Analyzing the factors affecting construction project schedules amidst COVID-19 pandemic

Nikhitha Adepu, Sharareh Kermanshachi, Apurva Pamidimukkala, Karthikeyan Loganathan
{"title":"Analyzing the factors affecting construction project schedules amidst COVID-19 pandemic","authors":"Nikhitha Adepu,&nbsp;Sharareh Kermanshachi,&nbsp;Apurva Pamidimukkala,&nbsp;Karthikeyan Loganathan","doi":"10.1016/j.plas.2023.100100","DOIUrl":null,"url":null,"abstract":"<div><p>The global health crisis caused by the COVID-19 pandemic led to disruptions and challenges across many business sectors, including the construction industry. A serious ramification of the pandemic on the construction industry was an increase in the number of project schedule delays that affected a multitude of projects around the world. Although the current literature explores the factors that cause project schedule delays, little research is available on the impact of variables, such as the size of the industry, type of project, and category of the organization, on the delays. This study used a four-step approach to address this knowledge gap by performing a comprehensive literature search, developing a survey, distributing the survey online, and conducting a quantitative analysis of the responses. The study's findings revealed that the factors contributing to project schedule overruns during the pandemic were diverse and differed with the variables cited above. Distinct differences were observed in areas such as procurement of materials and changes in material specifications and prices. This research sheds light on the multifaceted nature of the variables that impacted construction project schedules during the COVID-19 pandemic and provides valuable insights for industry stakeholders as they seek to establish effective strategies that will minimize risks and enhance project delivery during future periods of crisis.</p></div>","PeriodicalId":101050,"journal":{"name":"Project Leadership and Society","volume":"4 ","pages":"Article 100100"},"PeriodicalIF":0.0000,"publicationDate":"2023-10-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Project Leadership and Society","FirstCategoryId":"1085","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S2666721523000212","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The global health crisis caused by the COVID-19 pandemic led to disruptions and challenges across many business sectors, including the construction industry. A serious ramification of the pandemic on the construction industry was an increase in the number of project schedule delays that affected a multitude of projects around the world. Although the current literature explores the factors that cause project schedule delays, little research is available on the impact of variables, such as the size of the industry, type of project, and category of the organization, on the delays. This study used a four-step approach to address this knowledge gap by performing a comprehensive literature search, developing a survey, distributing the survey online, and conducting a quantitative analysis of the responses. The study's findings revealed that the factors contributing to project schedule overruns during the pandemic were diverse and differed with the variables cited above. Distinct differences were observed in areas such as procurement of materials and changes in material specifications and prices. This research sheds light on the multifaceted nature of the variables that impacted construction project schedules during the COVID-19 pandemic and provides valuable insights for industry stakeholders as they seek to establish effective strategies that will minimize risks and enhance project delivery during future periods of crisis.

新冠肺炎疫情下影响建设项目进度的因素分析
2019冠状病毒病大流行引发的全球卫生危机给包括建筑业在内的许多商业部门带来了中断和挑战。疫情对建筑业造成的一个严重后果是,项目进度延误的数量增加,影响到世界各地的许多项目。虽然目前的文献探讨了导致项目进度延迟的因素,但很少有研究表明,诸如行业规模、项目类型和组织类别等变量对延迟的影响。本研究采用了四步方法来解决这一知识差距,即进行全面的文献检索,开展调查,在线分发调查,并对反馈进行定量分析。研究结果显示,大流行期间造成项目进度超支的因素多种多样,与上述变量不同。在诸如材料采购和材料规格和价格变化等方面观察到明显的差异。这项研究揭示了在2019冠状病毒病大流行期间影响建筑项目进度的变量的多面性,并为行业利益相关者寻求建立有效战略,以在未来危机期间将风险降至最低并提高项目交付率提供了宝贵的见解。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
6.70
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信