分析一下在三宝楼地下室工作的成本和时间组合方法

S. Manggolo, Antonius, Kartono Wibowo
{"title":"分析一下在三宝楼地下室工作的成本和时间组合方法","authors":"S. Manggolo, Antonius, Kartono Wibowo","doi":"10.36728/jtsa.v28i2.2512","DOIUrl":null,"url":null,"abstract":"Tentrem Semarang Building is one of the tallest buildings in Semarang with 4 basement floors and 17 top floors. The construction of basements in high-rise buildings is currently being carried out a lot, one of the factors is due to the limited land to be built, in general, the construction of basements is used for parking lots. The basement to be built has different depths and conditions, so it takes the right method according to the conditions in the field. There are 2 methods for implementing basement construction, namely bottom-up and top-down. In the basement structure work of the existing Tentrem Semarang Building construction project, the basement construction used the bottom-up construction method. In this study, the method will be modified using the top-down construction method. Information regarding work methods, worker productivity was obtained by interviewing field supervisors from the owner, interviews with supervisors from the main contractor and direct field observations. Calculation of costs and time is carried out by analyzing the capacity and productivity of labor and heavy equipment, comparing the normal time with the time after changes in construction methods. The results of the modification of the construction method using the top-down construction method for the basement structure of the Tentrem Semarang Building project took 510 days to complete and cost IDR  205,059,861,826. Whereas for the bottom-up method it takes 685 days with a total cost of IDR 253,609,405,225. The application of the Top-Down method to the implementation of the basement structure of the Tentrem Semarang building project is more effective and efficient than the implementation of the Bottom-Up method and produces a time effectiveness value of 25.55% and a cost efficiency of 19.14% compared to the Bottom-Up method \n ","PeriodicalId":120082,"journal":{"name":"Jurnal Teknik Sipil dan Arsitektur","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-07-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ANALISA PERBANDINGAN BIAYA DAN WAKTU METODE KOSTRUKSI TOP-DOWN DAN BOTTOM-UP PADA PEKERJAAN BASEMENT GEDUNG TENTREM SEMARANG\",\"authors\":\"S. Manggolo, Antonius, Kartono Wibowo\",\"doi\":\"10.36728/jtsa.v28i2.2512\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Tentrem Semarang Building is one of the tallest buildings in Semarang with 4 basement floors and 17 top floors. The construction of basements in high-rise buildings is currently being carried out a lot, one of the factors is due to the limited land to be built, in general, the construction of basements is used for parking lots. The basement to be built has different depths and conditions, so it takes the right method according to the conditions in the field. There are 2 methods for implementing basement construction, namely bottom-up and top-down. In the basement structure work of the existing Tentrem Semarang Building construction project, the basement construction used the bottom-up construction method. In this study, the method will be modified using the top-down construction method. Information regarding work methods, worker productivity was obtained by interviewing field supervisors from the owner, interviews with supervisors from the main contractor and direct field observations. Calculation of costs and time is carried out by analyzing the capacity and productivity of labor and heavy equipment, comparing the normal time with the time after changes in construction methods. The results of the modification of the construction method using the top-down construction method for the basement structure of the Tentrem Semarang Building project took 510 days to complete and cost IDR  205,059,861,826. Whereas for the bottom-up method it takes 685 days with a total cost of IDR 253,609,405,225. The application of the Top-Down method to the implementation of the basement structure of the Tentrem Semarang building project is more effective and efficient than the implementation of the Bottom-Up method and produces a time effectiveness value of 25.55% and a cost efficiency of 19.14% compared to the Bottom-Up method \\n \",\"PeriodicalId\":120082,\"journal\":{\"name\":\"Jurnal Teknik Sipil dan Arsitektur\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-07-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Teknik Sipil dan Arsitektur\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.36728/jtsa.v28i2.2512\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Teknik Sipil dan Arsitektur","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36728/jtsa.v28i2.2512","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

三宝垄大厦是三宝垄最高的建筑之一,有4层地下室和17层顶层。高层建筑中地下室的建设目前正在大量进行,其中一个因素是由于可建的土地有限,一般来说,地下室的建设多用于停车场。要建的地下室有不同的深度和条件,因此要根据现场的情况采取合适的方法。地下室施工的实施方法有自下而上和自上而下两种。在现有三宝朗腾建筑工程的地下室结构工作中,地下室施工采用了自下而上的施工方法。在本研究中,将采用自顶向下的构建方法对该方法进行修改。通过采访业主的现场主管、主要承包商的主管以及直接的现场观察,获得了有关工作方法和工人生产率的信息。成本和时间的计算是通过分析劳动力和重型设备的能力和生产率,比较正常时间和施工方法变化后的时间来进行的。temtem三宝垄大厦工程的地下室结构采用自上而下的施工方法,修改施工方法的结果耗时510天,费用为205,059,861,826印尼盾。而自下而上的方法则需要685天,总成本为253,609,405,225印尼盾。应用自顶向下方法实施temtem三宝朗建筑项目地下室结构比采用自底向上方法更有效和高效,与自底向上方法相比,时间有效性值为25.55%,成本效率为19.14%
本文章由计算机程序翻译,如有差异,请以英文原文为准。
ANALISA PERBANDINGAN BIAYA DAN WAKTU METODE KOSTRUKSI TOP-DOWN DAN BOTTOM-UP PADA PEKERJAAN BASEMENT GEDUNG TENTREM SEMARANG
Tentrem Semarang Building is one of the tallest buildings in Semarang with 4 basement floors and 17 top floors. The construction of basements in high-rise buildings is currently being carried out a lot, one of the factors is due to the limited land to be built, in general, the construction of basements is used for parking lots. The basement to be built has different depths and conditions, so it takes the right method according to the conditions in the field. There are 2 methods for implementing basement construction, namely bottom-up and top-down. In the basement structure work of the existing Tentrem Semarang Building construction project, the basement construction used the bottom-up construction method. In this study, the method will be modified using the top-down construction method. Information regarding work methods, worker productivity was obtained by interviewing field supervisors from the owner, interviews with supervisors from the main contractor and direct field observations. Calculation of costs and time is carried out by analyzing the capacity and productivity of labor and heavy equipment, comparing the normal time with the time after changes in construction methods. The results of the modification of the construction method using the top-down construction method for the basement structure of the Tentrem Semarang Building project took 510 days to complete and cost IDR  205,059,861,826. Whereas for the bottom-up method it takes 685 days with a total cost of IDR 253,609,405,225. The application of the Top-Down method to the implementation of the basement structure of the Tentrem Semarang building project is more effective and efficient than the implementation of the Bottom-Up method and produces a time effectiveness value of 25.55% and a cost efficiency of 19.14% compared to the Bottom-Up method  
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信