Tertiary Voltage Unbalance Compensation for 500kV Single Phase Autotransformer Banks

Lianxiang Tang, P. Zhao
{"title":"Tertiary Voltage Unbalance Compensation for 500kV Single Phase Autotransformer Banks","authors":"Lianxiang Tang, P. Zhao","doi":"10.1109/TDC.2018.8440349","DOIUrl":null,"url":null,"abstract":"In an ungrounded transformer tertiary system, most often the phase-to-ground voltages are slightly unbalanced. Therefore all equipment supplied by the tertiary must have extra insulation to withstand the expected phase-to-ground overvoltages that arise from such unbalance. However, in a recent 3 ⨯ 250MV A single phase transformer bank replacement project, it was found that the tertiary phase-to-ground overvoltages were abnormally high therefore the transformer bank could not be put back into service. After extensive investigation, it was found that the transformer interwinding capacitances and tertiary phase-to-ground capacitances were unbalanced, resulting in excessive unbalance in the tertiary phase-to-ground voltages, which was directly responsible for the overvoltage. A mitigation plan was developed. The plan was to modify the tertiary phase-to-ground capacitances in such a way that the voltage unbalance due to the asymmetry in the inter-winding capacitances cancels the voltage unbalance due to the asymmetry in the phase-to-ground capacitances. Based on theoretical derivation and EMTP simulation, two CVTs (Capacitive Voltage Transformer) were selected from the warehouse and installed on the transformer tertiary. The voltage unbalance was successfully mitigated and the transformer bank was put back into service. The mitigation methodology developed in the project achieved significant cost saving and will have great value in future project development.","PeriodicalId":6568,"journal":{"name":"2018 IEEE/PES Transmission and Distribution Conference and Exposition (T&D)","volume":"40 1","pages":"1-6"},"PeriodicalIF":0.0000,"publicationDate":"2018-04-16","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 IEEE/PES Transmission and Distribution Conference and Exposition (T&D)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/TDC.2018.8440349","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

In an ungrounded transformer tertiary system, most often the phase-to-ground voltages are slightly unbalanced. Therefore all equipment supplied by the tertiary must have extra insulation to withstand the expected phase-to-ground overvoltages that arise from such unbalance. However, in a recent 3 ⨯ 250MV A single phase transformer bank replacement project, it was found that the tertiary phase-to-ground overvoltages were abnormally high therefore the transformer bank could not be put back into service. After extensive investigation, it was found that the transformer interwinding capacitances and tertiary phase-to-ground capacitances were unbalanced, resulting in excessive unbalance in the tertiary phase-to-ground voltages, which was directly responsible for the overvoltage. A mitigation plan was developed. The plan was to modify the tertiary phase-to-ground capacitances in such a way that the voltage unbalance due to the asymmetry in the inter-winding capacitances cancels the voltage unbalance due to the asymmetry in the phase-to-ground capacitances. Based on theoretical derivation and EMTP simulation, two CVTs (Capacitive Voltage Transformer) were selected from the warehouse and installed on the transformer tertiary. The voltage unbalance was successfully mitigated and the transformer bank was put back into service. The mitigation methodology developed in the project achieved significant cost saving and will have great value in future project development.
500kV单相自耦组三次电压不平衡补偿
在不接地的变压器三级系统中,大多数情况下相地电压略不平衡。因此,所有由三级供电的设备必须有额外的绝缘,以承受由这种不平衡引起的相对地过电压。然而,在最近的3 250MV单相变压器组更换项目中,发现三相对地过电压异常高,因此变压器组无法重新投入使用。经广泛调查,发现变压器绕组间电容和三次相对地电容不平衡,导致三次相对地电压过度不平衡,直接导致过电压。制定了一项缓解计划。计划是修改第三相对地电容,使绕组间电容不对称引起的电压不平衡抵消相对地电容不对称引起的电压不平衡。在理论推导和EMTP仿真的基础上,从仓库中选择了2台电容式电压互感器,安装在三级变压器上。电压不平衡得到有效缓解,变压器组恢复正常运行。在项目中制定的缓解方法大大节省了成本,并将在今后的项目开发中具有重要价值。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信