无排气冷却器的气举压缩机在Handil油田的运行- Pertamina Hulu Mahakam

S. Sia
{"title":"无排气冷却器的气举压缩机在Handil油田的运行- Pertamina Hulu Mahakam","authors":"S. Sia","doi":"10.29118/ipa22-f-149","DOIUrl":null,"url":null,"abstract":"Handil is a mature oil field in Mahakam Block which has been producing for more than 45 years. Following its depletion challenge, more than 90% of Handil’s oil production relies mainly on gas lift, which is circulated from Compressor in the process area. The HEOR (Handil Enhanced Oil Recovery) Compressor is one of the compressors used to supply gas lift in Handil field. HEOR is equipped with two air coolers, namely the interstage cooler (E-5550) and discharge cooler (E-5530). Based on inspection findings, the discharge cooler E-5530 is leaking and out of service. Consequently, HEOR compressor cannot be operated, thereby reducing the rate of gas lift to field and resulting to lower oil production from Handil field. Further study was then carried out to review the feasibility of running the HEOR compressor without its discharge cooler (discharge cooler operation by-passed). Several efforts were performed to ensure the process safety condition as follows: Jumper line size to ensure the deliverability of gas lift rate. The existing 6” jumper line with a rating 1500# is capable to deliver 48 MMscfd with potential debottlenecking to 8” line with a capacity of 86 MMscfd; Stress analysis on piping & pipeline is performed to review the impact of increasing temperature; Water condensation study along the pipeline discharge cooler to check the Top of Line Corrosion (ToLC) issue; Corrosion mitigations with sampling liquid (e.g. pH analysis) and corrosion monitoring requirement (e.g. routine UT measurement at critical sections and chemical injection on critical points as per sampling result); Field trial of the by-pass discharge cooler by utilizing existing configuration were carried out to examine the temperature profile along the pipeline and its impact on the performance of HEOR compressor. The new philosophy of running HEOR compressor without discharge cooler was successfully implemented in the Handil field. The modification is succeeded to boost oil production up to 2,000 bopd thanks to great collaboration among engineering, production method, and site Operation team. All efforts from engineering studies up to implementation in the field are a good lesson learns that can be implemented to other oil and gas field.","PeriodicalId":442360,"journal":{"name":"Proceedings of Indonesian Petroleum Association, 46th Annual Convention & Exhibition, 2022","volume":"13 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-09-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Operation of Gas Lift Compressor Without Discharge Cooler in Handil Field – Pertamina Hulu Mahakam\",\"authors\":\"S. Sia\",\"doi\":\"10.29118/ipa22-f-149\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Handil is a mature oil field in Mahakam Block which has been producing for more than 45 years. Following its depletion challenge, more than 90% of Handil’s oil production relies mainly on gas lift, which is circulated from Compressor in the process area. The HEOR (Handil Enhanced Oil Recovery) Compressor is one of the compressors used to supply gas lift in Handil field. HEOR is equipped with two air coolers, namely the interstage cooler (E-5550) and discharge cooler (E-5530). Based on inspection findings, the discharge cooler E-5530 is leaking and out of service. Consequently, HEOR compressor cannot be operated, thereby reducing the rate of gas lift to field and resulting to lower oil production from Handil field. Further study was then carried out to review the feasibility of running the HEOR compressor without its discharge cooler (discharge cooler operation by-passed). Several efforts were performed to ensure the process safety condition as follows: Jumper line size to ensure the deliverability of gas lift rate. The existing 6” jumper line with a rating 1500# is capable to deliver 48 MMscfd with potential debottlenecking to 8” line with a capacity of 86 MMscfd; Stress analysis on piping & pipeline is performed to review the impact of increasing temperature; Water condensation study along the pipeline discharge cooler to check the Top of Line Corrosion (ToLC) issue; Corrosion mitigations with sampling liquid (e.g. pH analysis) and corrosion monitoring requirement (e.g. routine UT measurement at critical sections and chemical injection on critical points as per sampling result); Field trial of the by-pass discharge cooler by utilizing existing configuration were carried out to examine the temperature profile along the pipeline and its impact on the performance of HEOR compressor. The new philosophy of running HEOR compressor without discharge cooler was successfully implemented in the Handil field. The modification is succeeded to boost oil production up to 2,000 bopd thanks to great collaboration among engineering, production method, and site Operation team. All efforts from engineering studies up to implementation in the field are a good lesson learns that can be implemented to other oil and gas field.\",\"PeriodicalId\":442360,\"journal\":{\"name\":\"Proceedings of Indonesian Petroleum Association, 46th Annual Convention & Exhibition, 2022\",\"volume\":\"13 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-09-21\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of Indonesian Petroleum Association, 46th Annual Convention & Exhibition, 2022\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.29118/ipa22-f-149\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of Indonesian Petroleum Association, 46th Annual Convention & Exhibition, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29118/ipa22-f-149","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

Handil是Mahakam区块的一个成熟油田,已经生产了45年以上。在面临枯竭挑战之后,Handil超过90%的石油生产主要依靠气举,气举从工艺区域的压缩机中循环。汉迪尔油田提高采收率压缩机(HEOR)是汉迪尔油田用于气举的压缩机之一。HEOR配有两个空气冷却器,即级间冷却器(E-5550)和排气冷却器(E-5530)。根据检查结果,排气冷却器E-5530发生泄漏,不能使用。因此,HEOR压缩机无法运行,从而降低了气举到现场的速度,导致Handil油田的产油量下降。在此基础上,进一步研究了不带排气冷却器(旁路排气冷却器)运行HEOR压缩机的可行性。为确保工艺安全条件,进行了以下几方面的努力:跳线尺寸确保气举率的可交付性。现有的6”跳线额定容量为1500#,能够输送48 MMscfd,并有可能突破8”线的瓶颈,容量为86 MMscfd;对管道和管道进行应力分析,以审查温度升高的影响;沿管道排放冷却器冷凝水研究,检查线顶腐蚀(ToLC)问题;通过取样液体(例如pH分析)和腐蚀监测要求(例如在关键部分进行常规UT测量,并根据取样结果在关键点进行化学注射)减轻腐蚀;利用现有配置对旁通排气冷却器进行了现场试验,考察了管道沿线的温度分布及其对HEOR压缩机性能的影响。无排气冷却器运行HEOR压缩机的新理念在Handil油田成功实施。由于工程、生产方法和现场操作团队的通力合作,改造成功将石油产量提高到2000桶/天。从工程研究到现场实施的所有努力都是一个很好的经验教训,可以应用到其他油气田。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Operation of Gas Lift Compressor Without Discharge Cooler in Handil Field – Pertamina Hulu Mahakam
Handil is a mature oil field in Mahakam Block which has been producing for more than 45 years. Following its depletion challenge, more than 90% of Handil’s oil production relies mainly on gas lift, which is circulated from Compressor in the process area. The HEOR (Handil Enhanced Oil Recovery) Compressor is one of the compressors used to supply gas lift in Handil field. HEOR is equipped with two air coolers, namely the interstage cooler (E-5550) and discharge cooler (E-5530). Based on inspection findings, the discharge cooler E-5530 is leaking and out of service. Consequently, HEOR compressor cannot be operated, thereby reducing the rate of gas lift to field and resulting to lower oil production from Handil field. Further study was then carried out to review the feasibility of running the HEOR compressor without its discharge cooler (discharge cooler operation by-passed). Several efforts were performed to ensure the process safety condition as follows: Jumper line size to ensure the deliverability of gas lift rate. The existing 6” jumper line with a rating 1500# is capable to deliver 48 MMscfd with potential debottlenecking to 8” line with a capacity of 86 MMscfd; Stress analysis on piping & pipeline is performed to review the impact of increasing temperature; Water condensation study along the pipeline discharge cooler to check the Top of Line Corrosion (ToLC) issue; Corrosion mitigations with sampling liquid (e.g. pH analysis) and corrosion monitoring requirement (e.g. routine UT measurement at critical sections and chemical injection on critical points as per sampling result); Field trial of the by-pass discharge cooler by utilizing existing configuration were carried out to examine the temperature profile along the pipeline and its impact on the performance of HEOR compressor. The new philosophy of running HEOR compressor without discharge cooler was successfully implemented in the Handil field. The modification is succeeded to boost oil production up to 2,000 bopd thanks to great collaboration among engineering, production method, and site Operation team. All efforts from engineering studies up to implementation in the field are a good lesson learns that can be implemented to other oil and gas field.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信