基于EDAM方法的建筑工程关键路径变更和并发延迟识别

Z. R. Kamandang
{"title":"基于EDAM方法的建筑工程关键路径变更和并发延迟识别","authors":"Z. R. Kamandang","doi":"10.31284/J.JASMET.2020.V1I1.867","DOIUrl":null,"url":null,"abstract":"Achieving a project whose punctually in completion date and duration is one of the main purposes of the project planning. However, avoiding the issue of the delay is hard to do. Delays itself commonly divided into three types, EN, EC and NE delays that represent the contribution of each project parties. Furthermore, the concurrent delay is at different levels that often use as a tool against each other parties. In term of preventing the time-frame problems, the critical path method (CPM) is widely applied. In the delay analysis technique, the EDAM method employs CPM to identify the critical path changes and the occurred concurrent delays. Implementing a six-floor building as-planned schedule and its delays information as a case study, this research results show that the critical path of the building has changed eight times and the concurrent delay occurred on the first change with six days of delays. By identifying the critical path change, project parties are expected to be able to prevent continuously delays by escalating the work progress. Furthermore, the information about concurrent delays would be essential in avoiding disputes regarding this issue. Project parties would be aware of their contribution to critical path changes by knowing their caused delay in that time period.","PeriodicalId":426640,"journal":{"name":"Journal of Applied Sciences, Management and Engineering Technology","volume":"13 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-02-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Identification of Critical Path Changes and Concurrent Delays Using EDAM Method for Building Project\",\"authors\":\"Z. R. Kamandang\",\"doi\":\"10.31284/J.JASMET.2020.V1I1.867\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Achieving a project whose punctually in completion date and duration is one of the main purposes of the project planning. However, avoiding the issue of the delay is hard to do. Delays itself commonly divided into three types, EN, EC and NE delays that represent the contribution of each project parties. Furthermore, the concurrent delay is at different levels that often use as a tool against each other parties. In term of preventing the time-frame problems, the critical path method (CPM) is widely applied. In the delay analysis technique, the EDAM method employs CPM to identify the critical path changes and the occurred concurrent delays. Implementing a six-floor building as-planned schedule and its delays information as a case study, this research results show that the critical path of the building has changed eight times and the concurrent delay occurred on the first change with six days of delays. By identifying the critical path change, project parties are expected to be able to prevent continuously delays by escalating the work progress. Furthermore, the information about concurrent delays would be essential in avoiding disputes regarding this issue. Project parties would be aware of their contribution to critical path changes by knowing their caused delay in that time period.\",\"PeriodicalId\":426640,\"journal\":{\"name\":\"Journal of Applied Sciences, Management and Engineering Technology\",\"volume\":\"13 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2020-02-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Applied Sciences, Management and Engineering Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31284/J.JASMET.2020.V1I1.867\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Applied Sciences, Management and Engineering Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31284/J.JASMET.2020.V1I1.867","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

项目计划的主要目的之一是在日期和时间上按时完成一个项目。然而,避免延迟的问题是很难做到的。延迟本身通常分为三种类型,EN, EC和NE延迟,代表每个项目各方的贡献。此外,并发延迟处于不同的级别,通常用作对抗对方的工具。在防止时间框架问题方面,关键路径法(CPM)得到了广泛应用。在延迟分析技术中,EDAM方法采用CPM来识别关键路径的变化和发生的并发延迟。以某六层建筑的计划进度及其延误信息为例,研究结果表明,该建筑的关键路径发生了8次变化,并且在第一次变化时发生了6天的并发延误。通过识别关键路径变更,项目各方有望通过升级工作进度来防止持续的延迟。此外,关于同时延误的信息对于避免关于这个问题的争端是必不可少的。通过了解在该时间段内造成的延迟,项目各方将意识到他们对关键路径变更的贡献。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Identification of Critical Path Changes and Concurrent Delays Using EDAM Method for Building Project
Achieving a project whose punctually in completion date and duration is one of the main purposes of the project planning. However, avoiding the issue of the delay is hard to do. Delays itself commonly divided into three types, EN, EC and NE delays that represent the contribution of each project parties. Furthermore, the concurrent delay is at different levels that often use as a tool against each other parties. In term of preventing the time-frame problems, the critical path method (CPM) is widely applied. In the delay analysis technique, the EDAM method employs CPM to identify the critical path changes and the occurred concurrent delays. Implementing a six-floor building as-planned schedule and its delays information as a case study, this research results show that the critical path of the building has changed eight times and the concurrent delay occurred on the first change with six days of delays. By identifying the critical path change, project parties are expected to be able to prevent continuously delays by escalating the work progress. Furthermore, the information about concurrent delays would be essential in avoiding disputes regarding this issue. Project parties would be aware of their contribution to critical path changes by knowing their caused delay in that time period.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信