COST PERFORMANCE ANALYSIS USING EARNED VALUE METHOD ON PRESERVATION OF EXIT TOLL ROAD SECTION 5 PANDAAN MALANG

Amalia Fathimah Azh Zhahra Mughni, H. T. Tjendani, Budi Witjaksana
{"title":"COST PERFORMANCE ANALYSIS USING EARNED VALUE METHOD ON PRESERVATION OF EXIT TOLL ROAD SECTION 5 PANDAAN MALANG","authors":"Amalia Fathimah Azh Zhahra Mughni, H. T. Tjendani, Budi Witjaksana","doi":"10.55047/ijateis.v2i4.969","DOIUrl":null,"url":null,"abstract":"The development of road or toll road infrastructure in a country can be used as a benchmark to determine the level of economic progress of a country, both macro and micro. The location of toll exits has a significant effect in absorbing labor and creating new business activities. Projects are dynamic, so contractors must be responsive to changes in situations and conditions on the project, if they want to succeed in reaping optimum profits. Aspects of planning a highly competitive construction at this time are very demanding on accuracy, effectiveness, efficiency, and economy in analyzing a project. In the world of construction projects, there are many things that can be done, one of which is cost control. In controlling costs, efforts can be made so that the realization of costs that occur is in accordance with the needs of implementation and is not excessive, such as cost suppression efforts, namely making savings without reducing quantity or quality. The Earned Value Method is used to determine project performance in terms of costs at one time, determine project performance in terms of schedule/time at one time, estimate costs to complete the project after the evaluation time and estimate the time to complete the project after the evaluation. In this research the author carried out a cost analysis using the Earned Value Method on the preservation of the Section 5 Pandaan Malang Toll Exit Road.","PeriodicalId":475177,"journal":{"name":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","volume":"32 2","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY ENGINEERING AND INFORMATION SYSTEM (IJATEIS)","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.55047/ijateis.v2i4.969","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The development of road or toll road infrastructure in a country can be used as a benchmark to determine the level of economic progress of a country, both macro and micro. The location of toll exits has a significant effect in absorbing labor and creating new business activities. Projects are dynamic, so contractors must be responsive to changes in situations and conditions on the project, if they want to succeed in reaping optimum profits. Aspects of planning a highly competitive construction at this time are very demanding on accuracy, effectiveness, efficiency, and economy in analyzing a project. In the world of construction projects, there are many things that can be done, one of which is cost control. In controlling costs, efforts can be made so that the realization of costs that occur is in accordance with the needs of implementation and is not excessive, such as cost suppression efforts, namely making savings without reducing quantity or quality. The Earned Value Method is used to determine project performance in terms of costs at one time, determine project performance in terms of schedule/time at one time, estimate costs to complete the project after the evaluation time and estimate the time to complete the project after the evaluation. In this research the author carried out a cost analysis using the Earned Value Method on the preservation of the Section 5 Pandaan Malang Toll Exit Road.
采用挣值法对马兰出口收费公路第 5 段的养护进行成本绩效分析
一个国家的公路或收费公路基础设施的发展情况,可以作为确定一个国家宏观和微观经济进步水平的基准。收费出口的位置对吸纳劳动力和创造新的商业活动有着重要影响。项目是动态的,因此承包商要想成功获得最佳利润,就必须对项目情况和条件的变化做出反应。在这个竞争激烈的时代,建筑规划对项目分析的准确性、有效性、效率和经济性都有很高的要求。在建筑项目的世界里,有许多事情可以做,其中之一就是成本控制。在控制成本的过程中,可以努力使发生的成本的实现符合实施的需要,不至于过高,如努力抑制成本,即在不降低数量和质量的前提下节约成本。挣值法用于确定一次成本方面的项目绩效、确定一次进度/时间方面的项目绩效、估算评估时间后完成项目的成本以及估算评估后完成项目的时间。在本研究中,作者使用挣值法对 Pandaan Malang 收费出口公路第 5 段的保护工作进行了成本分析。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信