D. Vozikis, A. Emhemed, S. Hynds, M. Filla, S. Rigby
{"title":"利用Bess方案对11kv孤岛型配电网在干扰下供电的柔性方案进行了评价","authors":"D. Vozikis, A. Emhemed, S. Hynds, M. Filla, S. Rigby","doi":"10.1049/icp.2021.2457","DOIUrl":null,"url":null,"abstract":"This paper presents an overview of the Resilience as a Service (RaaS) innovation project and the network modelling undertaken to investigate the technical feasibility of implementing a Battery Energy Storage System (BESS) scheme to improve the reliability and security of supply of customers in rural areas. The performance of the BESS scheme is assessed under different network conditions. This will include a variety of network and BESS operational modes - such as grid connected BESS, islanded operation, incorporation of other downstream Distributed Generation (DG), and a temporary diesel generator – together with the transition between these modes. Practical BESS-based black start sequences will be considered with regard to feasibility transient studies and the impact on the network assets. In addition, the impact and synchronisation (reconnection to the main grid) sequences will be explored.","PeriodicalId":347664,"journal":{"name":"The 17th International Conference on AC and DC Power Transmission (ACDC 2021)","volume":"36 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"EVALUATION OF A FLEXIBLE SOLUTION, USING A BESS SCHEME TO SUPPLY 11KV DISTRIBUTION NETWORK IN ISLANDED MODE DURING DISTURBANCES\",\"authors\":\"D. Vozikis, A. Emhemed, S. Hynds, M. Filla, S. Rigby\",\"doi\":\"10.1049/icp.2021.2457\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper presents an overview of the Resilience as a Service (RaaS) innovation project and the network modelling undertaken to investigate the technical feasibility of implementing a Battery Energy Storage System (BESS) scheme to improve the reliability and security of supply of customers in rural areas. The performance of the BESS scheme is assessed under different network conditions. This will include a variety of network and BESS operational modes - such as grid connected BESS, islanded operation, incorporation of other downstream Distributed Generation (DG), and a temporary diesel generator – together with the transition between these modes. Practical BESS-based black start sequences will be considered with regard to feasibility transient studies and the impact on the network assets. In addition, the impact and synchronisation (reconnection to the main grid) sequences will be explored.\",\"PeriodicalId\":347664,\"journal\":{\"name\":\"The 17th International Conference on AC and DC Power Transmission (ACDC 2021)\",\"volume\":\"36 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"The 17th International Conference on AC and DC Power Transmission (ACDC 2021)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1049/icp.2021.2457\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"The 17th International Conference on AC and DC Power Transmission (ACDC 2021)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1049/icp.2021.2457","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
EVALUATION OF A FLEXIBLE SOLUTION, USING A BESS SCHEME TO SUPPLY 11KV DISTRIBUTION NETWORK IN ISLANDED MODE DURING DISTURBANCES
This paper presents an overview of the Resilience as a Service (RaaS) innovation project and the network modelling undertaken to investigate the technical feasibility of implementing a Battery Energy Storage System (BESS) scheme to improve the reliability and security of supply of customers in rural areas. The performance of the BESS scheme is assessed under different network conditions. This will include a variety of network and BESS operational modes - such as grid connected BESS, islanded operation, incorporation of other downstream Distributed Generation (DG), and a temporary diesel generator – together with the transition between these modes. Practical BESS-based black start sequences will be considered with regard to feasibility transient studies and the impact on the network assets. In addition, the impact and synchronisation (reconnection to the main grid) sequences will be explored.