{"title":"网络分析崩溃法在海军基地设施建设项目进度评估中的应用","authors":"Raditya Novianto, S. Suparno, S. Sutrisno, Abdul Rahman","doi":"10.37875/asro.v12i01.392","DOIUrl":null,"url":null,"abstract":"A project of base facility is a kind of routine developing in Indonesian Naval. In this developmentt is necessary to develop methods in measuring performance and evaluating project time through a more accurate critical path feature. The research problem statement is how to evaluate the project schedule related to the time and cost of the Indonesian Navy's facility construction project by conducting a case study as a study for project scheduling at a later stage. The research objective is to identify the critical path of the project through network analysis, determine the factors that cause delays and how to overcome them, and calculate the time effectiveness and cost-efficiency of the project based on the calculation of scheduling acceleration. In this study, project performance measurement was carried out using the Earned Value Method (EVM) and network analysis using the Precedence Diagram Method (PDM). The solution to overcome delays with the crashing project method. The results of the discussion identified 15 critical path activities. The factor causing the delay is the delay in activities on the critical path due to the low level of productivity of the workforce group. The crashing method through additional 2 hours/day overtime can solve the problem of delays so that project implementation can be accelerated from the implementation of 256 working days to 226 working days (11.72% effectiveness) with the initial project cost of Rp. 74,316,727,585.00 reduced to Rp. 72,152,162,704.00 (2.91% efficiency). It will be measurable and reasonable in responsibility when it was suitable with the target. \n  \nKeywords : Network Analysis, Naval Base, and Project Development.","PeriodicalId":356564,"journal":{"name":"JOURNAL ASRO","volume":"10 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-01-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"APPLICATION OF NETWORK ANALYSIS CRASHING METHOD IN EVALUATING THE SCHEDULE OF NAVAL BASE FACILITY DEVELOPMENT PROJECT\",\"authors\":\"Raditya Novianto, S. Suparno, S. Sutrisno, Abdul Rahman\",\"doi\":\"10.37875/asro.v12i01.392\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A project of base facility is a kind of routine developing in Indonesian Naval. In this developmentt is necessary to develop methods in measuring performance and evaluating project time through a more accurate critical path feature. The research problem statement is how to evaluate the project schedule related to the time and cost of the Indonesian Navy's facility construction project by conducting a case study as a study for project scheduling at a later stage. The research objective is to identify the critical path of the project through network analysis, determine the factors that cause delays and how to overcome them, and calculate the time effectiveness and cost-efficiency of the project based on the calculation of scheduling acceleration. In this study, project performance measurement was carried out using the Earned Value Method (EVM) and network analysis using the Precedence Diagram Method (PDM). The solution to overcome delays with the crashing project method. The results of the discussion identified 15 critical path activities. The factor causing the delay is the delay in activities on the critical path due to the low level of productivity of the workforce group. The crashing method through additional 2 hours/day overtime can solve the problem of delays so that project implementation can be accelerated from the implementation of 256 working days to 226 working days (11.72% effectiveness) with the initial project cost of Rp. 74,316,727,585.00 reduced to Rp. 72,152,162,704.00 (2.91% efficiency). It will be measurable and reasonable in responsibility when it was suitable with the target. \\n  \\nKeywords : Network Analysis, Naval Base, and Project Development.\",\"PeriodicalId\":356564,\"journal\":{\"name\":\"JOURNAL ASRO\",\"volume\":\"10 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-01-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"JOURNAL ASRO\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.37875/asro.v12i01.392\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"JOURNAL ASRO","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.37875/asro.v12i01.392","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

基地设施建设项目是印尼海军的一种常规发展项目。在这种发展中,有必要通过更准确的关键路径特征来开发测量性能和评估项目时间的方法。研究问题陈述是如何通过案例研究来评估印尼海军设施建设项目的时间和成本相关的项目进度,作为后期项目进度的研究。研究目标是通过网络分析确定项目的关键路径,确定造成延误的因素以及如何克服这些因素,并在调度加速度计算的基础上计算项目的时间效益和成本效益。本研究采用挣值法(EVM)进行项目绩效评估,采用优先图法(PDM)进行网络分析。用崩溃项目法克服延迟的解决方案。讨论的结果确定了15个关键路径活动。造成延迟的因素是关键路径上的活动的延迟,这是由于劳动力群体的低生产力水平造成的。通过每天额外加班2小时的崩溃方式,可以解决延迟问题,使项目实施从256个工作日加快到226个工作日(11.72%的效率),项目初始成本从74,316,727,585.00卢比降低到72,152,162,704.00卢比(2.91%的效率)。当它与目标相适应时,它将是可衡量的和合理的责任。关键词:网络分析,海军基地,项目开发。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
APPLICATION OF NETWORK ANALYSIS CRASHING METHOD IN EVALUATING THE SCHEDULE OF NAVAL BASE FACILITY DEVELOPMENT PROJECT
A project of base facility is a kind of routine developing in Indonesian Naval. In this developmentt is necessary to develop methods in measuring performance and evaluating project time through a more accurate critical path feature. The research problem statement is how to evaluate the project schedule related to the time and cost of the Indonesian Navy's facility construction project by conducting a case study as a study for project scheduling at a later stage. The research objective is to identify the critical path of the project through network analysis, determine the factors that cause delays and how to overcome them, and calculate the time effectiveness and cost-efficiency of the project based on the calculation of scheduling acceleration. In this study, project performance measurement was carried out using the Earned Value Method (EVM) and network analysis using the Precedence Diagram Method (PDM). The solution to overcome delays with the crashing project method. The results of the discussion identified 15 critical path activities. The factor causing the delay is the delay in activities on the critical path due to the low level of productivity of the workforce group. The crashing method through additional 2 hours/day overtime can solve the problem of delays so that project implementation can be accelerated from the implementation of 256 working days to 226 working days (11.72% effectiveness) with the initial project cost of Rp. 74,316,727,585.00 reduced to Rp. 72,152,162,704.00 (2.91% efficiency). It will be measurable and reasonable in responsibility when it was suitable with the target.   Keywords : Network Analysis, Naval Base, and Project Development.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信