{"title":"热带地区大型并网光伏电站性能分析。","authors":"","doi":"10.29121/ijesrt.v10.i1.2021.5","DOIUrl":null,"url":null,"abstract":"The main objective of this research is analysed and compared the performance of two solar power plants to identify the possible operational problems in the tropical region. The grid connected PV power plants considered in the present study, Ten Merina and Senergy, were installed in the region of Thies (Senegal). Solar power plants have the same installed capacity 29.491 MWp. A period of one operation year of the solar power plants is considered, starting from January 2018 to December 2018. The performance parameters developed by the International Energy Agency (IEA) are used to analyse the performances of solar power plants. The results show that the plane of array irradiance at the sites is identical with an annual average of 6.2 kWh/m2/d. The annual average performance ratio and final yield of solar power plants are respectively 74.3 %; 4.61 kWh/kWp to Ten Merina and 75.9 %; 4.66 kWh/kWp to Senergy. These results are compared to other solar power plants installed in different locations around the world.","PeriodicalId":320722,"journal":{"name":"January-2021","volume":"73 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ANALYSIS PERFORMANCE OF LARGE SCALE GRID CONNECTED PV POWER PLANTS IN THE TROPICAL REGION.\",\"authors\":\"\",\"doi\":\"10.29121/ijesrt.v10.i1.2021.5\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The main objective of this research is analysed and compared the performance of two solar power plants to identify the possible operational problems in the tropical region. The grid connected PV power plants considered in the present study, Ten Merina and Senergy, were installed in the region of Thies (Senegal). Solar power plants have the same installed capacity 29.491 MWp. A period of one operation year of the solar power plants is considered, starting from January 2018 to December 2018. The performance parameters developed by the International Energy Agency (IEA) are used to analyse the performances of solar power plants. The results show that the plane of array irradiance at the sites is identical with an annual average of 6.2 kWh/m2/d. The annual average performance ratio and final yield of solar power plants are respectively 74.3 %; 4.61 kWh/kWp to Ten Merina and 75.9 %; 4.66 kWh/kWp to Senergy. These results are compared to other solar power plants installed in different locations around the world.\",\"PeriodicalId\":320722,\"journal\":{\"name\":\"January-2021\",\"volume\":\"73 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"January-2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.29121/ijesrt.v10.i1.2021.5\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"January-2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29121/ijesrt.v10.i1.2021.5","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
本研究的主要目的是分析和比较两个太阳能发电厂的性能,以确定热带地区可能出现的运行问题。本研究所考虑的并网光伏发电厂Ten Merina和Senergy安装在Thies(塞内加尔)地区。太阳能发电厂的装机容量相同,为29.491兆瓦。从2018年1月到2018年12月,太阳能发电厂的运营期为一年。采用国际能源署(IEA)制定的性能参数来分析太阳能电站的性能。结果表明:各站点阵列辐照度平面与年平均值一致,为6.2 kWh/m2/d;太阳能电站年平均性能比和最终发电量分别为74.3%;4.61 kWh/kWp: Ten Merina和75.9%;4.66 kWh/kWp到能源。这些结果与安装在世界各地不同地点的其他太阳能发电厂进行了比较。
ANALYSIS PERFORMANCE OF LARGE SCALE GRID CONNECTED PV POWER PLANTS IN THE TROPICAL REGION.
The main objective of this research is analysed and compared the performance of two solar power plants to identify the possible operational problems in the tropical region. The grid connected PV power plants considered in the present study, Ten Merina and Senergy, were installed in the region of Thies (Senegal). Solar power plants have the same installed capacity 29.491 MWp. A period of one operation year of the solar power plants is considered, starting from January 2018 to December 2018. The performance parameters developed by the International Energy Agency (IEA) are used to analyse the performances of solar power plants. The results show that the plane of array irradiance at the sites is identical with an annual average of 6.2 kWh/m2/d. The annual average performance ratio and final yield of solar power plants are respectively 74.3 %; 4.61 kWh/kWp to Ten Merina and 75.9 %; 4.66 kWh/kWp to Senergy. These results are compared to other solar power plants installed in different locations around the world.