Capacity and Perfomance Evaluation of Drainage Channel (Case Study on Letjen Sutoyo Street Malang City)

Medi Efendi, Ayisya Cindy Harifa, S. Sutikno
{"title":"Capacity and Perfomance Evaluation of Drainage Channel (Case Study on Letjen Sutoyo Street Malang City)","authors":"Medi Efendi, Ayisya Cindy Harifa, S. Sutikno","doi":"10.33366/rekabuana.v7i1.2807","DOIUrl":null,"url":null,"abstract":"The channel along Jalan Letjen Sutoyo is a drainage channel that drains dirty water from the residential area of 0.65 km2. By evaluating the capacity and flow profile using the Storm Water Management Model (SWMM), it is hoped that flooding problems in the channel can be minimized. The capacity of the existing canal along Jalan Letjen Sutoyo is to accommodate a discharge of 13.62 to 29.09 m3/s so that we get the dimensions of a trapezoidal channel with a base width of 2.8 m with a height of 2.3 m at the beginning of the channel and becomes more extensive, namely a base width of 4 m with a height of 3.7 m. Enough capacity to accommodate a discharge of 29.09 m3/s. After the evaluation, it was found that there was accumulation at two points, namely J2 and J5, due to the maximum discharge added to the discharge from local settlements at that point. So it is necessary to redesign the channel to accommodate the discharge from the settlement. The redesign was only carried out by increasing the height of the channel to 5 m because increasing the width of the channel was not possible because the channel is in a densely populated area.ABSTRAKSaluran di sepanjang Jalan Letjen Sutoyo merupakan saluran drainase yang mengalirkan debit air kotor dari daerah Kawasan permukiman seluas 0,65 km2. Dengan membuat evaluasi pada kapasitas dan profil aliran dengan menggunakan Storm Water Management Model (SWMM) diharapkan permasalahan banjir pada saluran tersebut dapat diminimalisir.  Kapasitas saluran eksisting sepanjang Jalan Letjen Sutoyo adalah untuk menampung debit 13,62 hingga 29,09 m3/dt. Sehingga didapatkan dimensi berupa saluran trapesium dengan lebar dasar 2,8 m dengan ketinggian 2,3 m di awal saluran dan menjadi lebih besar yaitu lebar dasar 4 m dengan ketinggian 3.7 m. Kapasitas yang cukup untuk menampung debit sebesar 29,09 m3/dt. Setelah di evaluasi maka ditemukan adanya penumpukan pada dua titik yaitu J2 dan J5, akibat debit maksimum ditambahkan dengan debit yang berasal dari pemukiman setempat pada titik tersebut. Sehingga perlu adanya redesain saluran agar dapat menampung debit dari pemukiman. Redesain hanya dilakukan dengan penambahan ketinggian saluran menjadi 5 m, karena untuk penambahan lebar saluran tidak memungkinkan, karena saluran berada di wilayah padat pemukiman. ","PeriodicalId":20973,"journal":{"name":"Reka Buana : Jurnal Ilmiah Teknik Sipil dan Teknik Kimia","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2022-03-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Reka Buana : Jurnal Ilmiah Teknik Sipil dan Teknik Kimia","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.33366/rekabuana.v7i1.2807","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The channel along Jalan Letjen Sutoyo is a drainage channel that drains dirty water from the residential area of 0.65 km2. By evaluating the capacity and flow profile using the Storm Water Management Model (SWMM), it is hoped that flooding problems in the channel can be minimized. The capacity of the existing canal along Jalan Letjen Sutoyo is to accommodate a discharge of 13.62 to 29.09 m3/s so that we get the dimensions of a trapezoidal channel with a base width of 2.8 m with a height of 2.3 m at the beginning of the channel and becomes more extensive, namely a base width of 4 m with a height of 3.7 m. Enough capacity to accommodate a discharge of 29.09 m3/s. After the evaluation, it was found that there was accumulation at two points, namely J2 and J5, due to the maximum discharge added to the discharge from local settlements at that point. So it is necessary to redesign the channel to accommodate the discharge from the settlement. The redesign was only carried out by increasing the height of the channel to 5 m because increasing the width of the channel was not possible because the channel is in a densely populated area.ABSTRAKSaluran di sepanjang Jalan Letjen Sutoyo merupakan saluran drainase yang mengalirkan debit air kotor dari daerah Kawasan permukiman seluas 0,65 km2. Dengan membuat evaluasi pada kapasitas dan profil aliran dengan menggunakan Storm Water Management Model (SWMM) diharapkan permasalahan banjir pada saluran tersebut dapat diminimalisir.  Kapasitas saluran eksisting sepanjang Jalan Letjen Sutoyo adalah untuk menampung debit 13,62 hingga 29,09 m3/dt. Sehingga didapatkan dimensi berupa saluran trapesium dengan lebar dasar 2,8 m dengan ketinggian 2,3 m di awal saluran dan menjadi lebih besar yaitu lebar dasar 4 m dengan ketinggian 3.7 m. Kapasitas yang cukup untuk menampung debit sebesar 29,09 m3/dt. Setelah di evaluasi maka ditemukan adanya penumpukan pada dua titik yaitu J2 dan J5, akibat debit maksimum ditambahkan dengan debit yang berasal dari pemukiman setempat pada titik tersebut. Sehingga perlu adanya redesain saluran agar dapat menampung debit dari pemukiman. Redesain hanya dilakukan dengan penambahan ketinggian saluran menjadi 5 m, karena untuk penambahan lebar saluran tidak memungkinkan, karena saluran berada di wilayah padat pemukiman. 
排水通道容量与性能评价(以玛琅市Letjen Sutoyo街道为例)
沿着Jalan Letjen Sutoyo的河道是一条排水通道,从0.65平方公里的住宅区排出污水。通过使用暴雨水管理模型(SWMM)评估河道的容量和流量剖面,希望能最大限度地减少河道的洪水问题。沿着Jalan Letjen Sutoyo的现有运河的容量是容纳13.62至29.09立方米/秒的流量,因此我们得到了一个梯形通道的尺寸,其基础宽度为2.8米,通道开始高度为2.3米,并且变得更宽,即基础宽度为4米,高度为3.7米。有足够的容量容纳29.09立方米/秒的流量。评价后发现,在J2和J5两个点存在积存,这是由于在该点局部沉降的流量上加了最大的流量。因此,有必要重新设计通道,以适应沉降的排放。重新设计只通过将通道的高度增加到5米来进行,因为通道位于人口稠密的地区,不可能增加通道的宽度。[摘要]川山干流区面积为0.65 km2。登安成员评价,孟古纳坎暴雨水管理模式(SWMM), diharapkan permasalahan banjir pada saluran,但水的最小化。Kapasitas saluran eksisting sepanjang Jalan Letjen Sutoyo adalah untuk的流量分别为13,62,29,09 m3/dt。sehinga didapatkan尺寸berupa saluran trapesium登干lebar dasar 2,8 m登干ketinggian 2,3 m迪瓦瓦saluran dan menjadi lebih besar yitu lebar dasar 4 m登干ketinggian 3.7 m。Kapasitas yang cuup untuk menamonsebesar 29,09 m3/dt。Setelah di evaluasi maka ditemukan adanya penumpukan pada dua titik yitu J2和J5, akibat借记maksimum ditambahkan dengan借记yang berasal dari pemukiman seppat pada titik tersebut。seingga perlu adanya redesain saluran agar dapat menamung debit dari pemukman。5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,5米,
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信