安装深海海水养殖供水系统

T. Toyota, T. Nakashima, T. Fujita, S. Ishii, K. Hagiwara, K. Merino, K. Shimizu
{"title":"安装深海海水养殖供水系统","authors":"T. Toyota, T. Nakashima, T. Fujita, S. Ishii, K. Hagiwara, K. Merino, K. Shimizu","doi":"10.1109/OCEANS.1989.592890","DOIUrl":null,"url":null,"abstract":"A system was installed of pumping 460 m3 per day of deep-sea water from a depth of 320 m to shore for cultivating fish, shellfish, and algae. The material and the installation method were tested of a deep-sea water pipe. The particularly severe wave conditions that exist during a typhoon at the system site pose unique problems. It was determined that the most suitable material for a deep-sea water pipe was high-density polyethylene with steel wire armor, and that the reel-barge method was optimal for laying this pipe. Laying work was done accurately in a short period (two days). It was found that laying high-density polyethylene pipe with a steel wire armor by the reel-barge method was the best combination for construction of a deep-sea water supply pipeline. Before laying work, it was predicted that approximately 5 % of the total pipe was necessary for extra pipe because of possible errors during laying. During actual laying work, the pipe length was found to be practically equal to a designed pipeline length.","PeriodicalId":331017,"journal":{"name":"Proceedings OCEANS","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"1989-09-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Installation Of A Deep-sea Water Supply System For Mariculture\",\"authors\":\"T. Toyota, T. Nakashima, T. Fujita, S. Ishii, K. Hagiwara, K. Merino, K. Shimizu\",\"doi\":\"10.1109/OCEANS.1989.592890\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A system was installed of pumping 460 m3 per day of deep-sea water from a depth of 320 m to shore for cultivating fish, shellfish, and algae. The material and the installation method were tested of a deep-sea water pipe. The particularly severe wave conditions that exist during a typhoon at the system site pose unique problems. It was determined that the most suitable material for a deep-sea water pipe was high-density polyethylene with steel wire armor, and that the reel-barge method was optimal for laying this pipe. Laying work was done accurately in a short period (two days). It was found that laying high-density polyethylene pipe with a steel wire armor by the reel-barge method was the best combination for construction of a deep-sea water supply pipeline. Before laying work, it was predicted that approximately 5 % of the total pipe was necessary for extra pipe because of possible errors during laying. During actual laying work, the pipe length was found to be practically equal to a designed pipeline length.\",\"PeriodicalId\":331017,\"journal\":{\"name\":\"Proceedings OCEANS\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1989-09-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings OCEANS\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/OCEANS.1989.592890\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings OCEANS","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/OCEANS.1989.592890","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

安装了一个系统,每天从320米深处抽取460立方米的深海水到岸上,用于养殖鱼类、贝类和藻类。对深海输水管道的材料和安装方法进行了试验。台风期间在系统所在地存在的特别严重的波浪条件造成了独特的问题。确定了最适合用于深海水管道的材料是带钢丝铠装的高密度聚乙烯,而卷筒-驳船法是铺设该管道的最佳方法。铺设工作在短时间内(两天)准确完成。研究发现,采用卷筒-驳船法敷设高密度聚乙烯管加钢丝铠装是深海给水管道施工的最佳组合。在铺设工作之前,预计由于铺设过程中可能出现的错误,需要额外铺设约5%的管道。在实际铺设工作中,发现管道长度几乎等于设计管道长度。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Installation Of A Deep-sea Water Supply System For Mariculture
A system was installed of pumping 460 m3 per day of deep-sea water from a depth of 320 m to shore for cultivating fish, shellfish, and algae. The material and the installation method were tested of a deep-sea water pipe. The particularly severe wave conditions that exist during a typhoon at the system site pose unique problems. It was determined that the most suitable material for a deep-sea water pipe was high-density polyethylene with steel wire armor, and that the reel-barge method was optimal for laying this pipe. Laying work was done accurately in a short period (two days). It was found that laying high-density polyethylene pipe with a steel wire armor by the reel-barge method was the best combination for construction of a deep-sea water supply pipeline. Before laying work, it was predicted that approximately 5 % of the total pipe was necessary for extra pipe because of possible errors during laying. During actual laying work, the pipe length was found to be practically equal to a designed pipeline length.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信