改进直布罗陀建筑业施工管理实践

E. Daniel, D. Garcia, R. Marasini, Shaba Kolo, O. Oshodi
{"title":"改进直布罗陀建筑业施工管理实践","authors":"E. Daniel, D. Garcia, R. Marasini, Shaba Kolo, O. Oshodi","doi":"10.24928/2019/0227","DOIUrl":null,"url":null,"abstract":"Research has shown that 57% of activities in a construction project is non-value adding (waste) which contributes to the poor performance of the sector. While other countries of the world such the USA, UK, Brazil, Nigeria and Israel among others are seeking to understand this challenge and deploy innovative ways and modern techniques to improve it, limited studies have explored factors that contribute to non-value adding activities (NVA) in the Gibraltar construction industry. The current study aims to identify the factors that contribute to NVA on construction sites in Gibraltar and to present an outlook on how this could be minimised using Last Planner System(LPS). A combination of quantative and qualitative research approaches were used. Thirtyone questionnaire responses were analysed and seven semi-structured interviews were conducted. The investigation reveals that the development of unrealistic schedules, lack of adequate training, delayed approval process and work interruption due to the community are the key factors that contribute to NVA. The study found that the suggestions offered by construction professional for minimising NVA align with some LPS principles. The study concludes that some of the current practices, could serve as justification for the introduction of LPS in the construction sector of Gibraltar.","PeriodicalId":278113,"journal":{"name":"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)","volume":"154 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-07-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Improving Construction Management Practice in the Gibraltar Construction Industry\",\"authors\":\"E. Daniel, D. Garcia, R. Marasini, Shaba Kolo, O. Oshodi\",\"doi\":\"10.24928/2019/0227\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Research has shown that 57% of activities in a construction project is non-value adding (waste) which contributes to the poor performance of the sector. While other countries of the world such the USA, UK, Brazil, Nigeria and Israel among others are seeking to understand this challenge and deploy innovative ways and modern techniques to improve it, limited studies have explored factors that contribute to non-value adding activities (NVA) in the Gibraltar construction industry. The current study aims to identify the factors that contribute to NVA on construction sites in Gibraltar and to present an outlook on how this could be minimised using Last Planner System(LPS). A combination of quantative and qualitative research approaches were used. Thirtyone questionnaire responses were analysed and seven semi-structured interviews were conducted. The investigation reveals that the development of unrealistic schedules, lack of adequate training, delayed approval process and work interruption due to the community are the key factors that contribute to NVA. The study found that the suggestions offered by construction professional for minimising NVA align with some LPS principles. The study concludes that some of the current practices, could serve as justification for the introduction of LPS in the construction sector of Gibraltar.\",\"PeriodicalId\":278113,\"journal\":{\"name\":\"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)\",\"volume\":\"154 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-07-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.24928/2019/0227\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proc. 27th Annual Conference of the International Group for Lean Construction (IGLC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24928/2019/0227","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

研究表明,建筑项目中57%的活动是非增值的(浪费),这导致了该行业的糟糕表现。虽然世界上其他国家,如美国、英国、巴西、尼日利亚和以色列等正在努力了解这一挑战,并采用创新方法和现代技术来改善这一挑战,但有限的研究探索了导致直布罗陀建筑业非增值活动(NVA)的因素。当前的研究旨在确定导致直布罗陀建筑工地NVA的因素,并展望如何使用最后规划师系统(LPS)将其最小化。定量研究与定性研究相结合。分析了31份问卷,并进行了7次半结构化访谈。调查显示,制定不切实际的时间表、缺乏足够的培训、审批程序延迟以及社区造成的工作中断是导致NVA的关键因素。研究发现,建筑专业人员提供的最小化NVA的建议与LPS的一些原则相一致。该研究的结论是,目前的一些做法可以作为在直布罗陀建筑部门采用LPS的理由。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Improving Construction Management Practice in the Gibraltar Construction Industry
Research has shown that 57% of activities in a construction project is non-value adding (waste) which contributes to the poor performance of the sector. While other countries of the world such the USA, UK, Brazil, Nigeria and Israel among others are seeking to understand this challenge and deploy innovative ways and modern techniques to improve it, limited studies have explored factors that contribute to non-value adding activities (NVA) in the Gibraltar construction industry. The current study aims to identify the factors that contribute to NVA on construction sites in Gibraltar and to present an outlook on how this could be minimised using Last Planner System(LPS). A combination of quantative and qualitative research approaches were used. Thirtyone questionnaire responses were analysed and seven semi-structured interviews were conducted. The investigation reveals that the development of unrealistic schedules, lack of adequate training, delayed approval process and work interruption due to the community are the key factors that contribute to NVA. The study found that the suggestions offered by construction professional for minimising NVA align with some LPS principles. The study concludes that some of the current practices, could serve as justification for the introduction of LPS in the construction sector of Gibraltar.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信