria, and the project’s execution and important milestones, including risk occurrences during project execution, are recognized and discussed. Finally, modifications to the approach are suggested, as well as future study opportunities.","PeriodicalId":177983,"journal":{"name":"2023 46th MIPRO ICT and Electronics Convention (MIPRO)","volume":"64 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-05-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Risk Management in Development of Croatian Maritime Cargo Single Window System\",\"authors\":\"S. Aksentijević, E. Tijan, Kristijan Nikolozo, A. Hadzic\",\"doi\":\"10.23919/MIPRO57284.2023.10159978\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The aim of this paper is to research and describe the effectiveness of the risk management approach used during implementation of the Croatian national maritime Single Window system related to cargo, or Port Community System, initially in the port of Rijeka. The primary stakeholders and their internal systems, as well as formal development requirements, are defined. Project risk is identified within the project management framework’s criteria, and the project’s execution and important milestones, including risk occurrences during project execution, are recognized and discussed. Finally, modifications to the approach are suggested, as well as future study opportunities.\",\"PeriodicalId\":177983,\"journal\":{\"name\":\"2023 46th MIPRO ICT and Electronics Convention (MIPRO)\",\"volume\":\"64 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-05-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2023 46th MIPRO ICT and Electronics Convention (MIPRO)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.23919/MIPRO57284.2023.10159978\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2023 46th MIPRO ICT and Electronics Convention (MIPRO)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.23919/MIPRO57284.2023.10159978","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本文的目的是研究和描述在实施克罗地亚国家海事单一窗口系统期间使用的风险管理方法的有效性,该系统与货物有关,或港口社区系统,最初在里耶卡港。确定了主要涉众及其内部系统,以及正式的开发需求。项目风险在项目管理框架的准则中被识别,项目的执行和重要的里程碑,包括项目执行过程中发生的风险,被识别和讨论。最后,提出了改进的建议,以及未来的研究机会。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Risk Management in Development of Croatian Maritime Cargo Single Window System
The aim of this paper is to research and describe the effectiveness of the risk management approach used during implementation of the Croatian national maritime Single Window system related to cargo, or Port Community System, initially in the port of Rijeka. The primary stakeholders and their internal systems, as well as formal development requirements, are defined. Project risk is identified within the project management framework’s criteria, and the project’s execution and important milestones, including risk occurrences during project execution, are recognized and discussed. Finally, modifications to the approach are suggested, as well as future study opportunities.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信