{"title":"应用数学模型在住宅开发项目建设规划中的应用","authors":"Grit Ngowtanasuwan","doi":"10.21834/AJBES.V3I13.140","DOIUrl":null,"url":null,"abstract":"The paper presented a method for solving a construction planning problem in a housing development project using a mathematical model which is an integer linear programming for dividing house construction jobs to three contractors in a project case study. 169 units of the houses in the project would be constructed by the three contractors in two methods, conventional construction method and precast method. The results found a minimum construction cost of the project was 417.69 million baht (M$13.92), and within the total project duration of 72 months. Conclusions and recommendations were discussed in this article.Keywords: Housing Development Project, Mathematical Model, Precast Concrete Construction.eISSN 2398-4295 © 2018. The Authors. Published for AMER ABRA cE-Bs by e-International Publishing House, Ltd., UK. This is an open-access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/). Peer–review under responsibility of AMER (Association of Malaysian Environment-Behaviour Researchers), ABRA (Association of Behavioural Researchers on Asians) and cE-Bs (Centre for Environment-Behaviour Studies), Faculty of Architecture, Planning & Surveying, Universiti Teknologi MARA, Malaysia. DOI: http://dx.doi.org/10.21834/ajbes.v3i13.140","PeriodicalId":439477,"journal":{"name":"Asian Journal of Behavioural Studies","volume":"12 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-08-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Applied Mathematical Model for Construction Planning in a Housing Development Project\",\"authors\":\"Grit Ngowtanasuwan\",\"doi\":\"10.21834/AJBES.V3I13.140\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The paper presented a method for solving a construction planning problem in a housing development project using a mathematical model which is an integer linear programming for dividing house construction jobs to three contractors in a project case study. 169 units of the houses in the project would be constructed by the three contractors in two methods, conventional construction method and precast method. The results found a minimum construction cost of the project was 417.69 million baht (M$13.92), and within the total project duration of 72 months. Conclusions and recommendations were discussed in this article.Keywords: Housing Development Project, Mathematical Model, Precast Concrete Construction.eISSN 2398-4295 © 2018. The Authors. Published for AMER ABRA cE-Bs by e-International Publishing House, Ltd., UK. This is an open-access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/). Peer–review under responsibility of AMER (Association of Malaysian Environment-Behaviour Researchers), ABRA (Association of Behavioural Researchers on Asians) and cE-Bs (Centre for Environment-Behaviour Studies), Faculty of Architecture, Planning & Surveying, Universiti Teknologi MARA, Malaysia. DOI: http://dx.doi.org/10.21834/ajbes.v3i13.140\",\"PeriodicalId\":439477,\"journal\":{\"name\":\"Asian Journal of Behavioural Studies\",\"volume\":\"12 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-08-25\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Asian Journal of Behavioural Studies\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21834/AJBES.V3I13.140\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Asian Journal of Behavioural Studies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21834/AJBES.V3I13.140","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
Applied Mathematical Model for Construction Planning in a Housing Development Project
The paper presented a method for solving a construction planning problem in a housing development project using a mathematical model which is an integer linear programming for dividing house construction jobs to three contractors in a project case study. 169 units of the houses in the project would be constructed by the three contractors in two methods, conventional construction method and precast method. The results found a minimum construction cost of the project was 417.69 million baht (M$13.92), and within the total project duration of 72 months. Conclusions and recommendations were discussed in this article.Keywords: Housing Development Project, Mathematical Model, Precast Concrete Construction.eISSN 2398-4295 © 2018. The Authors. Published for AMER ABRA cE-Bs by e-International Publishing House, Ltd., UK. This is an open-access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/). Peer–review under responsibility of AMER (Association of Malaysian Environment-Behaviour Researchers), ABRA (Association of Behavioural Researchers on Asians) and cE-Bs (Centre for Environment-Behaviour Studies), Faculty of Architecture, Planning & Surveying, Universiti Teknologi MARA, Malaysia. DOI: http://dx.doi.org/10.21834/ajbes.v3i13.140