Deduction of the Bromilow's time-cost model from the fractal nature of activity networks

Alexei Vazquez
{"title":"Deduction of the Bromilow's time-cost model from the fractal nature of activity networks","authors":"Alexei Vazquez","doi":"arxiv-2409.00110","DOIUrl":null,"url":null,"abstract":"In 1969 Bromilow observed that the time $T$ to execute a construction project\nfollows a power law scaling with the project cost $C$, $T\\sim C^B$ [Bromilow\n1969]. While the Bromilow's time-cost model has been extensively tested using\ndata for different countries and project types, there is no theoretical\nexplanation for the algebraic scaling. Here I mathematically deduce the\nBromilow's time-cost model from the fractal nature of activity networks. The\nBromislow's exponent is $B=1-\\alpha$, where $1-\\alpha$ is the scaling exponent\nbetween the number of activities in the critical path $L$ and the number of\nactivities $N$, $L\\sim N^{1-\\alpha}$ with $0\\leq\\alpha<1$ [Vazquez et al 2023].\nI provide empirical data showing that projects with low serial/parallel (SP)%\nhave lower $B$ values than those with higher SP%. I conclude that the\nBromilow's time-cost model is a law of activity networks, the Bromilow's\nexponent is a network property and forecasting project duration from cost\nshould be limited to projects with high SP%.","PeriodicalId":501043,"journal":{"name":"arXiv - PHYS - Physics and Society","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2024-08-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"arXiv - PHYS - Physics and Society","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/arxiv-2409.00110","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

In 1969 Bromilow observed that the time $T$ to execute a construction project follows a power law scaling with the project cost $C$, $T\sim C^B$ [Bromilow 1969]. While the Bromilow's time-cost model has been extensively tested using data for different countries and project types, there is no theoretical explanation for the algebraic scaling. Here I mathematically deduce the Bromilow's time-cost model from the fractal nature of activity networks. The Bromislow's exponent is $B=1-\alpha$, where $1-\alpha$ is the scaling exponent between the number of activities in the critical path $L$ and the number of activities $N$, $L\sim N^{1-\alpha}$ with $0\leq\alpha<1$ [Vazquez et al 2023]. I provide empirical data showing that projects with low serial/parallel (SP)% have lower $B$ values than those with higher SP%. I conclude that the Bromilow's time-cost model is a law of activity networks, the Bromilow's exponent is a network property and forecasting project duration from cost should be limited to projects with high SP%.
从活动网络的分形性质推导出布罗米洛时间成本模型
1969 年,Bromilow 发现执行一个建筑项目的时间 $T$ 与项目成本 $C$ 成幂律关系,即 $T\sim C^B$ [Bromilow1969]。虽然 Bromilow 的时间成本模型已使用不同国家和项目类型的数据进行了广泛测试,但对于代数缩放并没有理论解释。在此,我从活动网络的分形性质出发,从数学上推导出布罗米洛时间成本模型。布罗米洛指数为 $B=1-\alpha$,其中 1-\alpha$ 是关键路径 $L 的活动数量与活动数量 $N 之间的比例指数,$L\sim N^{1-\alpha}$ 与 $0\leq\alpha<1$ [Vazquez et al 2023].我的结论是,布罗米洛时间成本模型是活动网络的定律,布罗米洛指数是网络属性,根据成本预测项目工期应仅限于高 SP% 的项目。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信