{"title":"Takt计划中的缓冲区管理- Takt系统中的缓冲区概述","authors":"J. Dlouhy, M. Binninger, Shervin Haghsheno","doi":"10.24928/2019/0226","DOIUrl":null,"url":null,"abstract":"Takt Planning and Takt Control (TPTC) as a method for construction has the potential to reduce construction time in relation to normal scheduling without the increase of manpower. This leads to the question: what changes with the use of Takt planning? One theory is that Takt planning is using buffers more effectively than other schedule and planning methods. This paper provides an overview of the various buffers in Takt planning and describes how they can be used.","PeriodicalId":278113,"journal":{"name":"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)","volume":"39 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-07-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"10","resultStr":"{\"title\":\"Buffer Management in Takt Planning – An Overview of Buffers in Takt Systems\",\"authors\":\"J. Dlouhy, M. Binninger, Shervin Haghsheno\",\"doi\":\"10.24928/2019/0226\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Takt Planning and Takt Control (TPTC) as a method for construction has the potential to reduce construction time in relation to normal scheduling without the increase of manpower. This leads to the question: what changes with the use of Takt planning? One theory is that Takt planning is using buffers more effectively than other schedule and planning methods. This paper provides an overview of the various buffers in Takt planning and describes how they can be used.\",\"PeriodicalId\":278113,\"journal\":{\"name\":\"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)\",\"volume\":\"39 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-07-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"10\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.24928/2019/0226\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24928/2019/0226","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Buffer Management in Takt Planning – An Overview of Buffers in Takt Systems
Takt Planning and Takt Control (TPTC) as a method for construction has the potential to reduce construction time in relation to normal scheduling without the increase of manpower. This leads to the question: what changes with the use of Takt planning? One theory is that Takt planning is using buffers more effectively than other schedule and planning methods. This paper provides an overview of the various buffers in Takt planning and describes how they can be used.