印第安角3号机组注硼罐维修

D. Crane
{"title":"印第安角3号机组注硼罐维修","authors":"D. Crane","doi":"10.1115/pvp2019-93449","DOIUrl":null,"url":null,"abstract":"\n In the Fall of 2018 Westinghouse designed a welded plug to repair a leak around a previously capped nozzle in the Boron Injection Tank at Indian Point Unit 3. The leak was caused by weld cracking around the nozzle. In order to complete the repair, the existing nozzle and weld needed to be removed by boring into the tank so that a custom plug could be installed. Due to site procedures, welding could not be performed inside the tank, so a single weld on the outside of the tank needed to be designed to meet ASME B&PV Code, Section III requirements. In addition, the tank was manufactured from carbon steel with a stainless steel cladding, so future corrosion of the carbon steel needed to be assessed. The leak was an outage related incident, which required the design to be expedited. This paper will discuss the technical challenges in designing the welded plug to meet the site and code requirements.","PeriodicalId":339189,"journal":{"name":"Volume 7: Operations, Applications, and Components","volume":"118 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-11-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Boron Injection Tank Repair at Indian Point Unit 3\",\"authors\":\"D. Crane\",\"doi\":\"10.1115/pvp2019-93449\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n In the Fall of 2018 Westinghouse designed a welded plug to repair a leak around a previously capped nozzle in the Boron Injection Tank at Indian Point Unit 3. The leak was caused by weld cracking around the nozzle. In order to complete the repair, the existing nozzle and weld needed to be removed by boring into the tank so that a custom plug could be installed. Due to site procedures, welding could not be performed inside the tank, so a single weld on the outside of the tank needed to be designed to meet ASME B&PV Code, Section III requirements. In addition, the tank was manufactured from carbon steel with a stainless steel cladding, so future corrosion of the carbon steel needed to be assessed. The leak was an outage related incident, which required the design to be expedited. This paper will discuss the technical challenges in designing the welded plug to meet the site and code requirements.\",\"PeriodicalId\":339189,\"journal\":{\"name\":\"Volume 7: Operations, Applications, and Components\",\"volume\":\"118 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-11-15\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Volume 7: Operations, Applications, and Components\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1115/pvp2019-93449\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Volume 7: Operations, Applications, and Components","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1115/pvp2019-93449","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

2018年秋,西屋电气设计了一种焊接塞,用于修复印第安角3号机组硼注入罐先前密封喷嘴周围的泄漏。泄漏是由喷嘴周围的焊缝开裂引起的。为了完成修复工作,需要将现有的喷嘴和焊缝钻孔到储罐中,以便安装定制的堵头。由于现场程序的原因,不能在罐内进行焊接,因此需要在罐外进行单焊缝设计,以满足ASME & pv规范第三节的要求。此外,储罐由碳钢和不锈钢包层制成,因此需要评估碳钢的未来腐蚀情况。泄漏是一个与停电有关的事件,这需要加快设计。本文将讨论在设计焊接塞以满足现场和规范要求时所面临的技术挑战。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Boron Injection Tank Repair at Indian Point Unit 3
In the Fall of 2018 Westinghouse designed a welded plug to repair a leak around a previously capped nozzle in the Boron Injection Tank at Indian Point Unit 3. The leak was caused by weld cracking around the nozzle. In order to complete the repair, the existing nozzle and weld needed to be removed by boring into the tank so that a custom plug could be installed. Due to site procedures, welding could not be performed inside the tank, so a single weld on the outside of the tank needed to be designed to meet ASME B&PV Code, Section III requirements. In addition, the tank was manufactured from carbon steel with a stainless steel cladding, so future corrosion of the carbon steel needed to be assessed. The leak was an outage related incident, which required the design to be expedited. This paper will discuss the technical challenges in designing the welded plug to meet the site and code requirements.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信