库邦液化石油气储罐EPC项目的延迟因素分析及动态系统建模

Agung Fachrully Ade, S. Santoso
{"title":"库邦液化石油气储罐EPC项目的延迟因素分析及动态系统建模","authors":"Agung Fachrully Ade, S. Santoso","doi":"10.36418/jrssem.v2i06.381","DOIUrl":null,"url":null,"abstract":"Project delays are an event that often occurs in every project, especially projects with the scope of Engineering Procurement & Construction (EPC) in Indonesia. Many factors affect the slowness of the project so that the performance of a project will not run well if supervision and control are not carried out. The purpose of this study is to find out what are the factors that cause delays, make modeling using dynamic systems and how to make effective managerial suggestions to accelerate project performance. This research method uses mixed methods. The results of this study there are 3 factors that cause delays in the project, starting from the largest factor based on the results of the mean rank analysis is the Construction factor, followed by Procurement, and finally Engineering. In the Construction Factor, five main indicators were taken to cause the delay in the Petreleum Gas Liquid Tank EPC project in Kupang which occurred because the material did not meet specifications, work was stopped due to design changes, delays in project manager decision making, differences of opinion between contractors and consultants, and poor construction quality. Managerial advice in this study is to improve the quality of Human Resources and improve communication networks, tighten the control function and evaluate periodically.","PeriodicalId":277211,"journal":{"name":"Journal Research of Social, Science, Economics, and Management","volume":"25 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-01-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Delay Factor Analysis and Dynamic System Modeling on the EPC Project of Liquid Petreleum Gas Tank in Kupang\",\"authors\":\"Agung Fachrully Ade, S. Santoso\",\"doi\":\"10.36418/jrssem.v2i06.381\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Project delays are an event that often occurs in every project, especially projects with the scope of Engineering Procurement & Construction (EPC) in Indonesia. Many factors affect the slowness of the project so that the performance of a project will not run well if supervision and control are not carried out. The purpose of this study is to find out what are the factors that cause delays, make modeling using dynamic systems and how to make effective managerial suggestions to accelerate project performance. This research method uses mixed methods. The results of this study there are 3 factors that cause delays in the project, starting from the largest factor based on the results of the mean rank analysis is the Construction factor, followed by Procurement, and finally Engineering. In the Construction Factor, five main indicators were taken to cause the delay in the Petreleum Gas Liquid Tank EPC project in Kupang which occurred because the material did not meet specifications, work was stopped due to design changes, delays in project manager decision making, differences of opinion between contractors and consultants, and poor construction quality. Managerial advice in this study is to improve the quality of Human Resources and improve communication networks, tighten the control function and evaluate periodically.\",\"PeriodicalId\":277211,\"journal\":{\"name\":\"Journal Research of Social, Science, Economics, and Management\",\"volume\":\"25 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-01-29\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal Research of Social, Science, Economics, and Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.36418/jrssem.v2i06.381\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal Research of Social, Science, Economics, and Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36418/jrssem.v2i06.381","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

项目延迟是每个项目中经常发生的事件,特别是在印度尼西亚,工程采购与施工(EPC)范围的项目。许多因素影响着项目的缓慢,如果不进行监督和控制,项目的绩效就不会很好地运行。本研究的目的是找出造成延迟的因素,利用动态系统进行建模,以及如何提出有效的管理建议来加速项目绩效。本研究方法采用混合方法。本研究的结果有3个因素导致项目延误,根据平均秩分析的结果,从最大的因素开始是建设因素,其次是采购,最后是工程。在施工因素中,采取了五个主要指标来导致Kupang油气液罐EPC项目的延误,原因是材料不符合规格,设计变更导致工作停止,项目经理决策延迟,承包商和顾问之间的意见分歧以及施工质量差。本研究的管理建议是提高人力资源的质量,改善沟通网络,加强控制功能,定期评估。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Delay Factor Analysis and Dynamic System Modeling on the EPC Project of Liquid Petreleum Gas Tank in Kupang
Project delays are an event that often occurs in every project, especially projects with the scope of Engineering Procurement & Construction (EPC) in Indonesia. Many factors affect the slowness of the project so that the performance of a project will not run well if supervision and control are not carried out. The purpose of this study is to find out what are the factors that cause delays, make modeling using dynamic systems and how to make effective managerial suggestions to accelerate project performance. This research method uses mixed methods. The results of this study there are 3 factors that cause delays in the project, starting from the largest factor based on the results of the mean rank analysis is the Construction factor, followed by Procurement, and finally Engineering. In the Construction Factor, five main indicators were taken to cause the delay in the Petreleum Gas Liquid Tank EPC project in Kupang which occurred because the material did not meet specifications, work was stopped due to design changes, delays in project manager decision making, differences of opinion between contractors and consultants, and poor construction quality. Managerial advice in this study is to improve the quality of Human Resources and improve communication networks, tighten the control function and evaluate periodically.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信