Refurbishment works in a hospital during normal operation.

GMS Krankenhaushygiene interdisziplinar Pub Date : 2011-01-01 Epub Date: 2011-12-15 DOI:10.3205/dgkh000168
Birgit Ross, Dorothea Hansen, Tim Lieske, Joschka Krude, Fuat Saner, Günter Marggraf, Andreas Paul, Heinz G Jakob, Walter Popp
{"title":"Refurbishment works in a hospital during normal operation.","authors":"Birgit Ross,&nbsp;Dorothea Hansen,&nbsp;Tim Lieske,&nbsp;Joschka Krude,&nbsp;Fuat Saner,&nbsp;Günter Marggraf,&nbsp;Andreas Paul,&nbsp;Heinz G Jakob,&nbsp;Walter Popp","doi":"10.3205/dgkh000168","DOIUrl":null,"url":null,"abstract":"<p><strong>Background: </strong>Construction and renovation work in hospitals pose risks of fungal airborne infections for immunosuppressed patients. If possible, reconstruction work will be postponed to periods without patient treatment. However, in many situations urgent damage demands immediate refurbishment works before the transferring of patients to other wards or closure of wards is possible. Reported here are infection control related measures and implemented procedures after two incidents of water damage which occurred on a surgical ward and an intensive care unit at the University hospital of Essen.</p><p><strong>Methods: </strong>Between January and April 2009 and between September and October 2009, respectively, concentration of air-borne particles and number of viable fungi were measured at two surgical wards and one ICU. Preventive Infection Control Measures included erection of protective walls and HEPA filtration of air from the renovation area.</p><p><strong>Results: </strong>During the renovation work on the surgical ward concentrations of moulds and particles ≥5 µm were significantly higher on the left side of the renovation area than on the right side (p=0.036 and p<0.001). Concentrations of particles ≥1 µm and particles ≥5 µm on both sides of the renovation area were significantly increased when compared with the control ward on the same floor but not when compared with the control ward on the other floor. Particles of all size were significantly elevated on the ICU during the renovation work. Aspergillus fumigatus could neither be cultured of the air of cardiac surgery intensive care unit nor of the intermediate care unit (control ward). During renovation works there was no nosocomial mould infection of patients treated on the two wards.</p><p><strong>Conclusion: </strong>Provided that the renovation area is tightly insulated from the areas of patient care on a ward, closure does not seem to be necessary during renovation works because variation of airborne fungi is similar to that of outdoor or control air. However a multidisciplinary team should be established. This team should perform risk assessment and determine necessary protective measures before starting any construction, renovation or maintenance work in health care settings.</p>","PeriodicalId":88496,"journal":{"name":"GMS Krankenhaushygiene interdisziplinar","volume":"6 1","pages":"Doc11"},"PeriodicalIF":0.0000,"publicationDate":"2011-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.3205/dgkh000168","citationCount":"5","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"GMS Krankenhaushygiene interdisziplinar","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.3205/dgkh000168","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"2011/12/15 0:00:00","PubModel":"Epub","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

Abstract

Background: Construction and renovation work in hospitals pose risks of fungal airborne infections for immunosuppressed patients. If possible, reconstruction work will be postponed to periods without patient treatment. However, in many situations urgent damage demands immediate refurbishment works before the transferring of patients to other wards or closure of wards is possible. Reported here are infection control related measures and implemented procedures after two incidents of water damage which occurred on a surgical ward and an intensive care unit at the University hospital of Essen.

Methods: Between January and April 2009 and between September and October 2009, respectively, concentration of air-borne particles and number of viable fungi were measured at two surgical wards and one ICU. Preventive Infection Control Measures included erection of protective walls and HEPA filtration of air from the renovation area.

Results: During the renovation work on the surgical ward concentrations of moulds and particles ≥5 µm were significantly higher on the left side of the renovation area than on the right side (p=0.036 and p<0.001). Concentrations of particles ≥1 µm and particles ≥5 µm on both sides of the renovation area were significantly increased when compared with the control ward on the same floor but not when compared with the control ward on the other floor. Particles of all size were significantly elevated on the ICU during the renovation work. Aspergillus fumigatus could neither be cultured of the air of cardiac surgery intensive care unit nor of the intermediate care unit (control ward). During renovation works there was no nosocomial mould infection of patients treated on the two wards.

Conclusion: Provided that the renovation area is tightly insulated from the areas of patient care on a ward, closure does not seem to be necessary during renovation works because variation of airborne fungi is similar to that of outdoor or control air. However a multidisciplinary team should be established. This team should perform risk assessment and determine necessary protective measures before starting any construction, renovation or maintenance work in health care settings.

Abstract Image

Abstract Image

Abstract Image

医院正常运作期间的翻新工作。
背景:医院的建筑和装修工作对免疫抑制患者存在空气传播真菌感染的风险。如果可能,重建工作将推迟到没有病人治疗的时期。然而,在许多情况下,紧急损坏需要在将患者转移到其他病房或关闭病房之前立即进行翻新工作。本文报告了发生在埃森大学医院外科病房和重症监护病房的两起水损害事件后的感染控制相关措施和实施程序。方法:2009年1 - 4月和2009年9 - 10月分别对2个外科病房和1个ICU的空气中颗粒物浓度和活菌数量进行测定。预防感染控制措施包括设置防护墙和对改造区空气进行高效微粒过滤。结果:外科病房装修过程中,改造区左侧霉菌浓度和≥5µm颗粒浓度明显高于右侧(p=0.036和p)。结论:如果改造区与病房病人护理区紧密隔离,装修过程中似乎不需要封闭,因为空气中真菌的变化与室外或对照空气相似。但是,应该建立一个多学科小组。该小组应在卫生保健机构开始任何建设、翻新或维护工作之前进行风险评估并确定必要的保护措施。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书