Deformation of underlying shield tunnel caused by adjacent excavation considering the consolidation effect

IF 8 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY
LinHai Lv , Shaokang Zhu , Cheng Dong , Zhonghui Huang , BingHua Wang , ShiZheng Qiu , MingJie Jiang , Liang Xiao , Guoxiong Mei
{"title":"Deformation of underlying shield tunnel caused by adjacent excavation considering the consolidation effect","authors":"LinHai Lv ,&nbsp;Shaokang Zhu ,&nbsp;Cheng Dong ,&nbsp;Zhonghui Huang ,&nbsp;BingHua Wang ,&nbsp;ShiZheng Qiu ,&nbsp;MingJie Jiang ,&nbsp;Liang Xiao ,&nbsp;Guoxiong Mei","doi":"10.1016/j.conbuildmat.2025.143841","DOIUrl":null,"url":null,"abstract":"<div><div>Excavation above existing tunnels induces vertical deformation due to unloading effects, with the underlying tunnel deformation exhibiting time-dependent behavior caused by soil consolidation. However, prevailing theoretical frameworks often neglect the consolidation process and the influence of the complete excavation sequence, resulting in an inability to predict time-evolving deformation. This study establishes a consolidation model tailored for foundation pit excavation, deriving a theoretical solution for excess pore water pressure. Vertical soil deformation induced by excavation is determined using the effective stress principle coupled with generalized Hooke's law. A consolidation model for internally loaded foundations is then formulated to obtain a flexibility matrix incorporating consolidation effects. By simplifying the tunnel as an Euler-Bernoulli beam and applying soil-tunnel displacement coupling conditions, a time-dependent solution for vertical deformation is derived and validated against physical model tests. Meanwhile, the results of data comparison further indicate that the time-dependent characteristics of the tunnel's vertical deformation are closely related to the dissipation of excess pore water pressure (i.e., the soil's consolidation characteristics). Parametric analysis shows that: Lowering the soil permeability coefficient reduces the tunnel’s deformation rate but also extends the time required for the deformation to stabilize, resulting in a smaller vertical displacement at the completion of excavation. An increase in the resilient modulus not only enhances the soil's ability to resist deformation but also weakens the soil's consolidation effect, thereby inhibiting the development of vertical displacement of the tunnel. The tunnel stiffness only affects the deformation magnitude, but not the time required to reach stability. Introducing an intermittent excavation schedule tends to increase the deformation of the tunnel by the end of excavation while attenuating the subsequent time-dependent deformation. The theory in this paper is of guiding significance for engineering practice.</div></div>","PeriodicalId":288,"journal":{"name":"Construction and Building Materials","volume":"497 ","pages":"Article 143841"},"PeriodicalIF":8.0000,"publicationDate":"2025-10-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Construction and Building Materials","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0950061825039923","RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 0

Abstract

Excavation above existing tunnels induces vertical deformation due to unloading effects, with the underlying tunnel deformation exhibiting time-dependent behavior caused by soil consolidation. However, prevailing theoretical frameworks often neglect the consolidation process and the influence of the complete excavation sequence, resulting in an inability to predict time-evolving deformation. This study establishes a consolidation model tailored for foundation pit excavation, deriving a theoretical solution for excess pore water pressure. Vertical soil deformation induced by excavation is determined using the effective stress principle coupled with generalized Hooke's law. A consolidation model for internally loaded foundations is then formulated to obtain a flexibility matrix incorporating consolidation effects. By simplifying the tunnel as an Euler-Bernoulli beam and applying soil-tunnel displacement coupling conditions, a time-dependent solution for vertical deformation is derived and validated against physical model tests. Meanwhile, the results of data comparison further indicate that the time-dependent characteristics of the tunnel's vertical deformation are closely related to the dissipation of excess pore water pressure (i.e., the soil's consolidation characteristics). Parametric analysis shows that: Lowering the soil permeability coefficient reduces the tunnel’s deformation rate but also extends the time required for the deformation to stabilize, resulting in a smaller vertical displacement at the completion of excavation. An increase in the resilient modulus not only enhances the soil's ability to resist deformation but also weakens the soil's consolidation effect, thereby inhibiting the development of vertical displacement of the tunnel. The tunnel stiffness only affects the deformation magnitude, but not the time required to reach stability. Introducing an intermittent excavation schedule tends to increase the deformation of the tunnel by the end of excavation while attenuating the subsequent time-dependent deformation. The theory in this paper is of guiding significance for engineering practice.
考虑固结效应的相邻开挖下伏盾构隧道变形分析
既有隧道上方开挖受卸荷作用引起竖向变形,下伏隧道变形受土体固结作用影响表现为随时间变化的变形特征。然而,现有的理论框架往往忽略了固结过程和完整开挖序列的影响,导致无法预测随时间变化的变形。建立了适合基坑开挖的固结模型,推导了超孔隙水压力的理论解。利用有效应力原理结合广义胡克定律确定开挖引起的土体竖向变形。然后建立了内部荷载基础的固结模型,得到了包含固结效应的柔度矩阵。通过将隧道简化为欧拉-伯努利梁,并应用土-隧道位移耦合条件,导出了垂直变形随时间的解,并通过物理模型试验进行了验证。同时,数据对比结果进一步表明,隧道竖向变形的时效特征与超孔隙水压力的耗散(即土体固结特性)密切相关。参数分析表明:土体渗透系数的降低降低了隧道的变形速率,但也延长了变形稳定所需的时间,使得开挖完成时的竖向位移较小。弹性模量的增加不仅增强了土体的抗变形能力,而且减弱了土体的固结作用,从而抑制了隧道竖向位移的发展。隧道刚度只影响变形大小,而不影响达到稳定所需的时间。引入间歇开挖方案往往会增加隧道开挖结束时的变形,同时减弱随后的随时间变化的变形。本文的理论对工程实践具有指导意义。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
Construction and Building Materials
Construction and Building Materials 工程技术-材料科学:综合
CiteScore
13.80
自引率
21.60%
发文量
3632
审稿时长
82 days
期刊介绍: Construction and Building Materials offers an international platform for sharing innovative and original research and development in the realm of construction and building materials, along with their practical applications in new projects and repair practices. The journal publishes a diverse array of pioneering research and application papers, detailing laboratory investigations and, to a limited extent, numerical analyses or reports on full-scale projects. Multi-part papers are discouraged. Additionally, Construction and Building Materials features comprehensive case studies and insightful review articles that contribute to new insights in the field. Our focus is on papers related to construction materials, excluding those on structural engineering, geotechnics, and unbound highway layers. Covered materials and technologies encompass cement, concrete reinforcement, bricks and mortars, additives, corrosion technology, ceramics, timber, steel, polymers, glass fibers, recycled materials, bamboo, rammed earth, non-conventional building materials, bituminous materials, and applications in railway materials.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信