{"title":"阿曼大型建设项目绩效分析:以石油和天然气行业选定项目为例","authors":"A. Saeedi, A. M. Karim","doi":"10.46545/aijbms.v2i2.247","DOIUrl":null,"url":null,"abstract":"This study investigates Omani O&G project’s performance and analyzes the most common time and cost overrun causes. In addition, the effects of delays are examined further along with the key enablers for efficient project delivery. This study adopts a mix method of research to improve the level of credibility of the study. A sample of 160 respondents is employed following both quantitative and qualitative method where a well-structured questionnaire was used for interviews with the concerned personnel. Following the quantitative method, this study revealed that 8% of the respondents, says the projects have completed ON time where the response rate was 80%. Besides, the qualitative part backed up this data as most of them have experienced delay of 3 months to 2 years of delay. For cost, 3% of the respondents have experienced projects finishing ON budget and the interviewees have expressed that the average cost overrun is between 10%-30%. In terms of time overrun group factors, the top group time-overrun factors among all the three parties are management factors, where it is ranked first by all stakeholders. The sub-group factor that affects more is the project planning and control. Poor understanding of scope of work during tendering factor is ranked first with main contractor and second with both the client and engineering firms. This factor is most factors that has similar ranking between all. As matter of fact is the only factor that exists between in the top 10 among all stakeholders. This study claimed that understanding the scope of work of the project properly and giving its time to be grasped by the contractors is one of the key solutions to tackle the top factor of this research. Also, the SOW must be detailed as possible to avoid any conflict between the parties, one of the recommended details to have WBS included.","PeriodicalId":202884,"journal":{"name":"American International Journal of Business and Management Studies","volume":"37 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-10-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Analyzing the Performance of Mega Construction Projects in Oman: A Study of Selected Projects from Oil & Gas Sector\",\"authors\":\"A. Saeedi, A. M. Karim\",\"doi\":\"10.46545/aijbms.v2i2.247\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This study investigates Omani O&G project’s performance and analyzes the most common time and cost overrun causes. In addition, the effects of delays are examined further along with the key enablers for efficient project delivery. This study adopts a mix method of research to improve the level of credibility of the study. A sample of 160 respondents is employed following both quantitative and qualitative method where a well-structured questionnaire was used for interviews with the concerned personnel. Following the quantitative method, this study revealed that 8% of the respondents, says the projects have completed ON time where the response rate was 80%. Besides, the qualitative part backed up this data as most of them have experienced delay of 3 months to 2 years of delay. For cost, 3% of the respondents have experienced projects finishing ON budget and the interviewees have expressed that the average cost overrun is between 10%-30%. In terms of time overrun group factors, the top group time-overrun factors among all the three parties are management factors, where it is ranked first by all stakeholders. The sub-group factor that affects more is the project planning and control. Poor understanding of scope of work during tendering factor is ranked first with main contractor and second with both the client and engineering firms. This factor is most factors that has similar ranking between all. As matter of fact is the only factor that exists between in the top 10 among all stakeholders. This study claimed that understanding the scope of work of the project properly and giving its time to be grasped by the contractors is one of the key solutions to tackle the top factor of this research. Also, the SOW must be detailed as possible to avoid any conflict between the parties, one of the recommended details to have WBS included.\",\"PeriodicalId\":202884,\"journal\":{\"name\":\"American International Journal of Business and Management Studies\",\"volume\":\"37 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2020-10-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"American International Journal of Business and Management Studies\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.46545/aijbms.v2i2.247\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"American International Journal of Business and Management Studies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.46545/aijbms.v2i2.247","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

本研究调查了阿曼油气项目的绩效,并分析了最常见的时间和成本超支原因。此外,将进一步检查延迟的影响以及有效项目交付的关键促成因素。本研究采用混合研究方法,以提高研究的可信度。采用定量和定性相结合的方法,抽样调查了160名回答者,并使用结构良好的问卷对有关人员进行了访谈。根据定量方法,本研究显示,8%的受访者表示项目按时完成,其中回复率为80%。此外,定性部分支持了这一数据,因为大多数人都经历了3个月至2年的延迟。在成本方面,3%的受访者经历过按预算完成项目,受访者表示平均成本超支在10%-30%之间。在时间超限组因素方面,三者中排名最高的组时间超限因素是管理因素,所有利益相关者都将其排在第一位。影响更大的子群体因素是项目计划和控制。在招标过程中,对工作范围的理解不足是主承包商的首要问题,其次是客户和工程公司的问题。这个因素是大多数因素之间具有相似排名的所有因素。事实上,这是所有利益相关者中唯一存在于前10名之间的因素。本研究认为,正确理解项目的工作范围,并给予承包商掌握的时间是解决本研究首要因素的关键解决方案之一。此外,工作状况必须尽可能详细,以避免各方之间的任何冲突,这是建议包括WBS的细节之一。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Analyzing the Performance of Mega Construction Projects in Oman: A Study of Selected Projects from Oil & Gas Sector
This study investigates Omani O&G project’s performance and analyzes the most common time and cost overrun causes. In addition, the effects of delays are examined further along with the key enablers for efficient project delivery. This study adopts a mix method of research to improve the level of credibility of the study. A sample of 160 respondents is employed following both quantitative and qualitative method where a well-structured questionnaire was used for interviews with the concerned personnel. Following the quantitative method, this study revealed that 8% of the respondents, says the projects have completed ON time where the response rate was 80%. Besides, the qualitative part backed up this data as most of them have experienced delay of 3 months to 2 years of delay. For cost, 3% of the respondents have experienced projects finishing ON budget and the interviewees have expressed that the average cost overrun is between 10%-30%. In terms of time overrun group factors, the top group time-overrun factors among all the three parties are management factors, where it is ranked first by all stakeholders. The sub-group factor that affects more is the project planning and control. Poor understanding of scope of work during tendering factor is ranked first with main contractor and second with both the client and engineering firms. This factor is most factors that has similar ranking between all. As matter of fact is the only factor that exists between in the top 10 among all stakeholders. This study claimed that understanding the scope of work of the project properly and giving its time to be grasped by the contractors is one of the key solutions to tackle the top factor of this research. Also, the SOW must be detailed as possible to avoid any conflict between the parties, one of the recommended details to have WBS included.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信