建筑总平面图设计的特点

Y. Novak, Y. Sobko, O. Sumariuk
{"title":"建筑总平面图设计的特点","authors":"Y. Novak, Y. Sobko, O. Sumariuk","doi":"10.32347/2077-3455.2023.66.300-309","DOIUrl":null,"url":null,"abstract":"The construction master plan (contgenplan) is the general plan of the construction site, which shows all existing and planned permanent buildings and structures, as well as temporary buildings necessary for construction and assembly works. The purpose of the budget plan is to organize the construction industry on the site, which would ensure the creation of the necessary production and living conditions for workers, the reception and delivery of materials, semi-finished products and structures to the workplace, the normal operation of construction machines and mechanized installations, uninterrupted supply of water and energy resources. There are two types of construction master plan: general site and object. \nThe general site budget plan is drawn up during the development of the construction organization project and covers the entire territory of the urban residential massif (microdistrict, block) or cultural and household complex. The facility budget plan is part of the construction project and covers the territory related to one facility or, in some cases, to several. At the stage of the construction project, an object budget plan is developed, which specifies and details the decisions of the site-wide budget plan. The budgenplan should show: entrances and exits, unloading points, entry into dangerous areas, the construction of roads and sidewalks, their width and connection to the designed buildings. \nThe budget plan should show storage facilities, temporary buildings, the organization of communication lighting and dispatching of the construction site, the organization of providing the facility with electricity, water, steam, compressed air, and oxygen. Before placing mechanized equipment on the construction site, it is necessary to determine the types and number of cranes, stationary lifts, as well as their installation locations. After that, it is necessary to calculate the operating zones of the cranes, taking into account the specifics of architectural and structural solutions and the construction conditions of the facility.","PeriodicalId":319540,"journal":{"name":"Current problems of architecture and urban planning","volume":"32 3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-04-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Features of designing building general plans\",\"authors\":\"Y. Novak, Y. Sobko, O. Sumariuk\",\"doi\":\"10.32347/2077-3455.2023.66.300-309\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The construction master plan (contgenplan) is the general plan of the construction site, which shows all existing and planned permanent buildings and structures, as well as temporary buildings necessary for construction and assembly works. The purpose of the budget plan is to organize the construction industry on the site, which would ensure the creation of the necessary production and living conditions for workers, the reception and delivery of materials, semi-finished products and structures to the workplace, the normal operation of construction machines and mechanized installations, uninterrupted supply of water and energy resources. There are two types of construction master plan: general site and object. \\nThe general site budget plan is drawn up during the development of the construction organization project and covers the entire territory of the urban residential massif (microdistrict, block) or cultural and household complex. The facility budget plan is part of the construction project and covers the territory related to one facility or, in some cases, to several. At the stage of the construction project, an object budget plan is developed, which specifies and details the decisions of the site-wide budget plan. The budgenplan should show: entrances and exits, unloading points, entry into dangerous areas, the construction of roads and sidewalks, their width and connection to the designed buildings. \\nThe budget plan should show storage facilities, temporary buildings, the organization of communication lighting and dispatching of the construction site, the organization of providing the facility with electricity, water, steam, compressed air, and oxygen. Before placing mechanized equipment on the construction site, it is necessary to determine the types and number of cranes, stationary lifts, as well as their installation locations. After that, it is necessary to calculate the operating zones of the cranes, taking into account the specifics of architectural and structural solutions and the construction conditions of the facility.\",\"PeriodicalId\":319540,\"journal\":{\"name\":\"Current problems of architecture and urban planning\",\"volume\":\"32 3 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-04-14\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Current problems of architecture and urban planning\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.32347/2077-3455.2023.66.300-309\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Current problems of architecture and urban planning","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.32347/2077-3455.2023.66.300-309","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

施工总体规划(contgenplan)是施工现场的总体规划,其中显示了所有现有和规划的永久性建筑物和构筑物,以及施工和装配工程所需的临时建筑物。预算计划的目的是在现场组织建筑行业,这将确保为工人创造必要的生产和生活条件,材料,半成品和结构的接收和交付到工作场所,施工机械和机械化装置的正常运行,水和能源的不间断供应。施工总体规划有两种类型:总场地和对象。总场地预算计划在施工组织项目的开发过程中制定,涵盖城市居住地块(微区、街区)或文化、家庭综合体的整个区域。设施预算计划是建设项目的一部分,包括与一个设施或在某些情况下与几个设施有关的领土。在建设项目阶段,制定目标预算计划,该计划规定并详细说明了整个现场预算计划的决策。预算方案应显示:出入口、卸货点、进入危险区域、道路和人行道的建设、其宽度和与设计建筑物的连接。预算计划应显示存储设施、临时建筑、施工现场的通信、照明和调度组织、为设施提供电、水、蒸汽、压缩空气和氧气的组织。在施工现场放置机械化设备前,必须确定起重机、固定升降机的种类和数量,以及安装位置。在此之后,需要计算起重机的操作区域,考虑到建筑和结构解决方案的具体情况以及设施的施工条件。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Features of designing building general plans
The construction master plan (contgenplan) is the general plan of the construction site, which shows all existing and planned permanent buildings and structures, as well as temporary buildings necessary for construction and assembly works. The purpose of the budget plan is to organize the construction industry on the site, which would ensure the creation of the necessary production and living conditions for workers, the reception and delivery of materials, semi-finished products and structures to the workplace, the normal operation of construction machines and mechanized installations, uninterrupted supply of water and energy resources. There are two types of construction master plan: general site and object. The general site budget plan is drawn up during the development of the construction organization project and covers the entire territory of the urban residential massif (microdistrict, block) or cultural and household complex. The facility budget plan is part of the construction project and covers the territory related to one facility or, in some cases, to several. At the stage of the construction project, an object budget plan is developed, which specifies and details the decisions of the site-wide budget plan. The budgenplan should show: entrances and exits, unloading points, entry into dangerous areas, the construction of roads and sidewalks, their width and connection to the designed buildings. The budget plan should show storage facilities, temporary buildings, the organization of communication lighting and dispatching of the construction site, the organization of providing the facility with electricity, water, steam, compressed air, and oxygen. Before placing mechanized equipment on the construction site, it is necessary to determine the types and number of cranes, stationary lifts, as well as their installation locations. After that, it is necessary to calculate the operating zones of the cranes, taking into account the specifics of architectural and structural solutions and the construction conditions of the facility.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信