Hibrah Hibrah, Sutrasno Kartohardjono, Mohammed Ali Berawi
{"title":"Rekayasa Nilai Kriteria Desain Fasilitas Produksi Gas Alam","authors":"Hibrah Hibrah, Sutrasno Kartohardjono, Mohammed Ali Berawi","doi":"10.33366/rekabuana.v6i2.2642","DOIUrl":null,"url":null,"abstract":"Natural gas is one of the primary hydrocarbon energies in Indonesia. The construction of natural gas production facilities is essential to accommodate domestic energy needs. These facilities include production, pipelines, and processing facilities in an integrated manner. This study used the hydrocarbon composition of Field-X with an average of 7.62% CO2 and 0.06% H2S. The alternative design uses a fixed platform (fixed platform), MOPU (Mobile Offshore Production Unit), and a Semi-Submersible platform. The design comparison criteria are capital expenditure (CapEx), net present value (NPV), internal rate of return (IRR), work completion time, safety risk, and flexibility of future facility development. Through the comparison method, it is found that Option A is the best option, which has a design criterion value of 57%, a higher NPV of $43,537,469.58 than the smallest NPV option, an IRR of 19%, and a payout time (POT) of 5 years. Option A uses a fixed platform with a pipeline to the north, the hydrocarbon separation process is carried out on an offshore platform, and the processing is carried out onshore. ABSTRAKGas alam merupakan salah satu energi hidrokarbon utama di Indonesia. Pembangunan fasilitas produksinya sangat penting untuk mengakomodasi kebutuhan energi dalam negeri. Fasilitas ini meliputi produksi, jalur pemipaan, dan fasilitas pengolahan hidrokarbon secara terintegrasi. Penelitian ini menggunakan komposisi hidrokarbon dari Lapangan-X dengan rata-rata CO2 7.62% dan H2S 0.06%. Alternatif desain menggunakan anjungan tetap (fix platform), MOPU (Mobile Offshore Production Unit), dan anjungan Semi-Submersible. Kriteria perbandingan desain adalah modal awal, nilai bersih saat ini (NPV), tingkat pengembalian internal (IRR), waktu penyelesaian pekerjaan, resiko keselamatan, dan flexibilitas pengembangan fasilitas kedepan. Melalui metode perbandingan yang dipadankan didapatkan Opsi A adalah opsi terbaik, yang memiliki nilai kriteria desain 57%, NPV lebih tinggi $43,537,469.58 dibanding opsi NPV terkecil, IRR 19% dan waktu pembayaran (payout time/POT) 5 tahun. Opsi A menggunakan anjungan tetap dengan jalur pemipaan ke arah Utara, proses separasi hidrokarbon dilakukan pada anjungan lepas pantai (offshore) dan pengolahannya dilakukan di darat (onshore). ","PeriodicalId":20973,"journal":{"name":"Reka Buana : Jurnal Ilmiah Teknik Sipil dan Teknik Kimia","volume":"50 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-10-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Reka Buana : Jurnal Ilmiah Teknik Sipil dan Teknik Kimia","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.33366/rekabuana.v6i2.2642","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Natural gas is one of the primary hydrocarbon energies in Indonesia. The construction of natural gas production facilities is essential to accommodate domestic energy needs. These facilities include production, pipelines, and processing facilities in an integrated manner. This study used the hydrocarbon composition of Field-X with an average of 7.62% CO2 and 0.06% H2S. The alternative design uses a fixed platform (fixed platform), MOPU (Mobile Offshore Production Unit), and a Semi-Submersible platform. The design comparison criteria are capital expenditure (CapEx), net present value (NPV), internal rate of return (IRR), work completion time, safety risk, and flexibility of future facility development. Through the comparison method, it is found that Option A is the best option, which has a design criterion value of 57%, a higher NPV of $43,537,469.58 than the smallest NPV option, an IRR of 19%, and a payout time (POT) of 5 years. Option A uses a fixed platform with a pipeline to the north, the hydrocarbon separation process is carried out on an offshore platform, and the processing is carried out onshore. ABSTRAKGas alam merupakan salah satu energi hidrokarbon utama di Indonesia. Pembangunan fasilitas produksinya sangat penting untuk mengakomodasi kebutuhan energi dalam negeri. Fasilitas ini meliputi produksi, jalur pemipaan, dan fasilitas pengolahan hidrokarbon secara terintegrasi. Penelitian ini menggunakan komposisi hidrokarbon dari Lapangan-X dengan rata-rata CO2 7.62% dan H2S 0.06%. Alternatif desain menggunakan anjungan tetap (fix platform), MOPU (Mobile Offshore Production Unit), dan anjungan Semi-Submersible. Kriteria perbandingan desain adalah modal awal, nilai bersih saat ini (NPV), tingkat pengembalian internal (IRR), waktu penyelesaian pekerjaan, resiko keselamatan, dan flexibilitas pengembangan fasilitas kedepan. Melalui metode perbandingan yang dipadankan didapatkan Opsi A adalah opsi terbaik, yang memiliki nilai kriteria desain 57%, NPV lebih tinggi $43,537,469.58 dibanding opsi NPV terkecil, IRR 19% dan waktu pembayaran (payout time/POT) 5 tahun. Opsi A menggunakan anjungan tetap dengan jalur pemipaan ke arah Utara, proses separasi hidrokarbon dilakukan pada anjungan lepas pantai (offshore) dan pengolahannya dilakukan di darat (onshore).
天然气是印尼主要的碳氢化合物能源之一。天然气生产设施的建设对于满足国内能源需求至关重要。这些设施包括一体化的生产、管道和加工设施。本次研究使用的是Field-X油田的油气成分,平均CO2含量为7.62%,H2S含量为0.06%。备选设计采用固定平台(fixed platform)、移动式海上生产单元(MOPU)和半潜式平台。设计比较标准是资本支出(CapEx)、净现值(NPV)、内部收益率(IRR)、工作完成时间、安全风险和未来设施开发的灵活性。通过比较方法发现,A选项为最佳选项,其设计准则值为57%,NPV为43,537,469.58美元,高于最小NPV选项,IRR为19%,支付时间(POT)为5年。方案A采用固定平台,北面有一条管道,油气分离过程在海上平台上进行,加工过程在陆上进行。【摘要】印尼天然气预警系统(gas alarm merupakan salah)。Pembangunan fasilitas producduksinya sangat penting untuk mengakomodasi kebutuhan energi dalam negeri。黄芪、黄芪、黄芪、黄芪、黄芪、黄芪、黄芪、黄芪、黄芪、黄芪等。Penelitian ini menggunakan komposisi hidrocarbon dari Lapangan-X dengan rata-rata CO2 7.62% H2S 0.06%备选设计蒙古那坎安军岗固定式钻井平台、移动式海上生产装置MOPU、安军岗半潜式钻井平台。标准:弹性与设计:adalah modal awal, nilai bersih saat ini (NPV), tingkat pengembalian internal (IRR), waktu penyelesaian pekerjaan, resiko keselamatan, danflexibilitas pengembangan和fasilitas kedepan。Melalui方法perbandingan yang dipadankan didapatkan Opsi A adalah Opsi terbaik, yang memililki nilai标准设计57%,NPV lebih tinggi $43,537,469.58 dialui Opsi NPV terkecil, IRR 19% dan waktu pembayaran(支付时间/POT) 5 tahun。Opsi A menggunakan anjungan tetap dengan jalur pemipaan ke arah Utara,处理separasi hidrokarbon dilakukan pada anjungan lepas pantai(海上)和pengolahannya dilakukan di darat(陆上)。