{"title":"建设项目规划阶段现金流量预测算法","authors":"Min Ock Kim, Hyung-Keun Park","doi":"10.1109/ICMIT.2012.6225887","DOIUrl":null,"url":null,"abstract":"The study suggests an algorithm, which forecasts cash flow in a planning stage to manage a liquidity crisis effectively. The algorithm involves calculation of optimal cash level considering time lag, item costs, and weight of items for construction projects. It also suggests a forecast of cash flow after a comparison of cash-in and cash-out with the simulation of billing time lag according to the earned value and time lag of each item. Forecasts on cash flow, moreover, are made using various simulations on the component ratio of each item according to the budget. Therefore, this study aims to provide a solution to liquidity problems from insufficient cash and a good measure to forecast a proper level of cash flow.","PeriodicalId":292290,"journal":{"name":"2012 IEEE International Conference on Management of Innovation & Technology (ICMIT)","volume":"107 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2012-06-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":"{\"title\":\"The algorithm of cash flow forecasting in planning stage for construction project\",\"authors\":\"Min Ock Kim, Hyung-Keun Park\",\"doi\":\"10.1109/ICMIT.2012.6225887\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The study suggests an algorithm, which forecasts cash flow in a planning stage to manage a liquidity crisis effectively. The algorithm involves calculation of optimal cash level considering time lag, item costs, and weight of items for construction projects. It also suggests a forecast of cash flow after a comparison of cash-in and cash-out with the simulation of billing time lag according to the earned value and time lag of each item. Forecasts on cash flow, moreover, are made using various simulations on the component ratio of each item according to the budget. Therefore, this study aims to provide a solution to liquidity problems from insufficient cash and a good measure to forecast a proper level of cash flow.\",\"PeriodicalId\":292290,\"journal\":{\"name\":\"2012 IEEE International Conference on Management of Innovation & Technology (ICMIT)\",\"volume\":\"107 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2012-06-11\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"5\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2012 IEEE International Conference on Management of Innovation & Technology (ICMIT)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICMIT.2012.6225887\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2012 IEEE International Conference on Management of Innovation & Technology (ICMIT)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICMIT.2012.6225887","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

摘要

该研究提出了一种算法,该算法在计划阶段预测现金流量,以有效地管理流动性危机。该算法包括考虑时间滞后、项目成本和项目权重的最优现金水平的计算。并根据各项目的挣值和时滞,通过对比现金流入和现金流出,模拟计费时滞,预测现金流量。此外,根据预算对各项目的组成比例进行各种模拟,对现金流量进行预测。因此,本研究旨在为现金不足带来的流动性问题提供解决方案,并为预测适当的现金流量水平提供良好的措施。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
The algorithm of cash flow forecasting in planning stage for construction project
The study suggests an algorithm, which forecasts cash flow in a planning stage to manage a liquidity crisis effectively. The algorithm involves calculation of optimal cash level considering time lag, item costs, and weight of items for construction projects. It also suggests a forecast of cash flow after a comparison of cash-in and cash-out with the simulation of billing time lag according to the earned value and time lag of each item. Forecasts on cash flow, moreover, are made using various simulations on the component ratio of each item according to the budget. Therefore, this study aims to provide a solution to liquidity problems from insufficient cash and a good measure to forecast a proper level of cash flow.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信