{"title":"Calibrating Software Cost Models to Department of Defense DatabasesA Review of Ten Studies","authors":"D. Ferens, D. Christensen","doi":"10.1080/10157891.1998.10462570","DOIUrl":null,"url":null,"abstract":"Abstract There are many sophisticated parametric models for estimating the size, cost, and schedule of software projects. In general, the predictive accuracy of these models is no better than within 25 percent of actual cost or schedule, about one half of the time (Thibodeau, 1981; IIT Research Institute, 1988). Several authors assert that a model's predictive accuracy can be improved by calibrating (adjusting) its default parameters to a specific environment (Kemerer, 1987; Van Genuchten and Koolen, 1991; Andolfi et al. 1996). This paper reports the results of a long-term project that tests this assertion.","PeriodicalId":54757,"journal":{"name":"Journal of Universal Computer Science","volume":"29 1","pages":""},"PeriodicalIF":0.7000,"publicationDate":"1998-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"38","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Universal Computer Science","FirstCategoryId":"94","ListUrlMain":"https://doi.org/10.1080/10157891.1998.10462570","RegionNum":4,"RegionCategory":"计算机科学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"COMPUTER SCIENCE, SOFTWARE ENGINEERING","Score":null,"Total":0}
引用次数: 38
Abstract
Abstract There are many sophisticated parametric models for estimating the size, cost, and schedule of software projects. In general, the predictive accuracy of these models is no better than within 25 percent of actual cost or schedule, about one half of the time (Thibodeau, 1981; IIT Research Institute, 1988). Several authors assert that a model's predictive accuracy can be improved by calibrating (adjusting) its default parameters to a specific environment (Kemerer, 1987; Van Genuchten and Koolen, 1991; Andolfi et al. 1996). This paper reports the results of a long-term project that tests this assertion.
有许多复杂的参数模型用于估算软件项目的规模、成本和进度。一般来说,这些模型的预测精度不超过实际成本或进度的25%,约占时间的一半(Thibodeau, 1981;印度理工学院研究所,1988年)。一些作者断言,模型的预测精度可以通过校准(调整)其默认参数来提高特定环境(Kemerer, 1987;Van Genuchten and Koolen, 1991;Andolfi et al. 1996)。本文报告了对这一断言进行检验的一个长期项目的结果。
期刊介绍:
J.UCS - The Journal of Universal Computer Science - is a high-quality electronic publication that deals with all aspects of computer science. J.UCS has been appearing monthly since 1995 and is thus one of the oldest electronic journals with uninterrupted publication since its foundation.