本厂原料药工艺中耐火砖材料混合过程的时间分析

Andika Puji Wirawan, Z. Arief
{"title":"本厂原料药工艺中耐火砖材料混合过程的时间分析","authors":"Andika Puji Wirawan, Z. Arief","doi":"10.55047/ijateis.v1i2.237","DOIUrl":null,"url":null,"abstract":"PT. Benteng Api Technic is a leading refractory company in Indonesia with refractory bricks as one of its superior products. The process of making refractory bricks that will be observed in this study is the process of mixing materials and the molding process. In the mixing process, there are no tools in the form of time indicators to help operators make decisions about the mixing time of ingredients. This research aims to obtain the time for the mixing of materials with maximum mixing quality and to support the press process optimally. The research was conducted using a perfectly randomized experimental design in order to obtain different mixing results based on the nine selected mixing time treatments. Measurement of working time is carried out using the stopwatch time study method on press operators who are experienced in their fields. Calculations to align the two processes using a Gantt chart with idle time as an indicator. The experimental results revealed that the most optimal mixing with a mixing time of 12 minutes resulted in 7.2 kilograms of mass that did not pass through an 18 mesh sieve. Based on the results of the gantt chart, the use of 11 mixing time for material B resulted in the lowest idle time of 178 minutes. The processing time obtained is expected to be used as a guide in determining the time input on the time indicator tool in the process of mixing refractory bricks.","PeriodicalId":188915,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","volume":"60 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-07-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"TIME ANALYSIS OF THE MIXING PROCESS OF FIRE BRICK MATERIALS IN PT. BENTENG API TECHNIC GRESIK\",\"authors\":\"Andika Puji Wirawan, Z. Arief\",\"doi\":\"10.55047/ijateis.v1i2.237\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"PT. Benteng Api Technic is a leading refractory company in Indonesia with refractory bricks as one of its superior products. The process of making refractory bricks that will be observed in this study is the process of mixing materials and the molding process. In the mixing process, there are no tools in the form of time indicators to help operators make decisions about the mixing time of ingredients. This research aims to obtain the time for the mixing of materials with maximum mixing quality and to support the press process optimally. The research was conducted using a perfectly randomized experimental design in order to obtain different mixing results based on the nine selected mixing time treatments. Measurement of working time is carried out using the stopwatch time study method on press operators who are experienced in their fields. Calculations to align the two processes using a Gantt chart with idle time as an indicator. The experimental results revealed that the most optimal mixing with a mixing time of 12 minutes resulted in 7.2 kilograms of mass that did not pass through an 18 mesh sieve. Based on the results of the gantt chart, the use of 11 mixing time for material B resulted in the lowest idle time of 178 minutes. The processing time obtained is expected to be used as a guide in determining the time input on the time indicator tool in the process of mixing refractory bricks.\",\"PeriodicalId\":188915,\"journal\":{\"name\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)\",\"volume\":\"60 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-07-12\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.55047/ijateis.v1i2.237\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.55047/ijateis.v1i2.237","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

PT. Benteng Api technology是印尼领先的耐火材料公司,耐火砖是其优势产品之一。本研究将观察到的耐火砖的制作过程是材料的混合过程和成型过程。在混合过程中,没有时间指标形式的工具来帮助操作人员对配料的混合时间进行决策。本研究的目的是获得物料的混合时间与最大的混合质量,并支持最佳的压制过程。为了获得不同混合时间处理下的混合结果,采用了完全随机化的实验设计。工作时间的测量是用秒表时间研究方法对在各自领域有经验的压力机操作人员进行的。使用空闲时间作为指示器的甘特图来对齐两个进程的计算。实验结果表明,当混合时间为12分钟时,最佳混合时间为7.2 kg,未通过18目筛。根据甘特图的结果,B物料使用11混合时间,空闲时间最低,为178分钟。所得到的加工时间有望作为确定混合耐火砖过程中时间指示工具上的时间输入的指导。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
TIME ANALYSIS OF THE MIXING PROCESS OF FIRE BRICK MATERIALS IN PT. BENTENG API TECHNIC GRESIK
PT. Benteng Api Technic is a leading refractory company in Indonesia with refractory bricks as one of its superior products. The process of making refractory bricks that will be observed in this study is the process of mixing materials and the molding process. In the mixing process, there are no tools in the form of time indicators to help operators make decisions about the mixing time of ingredients. This research aims to obtain the time for the mixing of materials with maximum mixing quality and to support the press process optimally. The research was conducted using a perfectly randomized experimental design in order to obtain different mixing results based on the nine selected mixing time treatments. Measurement of working time is carried out using the stopwatch time study method on press operators who are experienced in their fields. Calculations to align the two processes using a Gantt chart with idle time as an indicator. The experimental results revealed that the most optimal mixing with a mixing time of 12 minutes resulted in 7.2 kilograms of mass that did not pass through an 18 mesh sieve. Based on the results of the gantt chart, the use of 11 mixing time for material B resulted in the lowest idle time of 178 minutes. The processing time obtained is expected to be used as a guide in determining the time input on the time indicator tool in the process of mixing refractory bricks.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信