{"title":"重大资本项目的4D模拟关键度可视化","authors":"Michel Guévremont, A. Hammad","doi":"10.1109/WSC.2017.8247966","DOIUrl":null,"url":null,"abstract":"In construction, major capital projects are in need of a visualization method for scheduling and integrating the spatial dimensions with the time dimension. Traditional scheduling methods are limited to the time dimension, and can be used to visualize the critical path of schedules and to compare the criticality of activities. However, they do not consider the spatial constraints. This paper describes a method for developing 4D simulation to visualize the criticality of project activities considering the requirements of the levels of detail. The 4D visualization interface shows the criticality of activities linked to components with color coding based on the total float of each activity. Important benefits can be achieved in supporting decision-making associated with understanding the spatio-temporal constraints related to multiple contracts. Furthermore, the proposed method is useful for filtering, viewing critical and near critical activities, and comparing schedules. The method is tested in a hydroelectric powerhouse case study.","PeriodicalId":145780,"journal":{"name":"2017 Winter Simulation Conference (WSC)","volume":"69 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-12-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Criticality visualization using 4D simulation for major capital projects\",\"authors\":\"Michel Guévremont, A. Hammad\",\"doi\":\"10.1109/WSC.2017.8247966\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In construction, major capital projects are in need of a visualization method for scheduling and integrating the spatial dimensions with the time dimension. Traditional scheduling methods are limited to the time dimension, and can be used to visualize the critical path of schedules and to compare the criticality of activities. However, they do not consider the spatial constraints. This paper describes a method for developing 4D simulation to visualize the criticality of project activities considering the requirements of the levels of detail. The 4D visualization interface shows the criticality of activities linked to components with color coding based on the total float of each activity. Important benefits can be achieved in supporting decision-making associated with understanding the spatio-temporal constraints related to multiple contracts. Furthermore, the proposed method is useful for filtering, viewing critical and near critical activities, and comparing schedules. The method is tested in a hydroelectric powerhouse case study.\",\"PeriodicalId\":145780,\"journal\":{\"name\":\"2017 Winter Simulation Conference (WSC)\",\"volume\":\"69 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-12-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2017 Winter Simulation Conference (WSC)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/WSC.2017.8247966\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2017 Winter Simulation Conference (WSC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/WSC.2017.8247966","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

在建设中,重大基建项目需要一种可视化的方法来调度和整合空间维度和时间维度。传统的调度方法局限于时间维度,只能可视化调度的关键路径和比较活动的关键程度。然而,他们没有考虑到空间的限制。本文描述了一种开发4D模拟的方法,以可视化项目活动的关键程度,考虑到细节层次的要求。4D可视化界面根据每个活动的总浮动,用颜色编码显示与组件关联的活动的临界程度。通过理解与多个合同相关的时空约束,可以在支持决策方面获得重要的好处。此外,该方法可用于过滤、查看关键和接近关键的活动以及比较调度。该方法在某水电站实例中得到了验证。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Criticality visualization using 4D simulation for major capital projects
In construction, major capital projects are in need of a visualization method for scheduling and integrating the spatial dimensions with the time dimension. Traditional scheduling methods are limited to the time dimension, and can be used to visualize the critical path of schedules and to compare the criticality of activities. However, they do not consider the spatial constraints. This paper describes a method for developing 4D simulation to visualize the criticality of project activities considering the requirements of the levels of detail. The 4D visualization interface shows the criticality of activities linked to components with color coding based on the total float of each activity. Important benefits can be achieved in supporting decision-making associated with understanding the spatio-temporal constraints related to multiple contracts. Furthermore, the proposed method is useful for filtering, viewing critical and near critical activities, and comparing schedules. The method is tested in a hydroelectric powerhouse case study.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信