{"title":"通过概率理论对网络规划的持续工作进行评估","authors":"F. R. Gusmanova","doi":"10.51889/2022-1.1728-7901.02","DOIUrl":null,"url":null,"abstract":"The article deals with the organization and control of a complex of calculation methods, integrated work planning and management, based on process modeling using network graphics in network planning and management. The main parameters of network graphics are given and a brief description is given. The types of stocks of working time are described. Particular attention was paid to the features of determining the duration and topology of the critical path. Algorithms for planning, creating and configuring network graphics are considered. Finally, the network graphics are analyzed and optimized. It is based on the fact that the level of difficulty in the timely execution of each group of non-critical paths can be determined using the intensity factor of work.Improving the organization of work with deadlines means optimizing network graphics. It is indicated that optimization is carried out in order to reduce the duration of the critical path, equalize the intensity factors, rational use of resources.\n Мақалада желілік жоспарлау мен басқаруда желілік графиканың көмегімен үрдісті модельдеуге негізделген және есептеу әдістерінің жиынтығын, кешенді жұмыстарды жоспарлау және басқару бойынша ұйымдастыру мен бақылау мәселелеріқарастырылады. Желілік графикалардың негізгі параметрлері келтіріліп, оларға қысқаша сипаттамалары берілді. Жұмыстың уақыт қорының түрлері сипатталған. Сыншыл жолдың ұзындығы мен топологиясын анықтаудағы ерекшеліктерге көңіл бөлінді. Желілік графикаларды жоспарлаудың, оларды құру, реттеу алгоритмдері қарастырылады. Соңында желілік графикаға талдау жүргізіледі және оңтайландырылады. Сыншыл емес жолдағы жұмыстың әрбір тобының мерзімінде орындалу қиындығының деңгейін жұмыс қарбаластығының коэффициентінің көмегімен анықтауға болатыны негізделген. Жұмыс жинақтығының орындалу мерзімін ескеріп, оны ұйымдастыруды жетілдіру желілік графикада оңтайландыруды білдіреді. Оңтайландыру сыншыл жолдың ұзындығын қысқарту, жұмыстардың қарбаластығының коэффициенттерін теңестіру, қорларды ұтымды пайдалану мақсатында жүргізілетіндігі көрсетілген\n статье рассматриваются вопросы организации и управления комплексом вычислительных методов, интегрированного планирования работ, основанных на моделировании процессов с использованием сетевого графика при сетевом планировании и управлении сложными работами. Приведены основные параметры сетевого графика и дана их краткая характеристика.Особое внимание уделено особенностям определения длительности и топологии критического пути. Рассмотрены алгоритмы планирования, создания и настройки сетевого графика. Сетевой график анализируется и в дальнейшем оптимизируется. Он основан на том, что уровень трудности своевременного выполнения каждой группой некритического пути можно определить с помощью коэффициента интенсивности работ.Улучшение организации работы с учетом сроков означает оптимизацию сетевого графика. Показано, что оптимизация проводится с целью сокращения длительности критического пути, выравнивания коэффициентов интенсивности, рационального использования ресурсов.","PeriodicalId":215363,"journal":{"name":"BULLETIN Series Physical and Mathematical Sciences","volume":"167 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-03-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ОЦЕНКА ПРОДОЛЖИТЕЛЬНОСТИРАБОТ ПРИ СЕТЕВОМ ПЛАНИРОВАНИИС ПОМОЩЬЮ ТЕОРИИ ВЕРОЯТНОСТЕЙВ\",\"authors\":\"F. R. Gusmanova\",\"doi\":\"10.51889/2022-1.1728-7901.02\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The article deals with the organization and control of a complex of calculation methods, integrated work planning and management, based on process modeling using network graphics in network planning and management. The main parameters of network graphics are given and a brief description is given. The types of stocks of working time are described. Particular attention was paid to the features of determining the duration and topology of the critical path. Algorithms for planning, creating and configuring network graphics are considered. Finally, the network graphics are analyzed and optimized. It is based on the fact that the level of difficulty in the timely execution of each group of non-critical paths can be determined using the intensity factor of work.Improving the organization of work with deadlines means optimizing network graphics. It is indicated that optimization is carried out in order to reduce the duration of the critical path, equalize the intensity factors, rational use of resources.\\n Мақалада желілік жоспарлау мен басқаруда желілік графиканың көмегімен үрдісті модельдеуге негізделген және есептеу әдістерінің жиынтығын, кешенді жұмыстарды жоспарлау және басқару бойынша ұйымдастыру мен бақылау мәселелеріқарастырылады. Желілік графикалардың негізгі параметрлері келтіріліп, оларға қысқаша сипаттамалары берілді. Жұмыстың уақыт қорының түрлері сипатталған. Сыншыл жолдың ұзындығы мен топологиясын анықтаудағы ерекшеліктерге көңіл бөлінді. Желілік графикаларды жоспарлаудың, оларды құру, реттеу алгоритмдері қарастырылады. Соңында желілік графикаға талдау жүргізіледі және оңтайландырылады. Сыншыл емес жолдағы жұмыстың әрбір тобының мерзімінде орындалу қиындығының деңгейін жұмыс қарбаластығының коэффициентінің көмегімен анықтауға болатыны негізделген. Жұмыс жинақтығының орындалу мерзімін ескеріп, оны ұйымдастыруды жетілдіру желілік графикада оңтайландыруды білдіреді. Оңтайландыру сыншыл жолдың ұзындығын қысқарту, жұмыстардың қарбаластығының коэффициенттерін теңестіру, қорларды ұтымды пайдалану мақсатында жүргізілетіндігі көрсетілген\\n статье рассматриваются вопросы организации и управления комплексом вычислительных методов, интегрированного планирования работ, основанных на моделировании процессов с использованием сетевого графика при сетевом планировании и управлении сложными работами. Приведены основные параметры сетевого графика и дана их краткая характеристика.Особое внимание уделено особенностям определения длительности и топологии критического пути. Рассмотрены алгоритмы планирования, создания и настройки сетевого графика. Сетевой график анализируется и в дальнейшем оптимизируется. Он основан на том, что уровень трудности своевременного выполнения каждой группой некритического пути можно определить с помощью коэффициента интенсивности работ.Улучшение организации работы с учетом сроков означает оптимизацию сетевого графика. Показано, что оптимизация проводится с целью сокращения длительности критического пути, выравнивания коэффициентов интенсивности, рационального использования ресурсов.\",\"PeriodicalId\":215363,\"journal\":{\"name\":\"BULLETIN Series Physical and Mathematical Sciences\",\"volume\":\"167 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-03-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"BULLETIN Series Physical and Mathematical Sciences\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.51889/2022-1.1728-7901.02\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"BULLETIN Series Physical and Mathematical Sciences","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.51889/2022-1.1728-7901.02","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
本文论述了在网络规划与管理中,基于过程建模的网络图形的综合计算方法的组织与控制,综合工作计划与管理。给出了网络图形的主要参数,并作了简要说明。描述了工作时间存量的类型。重点研究了关键路径持续时间和拓扑结构的确定问题。考虑了规划、创建和配置网络图形的算法。最后,对网络图形进行了分析和优化。它基于这样一个事实,即每组非关键路径的及时执行的困难程度可以使用工作强度因子来确定。改进有最后期限的工作组织意味着优化网络图形。指出优化是为了缩短关键路径的持续时间,均衡强度因子,合理利用资源。Мақаладажелілікжоспарлауменбасқарудажелілікграфиканыңкөмегіменүрдістімодельдеугенегізделгенжәнеесептеуәдістерініңжиынтығын,кешендіжұмыстардыжоспарлаужәнебасқарубойыншаұйымдастыруменбақылаумәселелеріқарастырылады。Желілікграфикалардыңнегізгіпараметрлерікелтірілі,поларғақысқашасипаттамаларыберілді。Жұмыстың уақыт қорының түрлері сипатталған。Сыншылжолдыңұзындығыментопологиясынанықтаудағыерекшеліктергекөңілбөлінді。Желілікграфикалардыжоспарлаудың,олардықұр,уреттеуалгоритмдеріқарастырылады。Соңындажелілікграфикағаталдаужүргізіледіжәнеоңтайландырылады。Сыншылемесжолдағыжұмыстыңәрбіртобыныңмерзіміндеорындалуқиындығыныңдеңгейінжұмысқарбаластығыныңкоэффициентініңкөмегіменанықтауғаболатынынегізделген。Жұмысжинақтығыныңорындалумерзімінескері,поныұйымдастырудыжетілдіружелілікграфикадаоңтайландырудыбілдіреді。Оңтайландырусыншылжолдыңұзындығынқысқарту、жұмыстардыңқарбаластығыныңкоэффициенттерінтеңестіру、қорлардыұтымдыпайдаланумақсатындажүргізілетіндігікөрсетілгенстатьерассматриваютсявопросыорганизациииуправлениякомплексомвычислительныхметодов。интегрированногопланированияработ,основанныхнамоделированиипроцессовсиспользованиемсетевогографикаприсетевомпланированиииуправлениисложнымиработами。Приведеныосновныепараметрысетевогографикаиданаихкраткаяхарактеристика。Особоевниманиеуделеноособенностямопределениядлительностиитопологиикритическогопути。Рассмотреныалгоритмыпланирования,созданияинастройкисетевогографика。Сетевойграфиканализируетсяивдальнейшемоптимизируется。Оноснованнатом,чтоуровеньтрудностисвоевременноговыполнениякаждойгруппойнекритическогопутиможноопределитьспомощьюкоэффициентаинтенсивностиработ。Улучшениеорганизацииработысучетомсроковозначаетоптимизациюсетевогографика。,чПоказанотооптимизацияпроводитсясцельюсокращениядлительностикритическогопути,выравниваниякоэффициентовинтенсивности,рациональногоиспользованияресурсов。
ОЦЕНКА ПРОДОЛЖИТЕЛЬНОСТИРАБОТ ПРИ СЕТЕВОМ ПЛАНИРОВАНИИС ПОМОЩЬЮ ТЕОРИИ ВЕРОЯТНОСТЕЙВ
The article deals with the organization and control of a complex of calculation methods, integrated work planning and management, based on process modeling using network graphics in network planning and management. The main parameters of network graphics are given and a brief description is given. The types of stocks of working time are described. Particular attention was paid to the features of determining the duration and topology of the critical path. Algorithms for planning, creating and configuring network graphics are considered. Finally, the network graphics are analyzed and optimized. It is based on the fact that the level of difficulty in the timely execution of each group of non-critical paths can be determined using the intensity factor of work.Improving the organization of work with deadlines means optimizing network graphics. It is indicated that optimization is carried out in order to reduce the duration of the critical path, equalize the intensity factors, rational use of resources.
Мақалада желілік жоспарлау мен басқаруда желілік графиканың көмегімен үрдісті модельдеуге негізделген және есептеу әдістерінің жиынтығын, кешенді жұмыстарды жоспарлау және басқару бойынша ұйымдастыру мен бақылау мәселелеріқарастырылады. Желілік графикалардың негізгі параметрлері келтіріліп, оларға қысқаша сипаттамалары берілді. Жұмыстың уақыт қорының түрлері сипатталған. Сыншыл жолдың ұзындығы мен топологиясын анықтаудағы ерекшеліктерге көңіл бөлінді. Желілік графикаларды жоспарлаудың, оларды құру, реттеу алгоритмдері қарастырылады. Соңында желілік графикаға талдау жүргізіледі және оңтайландырылады. Сыншыл емес жолдағы жұмыстың әрбір тобының мерзімінде орындалу қиындығының деңгейін жұмыс қарбаластығының коэффициентінің көмегімен анықтауға болатыны негізделген. Жұмыс жинақтығының орындалу мерзімін ескеріп, оны ұйымдастыруды жетілдіру желілік графикада оңтайландыруды білдіреді. Оңтайландыру сыншыл жолдың ұзындығын қысқарту, жұмыстардың қарбаластығының коэффициенттерін теңестіру, қорларды ұтымды пайдалану мақсатында жүргізілетіндігі көрсетілген
статье рассматриваются вопросы организации и управления комплексом вычислительных методов, интегрированного планирования работ, основанных на моделировании процессов с использованием сетевого графика при сетевом планировании и управлении сложными работами. Приведены основные параметры сетевого графика и дана их краткая характеристика.Особое внимание уделено особенностям определения длительности и топологии критического пути. Рассмотрены алгоритмы планирования, создания и настройки сетевого графика. Сетевой график анализируется и в дальнейшем оптимизируется. Он основан на том, что уровень трудности своевременного выполнения каждой группой некритического пути можно определить с помощью коэффициента интенсивности работ.Улучшение организации работы с учетом сроков означает оптимизацию сетевого графика. Показано, что оптимизация проводится с целью сокращения длительности критического пути, выравнивания коэффициентов интенсивности, рационального использования ресурсов.