{"title":"案例研究:澳大利亚液化天然气设施的涡轮机负荷分担和减载系统","authors":"A. Khatib, Anshuman Mallya, Bowen Dai, Roberto Costa","doi":"10.1109/PCIC30934.2019.9074511","DOIUrl":null,"url":null,"abstract":"This paper presents a turbine load-sharing and load-shedding system for an islanded liquefied natural gas facility in Australia. The system includes three independent and redundant load-shedding schemes: process-based contingency load shedding with predefined load group and load pairs, high-speed underfrequency-based load shedding, and progressive overload shedding with system frequency supervision. In addition to the load-shedding schemes, the site includes a generation control system with frequency control, voltage control, automatic synchronization, and turbine load-sharing schemes. A breaker-and-a-half configuration complicates the fast load-shedding scheme. Results from hardware-in-the-loop testing are shared.","PeriodicalId":276673,"journal":{"name":"2019 IEEE Petroleum and Chemical Industry Committee Conference (PCIC)","volume":"3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Case Study: Turbine Load-Sharing and Load-Shedding System Foran Australian LNG Facility\",\"authors\":\"A. Khatib, Anshuman Mallya, Bowen Dai, Roberto Costa\",\"doi\":\"10.1109/PCIC30934.2019.9074511\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper presents a turbine load-sharing and load-shedding system for an islanded liquefied natural gas facility in Australia. The system includes three independent and redundant load-shedding schemes: process-based contingency load shedding with predefined load group and load pairs, high-speed underfrequency-based load shedding, and progressive overload shedding with system frequency supervision. In addition to the load-shedding schemes, the site includes a generation control system with frequency control, voltage control, automatic synchronization, and turbine load-sharing schemes. A breaker-and-a-half configuration complicates the fast load-shedding scheme. Results from hardware-in-the-loop testing are shared.\",\"PeriodicalId\":276673,\"journal\":{\"name\":\"2019 IEEE Petroleum and Chemical Industry Committee Conference (PCIC)\",\"volume\":\"3 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-09-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2019 IEEE Petroleum and Chemical Industry Committee Conference (PCIC)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/PCIC30934.2019.9074511\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2019 IEEE Petroleum and Chemical Industry Committee Conference (PCIC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PCIC30934.2019.9074511","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

本文介绍了一种用于澳大利亚孤岛液化天然气设施的汽轮机负荷分担和减载系统。该系统包括三种独立且冗余的减载方案:基于过程的偶然性减载方案、基于预定义负载组和负载对的高速低频减载方案和基于系统频率监督的渐进式过载减载方案。除了减载方案外,该站点还包括一个具有频率控制、电压控制、自动同步和涡轮负荷共享方案的发电控制系统。断路器半配置使快速减载方案复杂化。硬件在环测试的结果是共享的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Case Study: Turbine Load-Sharing and Load-Shedding System Foran Australian LNG Facility
This paper presents a turbine load-sharing and load-shedding system for an islanded liquefied natural gas facility in Australia. The system includes three independent and redundant load-shedding schemes: process-based contingency load shedding with predefined load group and load pairs, high-speed underfrequency-based load shedding, and progressive overload shedding with system frequency supervision. In addition to the load-shedding schemes, the site includes a generation control system with frequency control, voltage control, automatic synchronization, and turbine load-sharing schemes. A breaker-and-a-half configuration complicates the fast load-shedding scheme. Results from hardware-in-the-loop testing are shared.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信