{"title":"Design of a priority-based load shed scheme and operation tests","authors":"M. Adamiak, M. Schiefen, G. Schauerman, B. Cable","doi":"10.1109/PCIC.2010.5666862","DOIUrl":null,"url":null,"abstract":"Many large industrials operate internal co-generation systems to provide a substantial portion of their own power as well as to use the resulting output heat as part of their industrial process. Depending on the amount of co-generation, on loss of connection to the main grid or instability of the grid, these industrials may have the option of supplying all internal electrical loads from the co-generation or rather, shed a portion of the load in order to maintain plant stability. In order to maintain and maximize plant operations during either an islanded condition, a severe (and dropping) underfrequency condition, or a prolonged under voltage condition, a load shed scheme needs to dynamically monitor the load-generation unbalance in the plant and, upon detecting or determining any of the above conditions, needs to quickly initiate shedding of the optimal amount of load — based on a user-determined priority schedule. Examples of an actual load shed test are shown and analyzed.","PeriodicalId":67291,"journal":{"name":"中国石油和化工(企业版)","volume":"1 1","pages":"1-6"},"PeriodicalIF":0.0000,"publicationDate":"2010-12-13","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"22","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"中国石油和化工(企业版)","FirstCategoryId":"1087","ListUrlMain":"https://doi.org/10.1109/PCIC.2010.5666862","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 22
Abstract
Many large industrials operate internal co-generation systems to provide a substantial portion of their own power as well as to use the resulting output heat as part of their industrial process. Depending on the amount of co-generation, on loss of connection to the main grid or instability of the grid, these industrials may have the option of supplying all internal electrical loads from the co-generation or rather, shed a portion of the load in order to maintain plant stability. In order to maintain and maximize plant operations during either an islanded condition, a severe (and dropping) underfrequency condition, or a prolonged under voltage condition, a load shed scheme needs to dynamically monitor the load-generation unbalance in the plant and, upon detecting or determining any of the above conditions, needs to quickly initiate shedding of the optimal amount of load — based on a user-determined priority schedule. Examples of an actual load shed test are shown and analyzed.